SeveraL parameters affecting slag splashing in LD converter have been discussed. Using parffin and starch model, a simulated test about 30 t converter has been made in laboratory and the modified Frode numberwas chose...SeveraL parameters affecting slag splashing in LD converter have been discussed. Using parffin and starch model, a simulated test about 30 t converter has been made in laboratory and the modified Frode numberwas chosen as the main similar basis of the system. It was results that the optimized slag splashing parameters wasobtained through data treatment The nitrogen gas flow rate is about 8 500 m3/h, the splashing time is of 3 min,and the lance height is of 0.8 m. It is necessary to add MgO or carbon into the slag to adjusting slag composition.Also, it is difficult for the splashed slag condensing on the line when the slag temperature is much higher展开更多
Converter off-gas, an important energy resource for steel industries, is one of the weak points in the recov ery and utilization of secondary energy resources. To improve the level of recycling converter off-gas in st...Converter off-gas, an important energy resource for steel industries, is one of the weak points in the recov ery and utilization of secondary energy resources. To improve the level of recycling converter off-gas in steel plants, a novel approach to the recycle of CO2 separated from converter off-gas or other off-gas for the green slag splashing technique was developed, and the CO2 equilibrium conversion ratio of the green CO2 slag splashing under different technological conditions was calculated by the program of enthalpy (H), entropy (S), and heat capacity (C), i.e. HSC software. Furthermore, the experiments of CO2 injected into molten converter slag were carried out, and the influencing factors of the green slag splashing technique using CO2 were analyzed. The experimental results showed that the carbon content for smooth slag splashing using COs was about 4.0%.展开更多
文摘SeveraL parameters affecting slag splashing in LD converter have been discussed. Using parffin and starch model, a simulated test about 30 t converter has been made in laboratory and the modified Frode numberwas chosen as the main similar basis of the system. It was results that the optimized slag splashing parameters wasobtained through data treatment The nitrogen gas flow rate is about 8 500 m3/h, the splashing time is of 3 min,and the lance height is of 0.8 m. It is necessary to add MgO or carbon into the slag to adjusting slag composition.Also, it is difficult for the splashed slag condensing on the line when the slag temperature is much higher
基金Sponsored by Science and Technology Plan Projects of Tianjin of China(07ZCKFGX03800)Science and Technology Plan Projects for CAS Supporting Tianjin Construction of China(TJZX1-YW-09)
文摘Converter off-gas, an important energy resource for steel industries, is one of the weak points in the recov ery and utilization of secondary energy resources. To improve the level of recycling converter off-gas in steel plants, a novel approach to the recycle of CO2 separated from converter off-gas or other off-gas for the green slag splashing technique was developed, and the CO2 equilibrium conversion ratio of the green CO2 slag splashing under different technological conditions was calculated by the program of enthalpy (H), entropy (S), and heat capacity (C), i.e. HSC software. Furthermore, the experiments of CO2 injected into molten converter slag were carried out, and the influencing factors of the green slag splashing technique using CO2 were analyzed. The experimental results showed that the carbon content for smooth slag splashing using COs was about 4.0%.