In the context of a room-and-pillar mining gob in Shanxi province in China,this paper numerically investigates the stress distribution and deformation rules of roadway surrounding rocks at various locations of residua...In the context of a room-and-pillar mining gob in Shanxi province in China,this paper numerically investigates the stress distribution and deformation rules of roadway surrounding rocks at various locations of residual coal pillars in room-and-pillar mining gobs using software FLAC3 D.It is found that the concentrated stress beneath coal pillars distributes in a shape of ellipse.A reasonable roadway layout is then proposed.In this design,it is indicated that roadways should be designed to avoid the supporting zones of pillars with increasing compression and take into account the roof falling and crushing in the upper gob.According to the surrounding rock deformation characteristics and mining roadway locations as well as the supporting principles of timely support,rock reinforcing,piecewise management and suiting local conditions,a new asymmetric shield supporting plan is proposed.The field surveying results show that this supporting plan can effectively control the roadway rock deformation,thus guarantee the safe and smooth construction of roadways.展开更多
Coal seams in Tashan Mine of Datong Coal Group in China average 15 m thick and have been mined by the top coal caving longwall mining method of large mining height. Mining height was 3.8 m and the top coal caving heig...Coal seams in Tashan Mine of Datong Coal Group in China average 15 m thick and have been mined by the top coal caving longwall mining method of large mining height. Mining height was 3.8 m and the top coal caving height was 11.2 m. The gateroad pillar between panels was 38 m. During retreat mining,serious bumps occurred in the gateroads on both sides of the pillar affecting safety production. Therefore,pillarless mining was experimented. Using numerical modeling and comparative study of cases of similar mining condition,it was decided to employ a 6 m wide pillar,rather than the previous 38 m wide pillar.Support system for the gateroads was designed and implemented. During gateroad development,pillar failure conditions and entry deformation were monitored. Hydraulic fracturing method was employed to cut off the K3 sandstone along the entry rib so as to reduce the abutment pressure induced during retreat mining. Support reinforcement method combining grouting and advanced reinforcement methods was proposed to insure stable gateroad ahead of mining. Methane drainage and nitrogen injection were implemented to eliminate hazards associated with mine fire and spontaneous combustion. Since the development of gateroad has just completed,and retreat mining has not begun,the effectiveness of the proposed methods is unknown at this point. However,monitoring will continue until after mining.The results will be published in a separate paper.展开更多
Gateway supporting in long wall mining has been a problem that restricts the mine production and safety, the paper sets up an interaction model between support and surrounding rock (rock mass structure) and probes the...Gateway supporting in long wall mining has been a problem that restricts the mine production and safety, the paper sets up an interaction model between support and surrounding rock (rock mass structure) and probes the elementary theory about ground pressure behaviors of gateway. Based on the analysis of supporting theories, some new viewpoints about gateways supporting and ground pressure controlling are put forward.展开更多
基金the National 973 Programs of China (No.2014CB046905)the National Natural Science Foundation of China(Nos.51274191 and 51404245)the Doctoral Fund of Ministry of Education(No.20130095110018)
文摘In the context of a room-and-pillar mining gob in Shanxi province in China,this paper numerically investigates the stress distribution and deformation rules of roadway surrounding rocks at various locations of residual coal pillars in room-and-pillar mining gobs using software FLAC3 D.It is found that the concentrated stress beneath coal pillars distributes in a shape of ellipse.A reasonable roadway layout is then proposed.In this design,it is indicated that roadways should be designed to avoid the supporting zones of pillars with increasing compression and take into account the roof falling and crushing in the upper gob.According to the surrounding rock deformation characteristics and mining roadway locations as well as the supporting principles of timely support,rock reinforcing,piecewise management and suiting local conditions,a new asymmetric shield supporting plan is proposed.The field surveying results show that this supporting plan can effectively control the roadway rock deformation,thus guarantee the safe and smooth construction of roadways.
基金funded by the United Foundation key project fund,Chinese Natural Science Committee (No.U1261207)Datong Coal Group,Tashan Coal Mine,and supported by the Natural Science Foundation of Ningbo of China (No.U1261207)
文摘Coal seams in Tashan Mine of Datong Coal Group in China average 15 m thick and have been mined by the top coal caving longwall mining method of large mining height. Mining height was 3.8 m and the top coal caving height was 11.2 m. The gateroad pillar between panels was 38 m. During retreat mining,serious bumps occurred in the gateroads on both sides of the pillar affecting safety production. Therefore,pillarless mining was experimented. Using numerical modeling and comparative study of cases of similar mining condition,it was decided to employ a 6 m wide pillar,rather than the previous 38 m wide pillar.Support system for the gateroads was designed and implemented. During gateroad development,pillar failure conditions and entry deformation were monitored. Hydraulic fracturing method was employed to cut off the K3 sandstone along the entry rib so as to reduce the abutment pressure induced during retreat mining. Support reinforcement method combining grouting and advanced reinforcement methods was proposed to insure stable gateroad ahead of mining. Methane drainage and nitrogen injection were implemented to eliminate hazards associated with mine fire and spontaneous combustion. Since the development of gateroad has just completed,and retreat mining has not begun,the effectiveness of the proposed methods is unknown at this point. However,monitoring will continue until after mining.The results will be published in a separate paper.
文摘Gateway supporting in long wall mining has been a problem that restricts the mine production and safety, the paper sets up an interaction model between support and surrounding rock (rock mass structure) and probes the elementary theory about ground pressure behaviors of gateway. Based on the analysis of supporting theories, some new viewpoints about gateways supporting and ground pressure controlling are put forward.