A self-developed elasto-plastic finite element program was used to analyze the construction sequence of high rock slope's stabilization in a coal-coking plant, and the result was compared with that employing the u...A self-developed elasto-plastic finite element program was used to analyze the construction sequence of high rock slope's stabilization in a coal-coking plant, and the result was compared with that employing the ultimate equilibrium method. Based on the results of finite element analysis, the stress contour graphs and displacement vector graphs at different construction steps were obtained, and the behavior of the slope during stabilization construction process was analyzed quantitatively. Based on the analysis of safety factors of three different schemes of stabilization and two different construction schemes, the assessment of stability and bracing design of the construction process were performed. The results show that the original reinforcement design is improper; the stability of the rock slope is controlled by a developed structural plane, the stability factor after excavation is less than 1, and the free surface should be braced in time; for stability, the construction sequence should adopt that bracing follows excavation step by step up to down; the local slide occurred during the construction process agrees with the dangerous slide determined by the numerical analysis, which proves the validity and rationality of the adopted method.展开更多
Ground condition and construction (excavation and support) time and costs are the key factors in decision-making during planning and design phases of a tunnel project. An innovative methodology for probabilistic est...Ground condition and construction (excavation and support) time and costs are the key factors in decision-making during planning and design phases of a tunnel project. An innovative methodology for probabilistic estimation of ground condition and construction time and costs is proposed, which is an integration of the ground prediction approach based on Markov process, and the time and cost variance analysis based on Monte-Carlo (MC) simulation. The former provides the probabilistic description of ground classification along tunnel alignment according to the geological information revealed from geological profile and boreholes. The latter provides the probabilistic description of the expected construction time and costs for each operation according to the survey feedbacks from experts. Then an engineering application to Hamro tunnel is presented to demonstrate how the ground condition and the construction time and costs are estimated in a probabilistic way. In most items, in order to estimate the data needed for this methodology, a number of questionnaires are distributed among the tunneling experts and finally the mean values of the respondents are applied. These facilitate both the owners and the contractors to be aware of the risk that they should carry before construction, and are useful for both tendering and bidding.展开更多
基金Scientific and Technological Support and Guidance Plan Projects of Zhejiang Province(Grant No.2008C23019)
文摘A self-developed elasto-plastic finite element program was used to analyze the construction sequence of high rock slope's stabilization in a coal-coking plant, and the result was compared with that employing the ultimate equilibrium method. Based on the results of finite element analysis, the stress contour graphs and displacement vector graphs at different construction steps were obtained, and the behavior of the slope during stabilization construction process was analyzed quantitatively. Based on the analysis of safety factors of three different schemes of stabilization and two different construction schemes, the assessment of stability and bracing design of the construction process were performed. The results show that the original reinforcement design is improper; the stability of the rock slope is controlled by a developed structural plane, the stability factor after excavation is less than 1, and the free surface should be braced in time; for stability, the construction sequence should adopt that bracing follows excavation step by step up to down; the local slide occurred during the construction process agrees with the dangerous slide determined by the numerical analysis, which proves the validity and rationality of the adopted method.
文摘Ground condition and construction (excavation and support) time and costs are the key factors in decision-making during planning and design phases of a tunnel project. An innovative methodology for probabilistic estimation of ground condition and construction time and costs is proposed, which is an integration of the ground prediction approach based on Markov process, and the time and cost variance analysis based on Monte-Carlo (MC) simulation. The former provides the probabilistic description of ground classification along tunnel alignment according to the geological information revealed from geological profile and boreholes. The latter provides the probabilistic description of the expected construction time and costs for each operation according to the survey feedbacks from experts. Then an engineering application to Hamro tunnel is presented to demonstrate how the ground condition and the construction time and costs are estimated in a probabilistic way. In most items, in order to estimate the data needed for this methodology, a number of questionnaires are distributed among the tunneling experts and finally the mean values of the respondents are applied. These facilitate both the owners and the contractors to be aware of the risk that they should carry before construction, and are useful for both tendering and bidding.