In fossil energy pollution is serious and the“double carbon”goal is being promoted,as a symbol of fresh energy in the electrical system,solar and wind power have an increasing installed capacity,only conventional un...In fossil energy pollution is serious and the“double carbon”goal is being promoted,as a symbol of fresh energy in the electrical system,solar and wind power have an increasing installed capacity,only conventional units obviously can not solve the new energy as the main body of the scheduling problem.To enhance the systemscheduling ability,based on the participation of thermal power units,incorporate the high energy-carrying load of electro-melting magnesiuminto the regulation object,and consider the effects on the wind unpredictability of the power.Firstly,the operating characteristics of high energy load and wind power are analyzed,and the principle of the participation of electrofusedmagnesiumhigh energy-carrying loads in the elimination of obstructedwind power is studied.Second,a two-layer optimization model is suggested,with the objective function being the largest amount of wind power consumed and the lowest possible cost of system operation.In the upper model,the high energy-carrying load regulates the blocked wind power,and in the lower model,the second-order cone approximation algorithm is used to solve the optimizationmodelwithwind power uncertainty,so that a two-layer optimizationmodel that takes into account the regulation of the high energy-carrying load of the electrofused magnesium and the uncertainty of the wind power is established.Finally,the model is solved using Gurobi,and the results of the simulation demonstrate that the suggested model may successfully lower wind abandonment,lower system operation costs,increase the accuracy of day-ahead scheduling,and lower the final product error of the thermal electricity unit.展开更多
The anti-overturning ability and structure safety of jack-up unit in in-place condition are often affected by environment loads, especially wind load. According to the MODU rule, the projected area method is used for ...The anti-overturning ability and structure safety of jack-up unit in in-place condition are often affected by environment loads, especially wind load. According to the MODU rule, the projected area method is used for calculating the wind load. However, the calculated results are conservative and not good for structure optimization design. In this paper, a 400 ft jack-up is studied as an example. Based on the wind tunnel test and numerical simulation method, some key points of wind load calculation, such as shielding effect, lift effect and shape coefficient of component, are discussed. The study shows that the points mentioned above, which are ignored in the MODU rule calculation, result in the conservative result.展开更多
Northern China has rich wind power and photovoltaic renewable resources. Combined Heat and Power (CHP) Units to meet the load demand and limit its peaking capacity in winter, to a certain extent, it results in structu...Northern China has rich wind power and photovoltaic renewable resources. Combined Heat and Power (CHP) Units to meet the load demand and limit its peaking capacity in winter, to a certain extent, it results in structural problems of wind-solar power and thermoelectric. To solve these problems, this paper proposes a plurality of units together to ensure supply of heat load on the premise, by building a thermoelectric power peaking considering thermal load unit group dynamic scheduling model, to achieve the potential of different thermoelectric properties peaking units of the excavation. Simulation examples show, if the unit group exists obvious relationship thermoelectric individual differences, the thermal load dynamic scheduling can be more significantly improved overall performance peaking unit group, effectively increase clean energy consumptive.展开更多
As the steady-state frequency of an actual power system decreases from its nominal value,the composite load of the system generally responds positively to lower power consumption,and vice versa.It is believed that thi...As the steady-state frequency of an actual power system decreases from its nominal value,the composite load of the system generally responds positively to lower power consumption,and vice versa.It is believed that this load frequency damping(LFD)effect will be artificially enhanced,i.e.,sensitivities of loads with respect to operational frequency will increase,in future power systems.Thus,for wind-integrated power systems,this paper proposes a frequency-dependent chance constrained unit commitment(FDCCUC)model that employs the operational frequency as a dispatching variable so that the LFD effect-based load power can act as a supplemental reserve.Because the frequency deviation is safely restricted,this low-cost reserve can be sufficiently exerted to upgrade the wind power accommodation capability of a power system that is normally confined by an inadequate reserve to cope with uncertain wind power forecasting error.Moreover,when the FDCCUC model is applied to a bulk AC/DC hybrid power system consisting of several independently operated regional AC grids interconnected by DC tie-lines,a hierarchically implemented searching algorithm is proposed to protect private scheduling information of the regional AC grids.Simulations on a 2-area 6-bus system and a 3-area 354-bus system verify the effectiveness of the FDCCUC model and hierarchical searching algorithm.展开更多
基金funded by the National Key R&D Program of China,Grant Number 2019YFB1505400.
文摘In fossil energy pollution is serious and the“double carbon”goal is being promoted,as a symbol of fresh energy in the electrical system,solar and wind power have an increasing installed capacity,only conventional units obviously can not solve the new energy as the main body of the scheduling problem.To enhance the systemscheduling ability,based on the participation of thermal power units,incorporate the high energy-carrying load of electro-melting magnesiuminto the regulation object,and consider the effects on the wind unpredictability of the power.Firstly,the operating characteristics of high energy load and wind power are analyzed,and the principle of the participation of electrofusedmagnesiumhigh energy-carrying loads in the elimination of obstructedwind power is studied.Second,a two-layer optimization model is suggested,with the objective function being the largest amount of wind power consumed and the lowest possible cost of system operation.In the upper model,the high energy-carrying load regulates the blocked wind power,and in the lower model,the second-order cone approximation algorithm is used to solve the optimizationmodelwithwind power uncertainty,so that a two-layer optimizationmodel that takes into account the regulation of the high energy-carrying load of the electrofused magnesium and the uncertainty of the wind power is established.Finally,the model is solved using Gurobi,and the results of the simulation demonstrate that the suggested model may successfully lower wind abandonment,lower system operation costs,increase the accuracy of day-ahead scheduling,and lower the final product error of the thermal electricity unit.
基金supported by the National Natural Science Foundation of China(Grant No.51079034)the Fundamental Research Funds for the Central Universities(Grant No.HEUCFR1003)
文摘The anti-overturning ability and structure safety of jack-up unit in in-place condition are often affected by environment loads, especially wind load. According to the MODU rule, the projected area method is used for calculating the wind load. However, the calculated results are conservative and not good for structure optimization design. In this paper, a 400 ft jack-up is studied as an example. Based on the wind tunnel test and numerical simulation method, some key points of wind load calculation, such as shielding effect, lift effect and shape coefficient of component, are discussed. The study shows that the points mentioned above, which are ignored in the MODU rule calculation, result in the conservative result.
文摘Northern China has rich wind power and photovoltaic renewable resources. Combined Heat and Power (CHP) Units to meet the load demand and limit its peaking capacity in winter, to a certain extent, it results in structural problems of wind-solar power and thermoelectric. To solve these problems, this paper proposes a plurality of units together to ensure supply of heat load on the premise, by building a thermoelectric power peaking considering thermal load unit group dynamic scheduling model, to achieve the potential of different thermoelectric properties peaking units of the excavation. Simulation examples show, if the unit group exists obvious relationship thermoelectric individual differences, the thermal load dynamic scheduling can be more significantly improved overall performance peaking unit group, effectively increase clean energy consumptive.
基金supported by the National Natural Science Foundation of China(No.51777143)。
文摘As the steady-state frequency of an actual power system decreases from its nominal value,the composite load of the system generally responds positively to lower power consumption,and vice versa.It is believed that this load frequency damping(LFD)effect will be artificially enhanced,i.e.,sensitivities of loads with respect to operational frequency will increase,in future power systems.Thus,for wind-integrated power systems,this paper proposes a frequency-dependent chance constrained unit commitment(FDCCUC)model that employs the operational frequency as a dispatching variable so that the LFD effect-based load power can act as a supplemental reserve.Because the frequency deviation is safely restricted,this low-cost reserve can be sufficiently exerted to upgrade the wind power accommodation capability of a power system that is normally confined by an inadequate reserve to cope with uncertain wind power forecasting error.Moreover,when the FDCCUC model is applied to a bulk AC/DC hybrid power system consisting of several independently operated regional AC grids interconnected by DC tie-lines,a hierarchically implemented searching algorithm is proposed to protect private scheduling information of the regional AC grids.Simulations on a 2-area 6-bus system and a 3-area 354-bus system verify the effectiveness of the FDCCUC model and hierarchical searching algorithm.