梁辉水库隧洞引水工程出碴施工介绍
1
作者 王东华 《科技信息》 2009年第5期336-336,340,共2页
通过光面爆破技术在余姚市梁辉水库隧洞引水工程中的施工介绍,简述了在比较复杂的地质条件下,主要针对STB-8型梭式矿车的运行使用,能够大大提高出碴效率,并取得良好的应用效果。
关键词 隧洞引水工程 出碴方法 梭式矿车
下载PDF
梁辉水库隧洞引水工程出碴施工介绍
2
作者 王东华 《科技信息》 2009年第12期286-287,共2页
本文通过光面爆破技术在余姚市梁辉水库隧洞引水工程中的施工介绍,简述了在比较复杂的地质条件下,主要针对STB-8型梭式矿车的运行使用,能够大大提高出碴效率,并取得良好的应用效果。
关键词 隧洞引水工程 出碴方法 梭式矿车
下载PDF
Optimal design for buckets layout based on muck removal analysis of TBM cutterhead 被引量:3
3
作者 YANG Mei XIA Yi-min +2 位作者 LIN Lai-kuang QIAO Shuo JI Zhi-yong 《Journal of Central South University》 SCIE EI CAS CSCD 2020年第6期1729-1741,共13页
The layout of the buckets for tunnel boring machine(TBM)directly affects the muck removal efficiency of cutterhead during excavation.In order to improve the muck removal performance for TBM,the optimal design of bucke... The layout of the buckets for tunnel boring machine(TBM)directly affects the muck removal efficiency of cutterhead during excavation.In order to improve the muck removal performance for TBM,the optimal design of bucket layout was investigated.The whole muck transfer process was simulated by discrete-element method(DEM),including the muck falling,colliding,pilling up,shoveling and transferring into the hopper.The muck model was established based on size distribution analysis of muck samples from the water-supply tunnel project in Jilin Province,China.Then,the influence of the bucket number and the interval angle between buckets on muck removal performance was investigated.The results indicated that,as the number of buckets increased from four to eight,the removed muck increased by 29%and the residual volume decreased by 40.5%,and the process became steadier.Different interval angles between buckets were corresponding to different removed muck irregularly,but the residual muck number increased generally with the angles.The optimal layout of buckets for the cutterhead in this tunnel project was obtained based on the simulation results,and the muck removal performance of the TBM was verified by the actual data in the engineering construction. 展开更多
关键词 optimal design buckets layout discrete element method muck removal performance tunnel boring machine