大方发电厂场平防护工程施工
1
作者 樊胜 张健 《贵州电力技术》 2004年第9期37-38,共2页
贵州大方发电厂的厂址位于大方县新铺村,厂址区域的地质条件复杂,场地地形起伏大,场平施工挖填方量较大,根据西南设计院的设计在厂区西北侧边坡最大填土厚度达28m,在厂区东侧最大填土厚度达27m,所以对厂址区域的边坡处理是整个场... 贵州大方发电厂的厂址位于大方县新铺村,厂址区域的地质条件复杂,场地地形起伏大,场平施工挖填方量较大,根据西南设计院的设计在厂区西北侧边坡最大填土厚度达28m,在厂区东侧最大填土厚度达27m,所以对厂址区域的边坡处理是整个场平工程重中之重,也是大方发电厂厂区稳定的重要保证。 展开更多
关键词 大方发电厂 场平防护工程 施工 抗滑稳定性 重力式挡墙 边坡处理
下载PDF
Application of Digital Image Correlation and Geodetic Displacement Measuring Methods to Monitor Water Dam Behavior under Dynamic Load
2
作者 Janina Zaczek-Peplinska Maria Elzbieta Kowalska +1 位作者 Krzysztof Malowany MarcinMalesa 《Journal of Civil Engineering and Architecture》 2015年第12期1496-1505,共10页
This paper presents experiment results of the measurement conducted at the Roznew Dam power plant. For a course of starting and operating of turbo-plants, downstream face of the dam was monitored in relation to its ev... This paper presents experiment results of the measurement conducted at the Roznew Dam power plant. For a course of starting and operating of turbo-plants, downstream face of the dam was monitored in relation to its eventual displacements on direction parallel to the construction axis. For the purpose of the experiment, geodetic measurement techniques and 2D DIC (digital image correlation) method (utilizing photographs of the object recorded with digital camera) were compared with regard to credibility, efficiency and accuracy. The vertical and horizontal displacements were monitored by tachometers measurements. The deformations in x-axis and y-axis on the wall surface was monitored by 2D DIC. It has been noticed that 2D DIC method is a surface method, continuous--not discreet. It allows for continuous observations of surface deformations, which is not possible in case of tachemetric measurements. Despite many advantages, the 2D DIC method lacks unambiguous evaluation of precision and relevance of designated displacements, which is rather significant for possibilities of utilization in technical control of large engineered objects. It should be also marked that the tachometric method is more reliable but is more laborious. Research of this type might comprise additional element for the assessment of the influence of dynamic loads, such as activating turbine water flow, onto the overall condition of the surveyed structure. 展开更多
关键词 Hydrotechnical structure structure dynamic load engineering object displacement geodetic displacement measurements.digital image correlation.
下载PDF