不同盾径造成的施工成本差异对盾构机项目投资决策的影响分析 被引量:5
1
作者 王文准 《工程造价管理》 2020年第5期63-67,共5页
由于施工相同衬砌外径的隧道时,可选择的盾构机型号外径会有所不同,而外径不同的盾构施工时会造成同步注浆和即时注浆等辅助工程,以及土方开挖外运等其他工程的工程量不同,文章选取最常见的几种用于城市轨道交通工程中隧道工程施工的盾... 由于施工相同衬砌外径的隧道时,可选择的盾构机型号外径会有所不同,而外径不同的盾构施工时会造成同步注浆和即时注浆等辅助工程,以及土方开挖外运等其他工程的工程量不同,文章选取最常见的几种用于城市轨道交通工程中隧道工程施工的盾构机,计算因盾径不同,在施工相同衬砌外径的隧道时,产生的这些工程量的差异量,并进一步结合具体时期的工料机价格和相应施工条件,计算出相应的成本价格指标后,利用计算所得的价格指标计算出这些工程量差异量造成的施工成本的变化量。再采用现金流贴现的方法,结合相关施工企业的净资产收益率,分析在盾构机全寿命周期内,这种因盾径差异而产生的施工成本变化量,对盾构机项目全寿命周期内内总收益的影响。文章最终给出受影响的收益对应的理论价值公式,为盾构机的生产、购置和租赁等需要进行投资决策时,在经济比选方面,提供相应的理论依据。 展开更多
关键词 盾构 现金流量 贴现率 施工成本 投资决策 盾径
下载PDF
Energy saving analysis of segment positioning in shield tunneling machine considering assembling path optimization 被引量:4
2
作者 施虎 龚国芳 +1 位作者 杨华勇 梅雪松 《Journal of Central South University》 SCIE EI CAS 2014年第12期4526-4536,共11页
A motion parameter optimization method based on the objective of minimizing the total energy consumption in segment positioning was proposed for segment erector of shield tunneling machine. The segment positioning pro... A motion parameter optimization method based on the objective of minimizing the total energy consumption in segment positioning was proposed for segment erector of shield tunneling machine. The segment positioning process was decomposed into rotation, lifting and sliding actions in deriving the energy calculation model of segment erection. The work of gravity was taken into account in the mathematical modeling of energy consumed by each actuator. In order to investigate the relationship between the work done by the actuator and the path moved along by the segment, the upward and downward directions as well as the operating quadrant of the segment erector were defined. Piecewise nonlinear function of energy was presented, of which the result is determined by closely coupled components as working parameters and some intermediate variables. Finally, the effectiveness of the optimization method was proved by conducting a case study with a segment erector for the tunnel with a diameter of 3 m and drawing comparisons between different assembling paths. The results show that the energy required by assembling a ring of segments along the optimized moving path can be reduced up to 5%. The method proposed in this work definitely provides an effective energy saving solution for shield tunneling machine. 展开更多
关键词 energy saving segment erector work of gravity path optimization shield tunneling machine
下载PDF