The site drilling packer permeability test and TEM to the 2100 workface in Gucheng coalmine determined the two-zone height under sublevel strip mining.The conclusion considers that the lying strata deterioration law o...The site drilling packer permeability test and TEM to the 2100 workface in Gucheng coalmine determined the two-zone height under sublevel strip mining.The conclusion considers that the lying strata deterioration law of the strip mining is similar to that of the sublevel mining.Thus, against that the actually measured data lacked, it is feasible to refer to the reservation of the waterproof coal pillar in the neighbor coalmine under sublevel situation.However, it is necessary to further launch the research on lying strata deterioration law under sublevel striping mining for the purpose of providing the right foundation for the layout of the workface not mined so far and the reservation of the waterproof coal pillar in the mining area.展开更多
Coal mining under thin bedrock or thick unconsolidated soil layers brings mining problems related to these special geological conditions. The meaning of the term ''thin bedrock'' is defined through the...Coal mining under thin bedrock or thick unconsolidated soil layers brings mining problems related to these special geological conditions. The meaning of the term ''thin bedrock'' is defined through the thick- ness statistics of the coal seam and the bedrock layer. The coal-bearing strata having thick, unconsoli- dated aquifers and thin bedrock located at the Taiping Coal Mine in Shandong province were taken as a geological prototype for subsequent study. The geological, hydro-geological and engineering character- istics of the thin bedrock were analyzed. An engineering geological model was than established. Overbur- den failure and the development of ''Three Zones'' were studied by physical model tests. The rupture pattern and rock failure were analyzed for mining conditions under thin bedrock. The height of the caving zone and the freely flowing water fractured zone of different mining thicknesses were separately calcu- lated. The results show that a mining thickness greater than 3.5 m causes the height of the freely flowing water fractured zone to be sufficient to touch the weathered zone and the bottom of the Quaternary sys- tem aquifer, to various degrees. This, then, would lead to water and sand inrush into the working face. Measures to prevent water and sand flow inrush disasters by eliminating the power source are put fore- word. A field dewatering scheme was designed and observational data were obtained. The dewatering project had an obvious effect and the water level at working face number 8309 dropped to a safe level. The average draw down of the groundwater was observed to be 7.86 m. This showed that the dewatering project played a role in decreasing the hydraulic pressure and ensuring safety mining.展开更多
This paper focuses on the village coal pillar under huge thick loose bed and thin bedrock over high prelatic water level at the north of the Yellow River. The strip mining technology was used to protect the village ho...This paper focuses on the village coal pillar under huge thick loose bed and thin bedrock over high prelatic water level at the north of the Yellow River. The strip mining technology was used to protect the village houses. The stratum structure control action of mining subsidence was used to design the mining and pillar width. To further raise resources recovery, we adopted the mutative scheme of mining and pillar width. Observation was carried out while mining. Research shows there is feasibility of the strip mining technology to protecting the village buildings of the village coal pillar under huge thick loose bed and thin bedrock over high prelatic water level at the north of the Yellow River. Finally, subsidence parameters of strip mining were obtained. It is the basic data of the strip mining of the coal field at the north of the Yellow River.展开更多
基金Supported by Fujian Administration of Education for Science Research (JB08232)the State Key Development Program for Basic Research of China(2006CB202200)
文摘The site drilling packer permeability test and TEM to the 2100 workface in Gucheng coalmine determined the two-zone height under sublevel strip mining.The conclusion considers that the lying strata deterioration law of the strip mining is similar to that of the sublevel mining.Thus, against that the actually measured data lacked, it is feasible to refer to the reservation of the waterproof coal pillar in the neighbor coalmine under sublevel situation.However, it is necessary to further launch the research on lying strata deterioration law under sublevel striping mining for the purpose of providing the right foundation for the layout of the workface not mined so far and the reservation of the waterproof coal pillar in the mining area.
基金provided by the National Natural Science Foundation of China (No.40802076)the China Postdoctoral Science Foundation (No.20110491476)
文摘Coal mining under thin bedrock or thick unconsolidated soil layers brings mining problems related to these special geological conditions. The meaning of the term ''thin bedrock'' is defined through the thick- ness statistics of the coal seam and the bedrock layer. The coal-bearing strata having thick, unconsoli- dated aquifers and thin bedrock located at the Taiping Coal Mine in Shandong province were taken as a geological prototype for subsequent study. The geological, hydro-geological and engineering character- istics of the thin bedrock were analyzed. An engineering geological model was than established. Overbur- den failure and the development of ''Three Zones'' were studied by physical model tests. The rupture pattern and rock failure were analyzed for mining conditions under thin bedrock. The height of the caving zone and the freely flowing water fractured zone of different mining thicknesses were separately calcu- lated. The results show that a mining thickness greater than 3.5 m causes the height of the freely flowing water fractured zone to be sufficient to touch the weathered zone and the bottom of the Quaternary sys- tem aquifer, to various degrees. This, then, would lead to water and sand inrush into the working face. Measures to prevent water and sand flow inrush disasters by eliminating the power source are put fore- word. A field dewatering scheme was designed and observational data were obtained. The dewatering project had an obvious effect and the water level at working face number 8309 dropped to a safe level. The average draw down of the groundwater was observed to be 7.86 m. This showed that the dewatering project played a role in decreasing the hydraulic pressure and ensuring safety mining.
文摘This paper focuses on the village coal pillar under huge thick loose bed and thin bedrock over high prelatic water level at the north of the Yellow River. The strip mining technology was used to protect the village houses. The stratum structure control action of mining subsidence was used to design the mining and pillar width. To further raise resources recovery, we adopted the mutative scheme of mining and pillar width. Observation was carried out while mining. Research shows there is feasibility of the strip mining technology to protecting the village buildings of the village coal pillar under huge thick loose bed and thin bedrock over high prelatic water level at the north of the Yellow River. Finally, subsidence parameters of strip mining were obtained. It is the basic data of the strip mining of the coal field at the north of the Yellow River.