Thermal simulation tests were conducted at different deformation temperatures and degrees by a Gleeble simulator.The results show that the alloy has higher resistance to deformation;with an increase of the deformation...Thermal simulation tests were conducted at different deformation temperatures and degrees by a Gleeble simulator.The results show that the alloy has higher resistance to deformation;with an increase of the deformation temperature,the alloy’s flow stress and maximum value decrease;with an increase of the deformation degree,both the initial recrystallization temperature and the complete recrystallization temperature decrease sharply.When the deformation degree reaches 30%,60% and 80%,the initial recrystallization temperature is around 950℃,850℃ and 800℃,the complete recrystallization temperature is around 1 100℃,1 050℃ and 1 000℃ respectively.When the deformation temperature is higher than 1100℃,the deformation degree increases and the re-crystalized grains are significantly refined.The forging process parameters were established according to the regular pattern mentioned above.The microstructure of the bar forged in this pattern is uniform and the result is satisfying.展开更多
为满足500 k V武—察输变电工程系统调试需要,文中利用PSCAD电磁暂态仿真软件,在系统调试方式、正常运行方式及检修方式下对500 k V武—察输变电工程系统启动过程中工频过电压、控制电压、潜供电流与恢复电压进行计算分析,以便为工程实...为满足500 k V武—察输变电工程系统调试需要,文中利用PSCAD电磁暂态仿真软件,在系统调试方式、正常运行方式及检修方式下对500 k V武—察输变电工程系统启动过程中工频过电压、控制电压、潜供电流与恢复电压进行计算分析,以便为工程实施提供理论依据,为运行提供参考。展开更多
雷击是影响±500 k V直流架空输电线路运行的重要因素,±500 k V直流线路避雷器的挂网试运行成功,为直流线路防雷改造提供了有效技术手段,但大规模的工程应用仍是空白。笔者结合±500 k V江城线直流线路避雷器安装项目,研究...雷击是影响±500 k V直流架空输电线路运行的重要因素,±500 k V直流线路避雷器的挂网试运行成功,为直流线路防雷改造提供了有效技术手段,但大规模的工程应用仍是空白。笔者结合±500 k V江城线直流线路避雷器安装项目,研究了±500 k V直流线路避雷器选型、选点原则,给出了不同塔型下直流线路避雷器的安装方案,并提出直线塔宜采用悬挂式安装方案,耐张塔宜采用地面支柱式安装方案。运行数据表明,笔者提出的±500 k V直流线路避雷器选型、选点原则防雷改造效果明显,安装方案达到线路安全运行要求,对±500 k V直流线路避雷器的推广应用和在运直流线路防雷改造工作具有重要的实践和借鉴意义。展开更多
在500 k V线路的系统操作过电压超过相关规范规定要求时,必须对其采取限制措施以保证供电系统的安全可靠性。分析操作过电压的限制措施、氧化性避雷器电位分布,结合工程实例分析采取氧化性避雷器限制措施前后的过电压变化以及避雷器参...在500 k V线路的系统操作过电压超过相关规范规定要求时,必须对其采取限制措施以保证供电系统的安全可靠性。分析操作过电压的限制措施、氧化性避雷器电位分布,结合工程实例分析采取氧化性避雷器限制措施前后的过电压变化以及避雷器参数的取值;同时验证在不采取限制措施情况下输电线路绝缘设计是否满足要求。结果表明,这2种不同的操作过电压处理方式,均可作为解决操作过电压水平超过要求值时的解决方案。展开更多
大容量静止同步补偿器(STATCOM)对于增加受端负荷母线动态无功支撑、提高电压稳定性具有重要意义,但在输电线路补偿方面的应用尚少。介绍了南方电网±200 Mvar STATCOM成套设备首次应用于500 k V电压等级——500 k V水乡站,包括在...大容量静止同步补偿器(STATCOM)对于增加受端负荷母线动态无功支撑、提高电压稳定性具有重要意义,但在输电线路补偿方面的应用尚少。介绍了南方电网±200 Mvar STATCOM成套设备首次应用于500 k V电压等级——500 k V水乡站,包括在该工程的设计方案和技术特点、阀组功率单元、成套设备柜体布置以及控制保护系统工程中得以实现,最后对现场调试运行等情况进行分析说明,南网水乡站工程为大容量STATCOM在高压大功率输电领域的应用提供了经验借鉴。展开更多
随着输电网架规模的不断扩大,电网分区已经成为电网发展的必然趋势.介绍了500/220 k V电网的建设过程,强调了进行500/220 k V电网分区研究的必要性,并结合现有研究,将500/220 k V电网分区的研究方法归纳为启发式分区和整体式分区.最后,...随着输电网架规模的不断扩大,电网分区已经成为电网发展的必然趋势.介绍了500/220 k V电网的建设过程,强调了进行500/220 k V电网分区研究的必要性,并结合现有研究,将500/220 k V电网分区的研究方法归纳为启发式分区和整体式分区.最后,结合大电网的发展趋势,对分区研究进行了展望.展开更多
文摘Thermal simulation tests were conducted at different deformation temperatures and degrees by a Gleeble simulator.The results show that the alloy has higher resistance to deformation;with an increase of the deformation temperature,the alloy’s flow stress and maximum value decrease;with an increase of the deformation degree,both the initial recrystallization temperature and the complete recrystallization temperature decrease sharply.When the deformation degree reaches 30%,60% and 80%,the initial recrystallization temperature is around 950℃,850℃ and 800℃,the complete recrystallization temperature is around 1 100℃,1 050℃ and 1 000℃ respectively.When the deformation temperature is higher than 1100℃,the deformation degree increases and the re-crystalized grains are significantly refined.The forging process parameters were established according to the regular pattern mentioned above.The microstructure of the bar forged in this pattern is uniform and the result is satisfying.
文摘雷击是影响±500 k V直流架空输电线路运行的重要因素,±500 k V直流线路避雷器的挂网试运行成功,为直流线路防雷改造提供了有效技术手段,但大规模的工程应用仍是空白。笔者结合±500 k V江城线直流线路避雷器安装项目,研究了±500 k V直流线路避雷器选型、选点原则,给出了不同塔型下直流线路避雷器的安装方案,并提出直线塔宜采用悬挂式安装方案,耐张塔宜采用地面支柱式安装方案。运行数据表明,笔者提出的±500 k V直流线路避雷器选型、选点原则防雷改造效果明显,安装方案达到线路安全运行要求,对±500 k V直流线路避雷器的推广应用和在运直流线路防雷改造工作具有重要的实践和借鉴意义。
文摘在500 k V线路的系统操作过电压超过相关规范规定要求时,必须对其采取限制措施以保证供电系统的安全可靠性。分析操作过电压的限制措施、氧化性避雷器电位分布,结合工程实例分析采取氧化性避雷器限制措施前后的过电压变化以及避雷器参数的取值;同时验证在不采取限制措施情况下输电线路绝缘设计是否满足要求。结果表明,这2种不同的操作过电压处理方式,均可作为解决操作过电压水平超过要求值时的解决方案。
文摘大容量静止同步补偿器(STATCOM)对于增加受端负荷母线动态无功支撑、提高电压稳定性具有重要意义,但在输电线路补偿方面的应用尚少。介绍了南方电网±200 Mvar STATCOM成套设备首次应用于500 k V电压等级——500 k V水乡站,包括在该工程的设计方案和技术特点、阀组功率单元、成套设备柜体布置以及控制保护系统工程中得以实现,最后对现场调试运行等情况进行分析说明,南网水乡站工程为大容量STATCOM在高压大功率输电领域的应用提供了经验借鉴。
文摘随着输电网架规模的不断扩大,电网分区已经成为电网发展的必然趋势.介绍了500/220 k V电网的建设过程,强调了进行500/220 k V电网分区研究的必要性,并结合现有研究,将500/220 k V电网分区的研究方法归纳为启发式分区和整体式分区.最后,结合大电网的发展趋势,对分区研究进行了展望.