With the increase of axle load and the train speed, dynamic interaction of train-track system becomes so exacerbated that the deformation and dynamic response of subgrade are more aggravated. The differential settleme...With the increase of axle load and the train speed, dynamic interaction of train-track system becomes so exacerbated that the deformation and dynamic response of subgrade are more aggravated. The differential settlement will be created in bridge-embankment transition section under such dynamic action, and an adverse effect on the train operation safety can be caused. Meanwhile, differential settlement will produce additional dynamic effect when high-speed trains go through the transition between bridge-embankment. Such dynamic action will aggravate the differential settlement and subgrade damage. This paper applies the methods of field test and finite-element to systematically study the dynamic response characteristics of subgrade in bridge-embankment transition section of heavy haul railway under dynamic load for the first time. This research is focused on the analysis of influence of the different axle load, train speed, filled soil modulus, etc.. At last, the dynamic response rules are systematically summarized.展开更多
This paper presents a method to determine the safety threshold of bridge pier settlement in high-speed railways.An analytical expression of the mapping relationship between the pier settlement and the rail deformation...This paper presents a method to determine the safety threshold of bridge pier settlement in high-speed railways.An analytical expression of the mapping relationship between the pier settlement and the rail deformation is derived theoretically for the double block ballastless track-bridge system.By adopting the superposition of the track random irregularity and the rail deformation caused by the pier settlement as the excitation inputs,the variations of vehicle dynamics indices with pier settlement are comparatively analyzed.Then,the safety threshold of the bridge pier settlement is obtained according to the limit of vehicle running safety and ride comfort indices of the high-speed trains.Results show that the dynamics indices of different trains have different sensitivities to the pier settlement,and the train CRH2C is the most sensitive one among all the types of Chinese high-speed trains.When passing through the bridges in common span with pier settlement at the speed of 250–350 km/h,the trains suffer the low-frequency excitations,and the vertical acceleration of car body is most sensitive to the pier settlement of all the dynamics indices.When the car body vertical acceleration just exceeds the allowable limit,the critical settlement value is 23.4 mm,which is much bigger than the pier differential settlement limit in the current code for Chinese high-speed railways.展开更多
文摘With the increase of axle load and the train speed, dynamic interaction of train-track system becomes so exacerbated that the deformation and dynamic response of subgrade are more aggravated. The differential settlement will be created in bridge-embankment transition section under such dynamic action, and an adverse effect on the train operation safety can be caused. Meanwhile, differential settlement will produce additional dynamic effect when high-speed trains go through the transition between bridge-embankment. Such dynamic action will aggravate the differential settlement and subgrade damage. This paper applies the methods of field test and finite-element to systematically study the dynamic response characteristics of subgrade in bridge-embankment transition section of heavy haul railway under dynamic load for the first time. This research is focused on the analysis of influence of the different axle load, train speed, filled soil modulus, etc.. At last, the dynamic response rules are systematically summarized.
基金supported by the National Basic Research Program of China("973"Program)(Grant Nos.2013CB036206 and 2013CB036205)the National Natural Science Foundation of China(Grant No.50838006)+1 种基金the Research Project of State Key Laboratory of Traction Power(Grant No.2014TPL_T01)the 2015 Doctors’Innovation Fund of Southwest Jiaotong University
文摘This paper presents a method to determine the safety threshold of bridge pier settlement in high-speed railways.An analytical expression of the mapping relationship between the pier settlement and the rail deformation is derived theoretically for the double block ballastless track-bridge system.By adopting the superposition of the track random irregularity and the rail deformation caused by the pier settlement as the excitation inputs,the variations of vehicle dynamics indices with pier settlement are comparatively analyzed.Then,the safety threshold of the bridge pier settlement is obtained according to the limit of vehicle running safety and ride comfort indices of the high-speed trains.Results show that the dynamics indices of different trains have different sensitivities to the pier settlement,and the train CRH2C is the most sensitive one among all the types of Chinese high-speed trains.When passing through the bridges in common span with pier settlement at the speed of 250–350 km/h,the trains suffer the low-frequency excitations,and the vertical acceleration of car body is most sensitive to the pier settlement of all the dynamics indices.When the car body vertical acceleration just exceeds the allowable limit,the critical settlement value is 23.4 mm,which is much bigger than the pier differential settlement limit in the current code for Chinese high-speed railways.