Analysis on the Problems in Start-up and Debugging of Two 600 MW Generating Units in Yangzhou No.2 Thermal Power Plant
1
作者 蒯狄正 《Electricity》 2001年第2期11-15,共5页
The problems including excessive flow of attemperating water for boiler, failure of butterfly valve at the outlet of circulating water pump, burnt-out of thyristor for excitation regulator, load variation rate of CCS ... The problems including excessive flow of attemperating water for boiler, failure of butterfly valve at the outlet of circulating water pump, burnt-out of thyristor for excitation regulator, load variation rate of CCS not complying with the contract target, etc. occurred during start-up and debugging of two 600 MW generating units in Yangzhou No.2 Thermal Power Plant. Through analysis on these problems. the remedial measures were put forward, to which can be referred for similar units. 展开更多
关键词 start-up and debugging problems analysis remedial measures 600 MW generating unit