The dynamic finite element model (FEM) of a prestressed concrete continuous box-girder bridge, called the Tongyang Canal Bridge, is built and updated based on the results of ambient vibration testing (AVT) using a...The dynamic finite element model (FEM) of a prestressed concrete continuous box-girder bridge, called the Tongyang Canal Bridge, is built and updated based on the results of ambient vibration testing (AVT) using a real-coded accelerating genetic algorithm (RAGA). The objective functions are defined based on natural frequency and modal assurance criterion (MAC) metrics to evaluate the updated FEM. Two objective functions are defined to fully account for the relative errors and standard deviations of the natural frequencies and MAC between the AVT results and the updated FEM predictions. The dynamically updated FEM of the bridge can better represent its structural dynamics and serve as a baseline in long-term health monitoring, condition assessment and damage identification over the service life of the bridge .展开更多
The seismic analysis of a rigid-framed prestressed concrete bridge in Tianjin Light Railway is performed. A 3-D dynamic finite element model of the bridge is established considering the weakening effect caused by the ...The seismic analysis of a rigid-framed prestressed concrete bridge in Tianjin Light Railway is performed. A 3-D dynamic finite element model of the bridge is established considering the weakening effect caused by the soft soil foundation. After the dynamic characteristics are calculated in terms of natural frequencies and modes, the seismic analysis is carried out using the modal response spectrum method and the time-history method, respectively. Based on the calculated results, the reasonable design values are finally suggested as the basis of the seismic design of the bridge, and meanwhile the problems encountered were also analyzed. Finally, some conclusions are drawn as: 1) Despite the superiority of rigid-framed prestressed concrete bridge, the upper and lower ends of the piers of the bridge are proved to be the crucial parts of the bridge, which are easily destroyed under designed earthquake excitations and should be carefully analyzed and designed; 2) The soft soil foundation can possibly result in rather weakening of the lateral rigidity of the rigid-framed bridge, and should be paid considerable attention; 3) The modal response spectrum method, combined with time-history method, is suggested for the seismic analysis in engineering design of the rigid-framed prestressed concrete bridge.展开更多
To accurately evaluate the degradation process of prestressed concrete continuous bridges exposed to aggressive environments in life-cycle,a finite element-based approach with respect to the lifetime performance asses...To accurately evaluate the degradation process of prestressed concrete continuous bridges exposed to aggressive environments in life-cycle,a finite element-based approach with respect to the lifetime performance assessment of concrete bridges was proposed.The existing assessment methods were firstly introduced and compared.Some essential mechanics problems involved in the degradation process,such as the deterioration of materials properties,the reduction of sectional areas and the variation of overall structural performance caused by the first two problems,were investigated and solved.A computer program named CBDAS(Concrete Bridge Durability Analysis System) was written to perform the above-metioned approach.Finally,the degradation process of a prestressed concrete continuous bridge under chloride penetration was discussed.The results show that the concrete normal stress for serviceability limit state exceeds the threshold value after 60 a,but the various performance indicators at ultimate limit state are consistently in the allowable level during service life.Therefore,in the case of prestressed concrete bridges,the serviceability limit state is more possible to have durability problems in life-cycle;however,the performance indicators at ultimate limit state can satisfy the requirements.展开更多
Considering the construction features of prestressed concrete bridge, the comprehensive evaluation method about the bridge damage conditions are studied. Particular attentions are paid on establishing a muhilevel eval...Considering the construction features of prestressed concrete bridge, the comprehensive evaluation method about the bridge damage conditions are studied. Particular attentions are paid on establishing a muhilevel evaluation model for damaged prestressed concrete bridge, and the evaluation indices of the model as well as the rating standards are defined in the model. A normal relative function about the evaluation indices of each element is developed to calculate the relative degree, and for each element which is no sub-level elements. When evaluating the elements in sub-item level or index level of the model, the weights of elements that are pertained to one element are adopted, taking account of their deterioration degree. At the same time, the dam- age conditions of bridge are characterized by relative degree, element evaluation scale and structural technology mark of bridge, so it agrees with Code for Maintenance of Highway Bridges and Culvers.展开更多
Time-dependant reliability is analyzed for the flexural cracking of prestressed concrete bridges under service limit state. The limit state function and random variables are derived from Chinese highway bridge design ...Time-dependant reliability is analyzed for the flexural cracking of prestressed concrete bridges under service limit state. The limit state function and random variables are derived from Chinese highway bridge design specifications. For deterioration of structural performances, chloride-induced reinforcement corrosion is emphasized. Through integrating first order reliability method (FORM) and time discretized approach, the time-variant reliability is evaluated. For illustrative propose, the reliability of a typical simply supported prestressed concrete beam is exemplified.展开更多
The formwork and falsework in the construction of twin ribbed slab decks on a multi-span ecological bridge for a dual carriageway are presented. The bridge is situated in a valley plain which is crossed by small river...The formwork and falsework in the construction of twin ribbed slab decks on a multi-span ecological bridge for a dual carriageway are presented. The bridge is situated in a valley plain which is crossed by small rivers and was designed principally with the environment in mind. The bridge length is over 356 m, and the width of the decks is 11.5 m. For the bridge works, a simple conventional falsework system was chosen with steel frames for the supports and steel rolled beams for the decks. The formwork was constructed in solid timber and plywood as multiple-use panels. The falsework was designed in order to build the two 10-span bridge decks in stages. The decks are continuous cast-in-situ prestressed concrete twin rib with spans of 30 m, 34 m and 45 m. An individual falsework system was designed, which was easy to move transversally following completion of each stage for one deck. After finishing each stage, for the second deck, the falsework was dismantled and used again in the next construction fronts. An individual arrangement for the falsework along with timber pilings was used to cross the biggest river. The formwork timber panels were used several times in the multistage bridge construction. The adopted falsework system is very simple, but it allowed the speedy construction of the two decks where there were severe time constraints.展开更多
Based on experimental study result of two simply supported beams,which were prestressed by vertical tendons,the research on the weakening effect of vertical prestress ducts on web sections of prestressed concrete box ...Based on experimental study result of two simply supported beams,which were prestressed by vertical tendons,the research on the weakening effect of vertical prestress ducts on web sections of prestressed concrete box girder was carried out. The test result shows that in the condition without grouting into the ducts,the cracking load is evidently lower than that with full grouting,and stirrup stress and principal tension stress at the surface of concrete will increase obviously. Meanwhile,the finite element analysis has been done to the test beams. The research is consistent with the analysis of finite element. The research tells that strengthening the detection and management for the vertical prestress grouting quality have an important meaning to prevent cracking of the prestressed concrete box girder bridge and provide one theoretical and testing basis for analyzing the cracking reason of such bridges.展开更多
This study developed an optimal structural system for the hybrid cable-stayed bridge expected to have a durable lifetime of 200 years and of which major structural members are made of ultra high performance concrete (...This study developed an optimal structural system for the hybrid cable-stayed bridge expected to have a durable lifetime of 200 years and of which major structural members are made of ultra high performance concrete (UHPC) with 200 MPa-class compressive strength. This innovative cable-stayed bridge system makes it possible to reduce each of the construction and maintenance costs by 20% compared to the conventional concrete cable-stayed bridge by improving significantly the weight and durability of the bridge. Therefore, detail design is carried out considering a real 800 m cable-stayed bridge and the optimal structure of the hybrid cable-stayed bridge is proposed and verified.展开更多
This paper presents the method of reinforcing main girder of reinforced concrete cable-stayed bridge with prestressed steel strands.To verify the effectiveness of external prestressed strand reinforcement method.Stati...This paper presents the method of reinforcing main girder of reinforced concrete cable-stayed bridge with prestressed steel strands.To verify the effectiveness of external prestressed strand reinforcement method.Static load tests and health monitoring-based assessment were carried out before and after reinforcement.Field load test shows that the deflection and stress values of the main girder are reduced by 10%~20%after reinforcement,and the flexural strength and stiffness of the strengthened beam are improved.The deflection and strain data of health monitoring of the specified section are collected.The deflection of the second span is 4 mm~10 mm,the strain range of the upper edge of the second span is-10με~-40με,and the strain range of the lower edge is 30με~75με.These values show the deflection and strain values fluctuate within a prescribed range,verifying the safety of the bridge.The reinforcement method of prestressed steel strand is feasible and effective.It can provide reference basis for the application of external prestressed strand reinforcement technology in similar projects.展开更多
Based on full-scale segment model tests of the abnormally shaped anchorage zone of the Maling River cable-stayed bridge pylon and FEM analysis, its mechanical and deformation properties were obtained, and the validity...Based on full-scale segment model tests of the abnormally shaped anchorage zone of the Maling River cable-stayed bridge pylon and FEM analysis, its mechanical and deformation properties were obtained, and the validity of FEM analysis was verified. An optimal layout of prestressed tendons in the anchorage zone was obtained by using the strut-and-tie method (STM). The comparison FEM analysis between the full-scale segment model and the optimal prestressed tendons model show that: the optimal model not only saves prestressed tendons, but also achieves the same cracking resistance; STM method is reliable and accurate in the analysis of the abnormally shaped anchorage zone of cable-stayed bridge pylon.展开更多
In the past 20 years, great progress has been achieved in China in the construction of concrete-filled steel tube (CFST) arch bridges and concrete arch bridges with a CFST skeleton. The span of these bridges has bee...In the past 20 years, great progress has been achieved in China in the construction of concrete-filled steel tube (CFST) arch bridges and concrete arch bridges with a CFST skeleton. The span of these bridges has been increasing rapidly, which is rare in the history of bridge development. The large-scale construction of expressways and high-speed railways demands the development of long-span arch bridges, and advances in design and construction techniques have made it possible to construct such bridges. In the present study, the current status, development, and major innovative technologies of CFST arch bridges and concrete arch bridges with a CFST skeleton in China are elaborated. This paper covers the key con- struction technologies of CFST arch bridges, such as the design, manufacture, and installation of steel tube arch trusses, the preparation and pouring of in-tube concrete, and the construction of the world's longest CFST arch bridge-the First Hejiang Yangtze River Bridge. The main construction technologies of rein- forced concrete arch bridges are also presented, which include cable-stayed fastening-hanging cantilever assembly, adjusting the load by means of stay cables, surrounding the concrete for arch rib pouring, and so forth. In addition, the construction of two CFST skeleton concrete arch bridges-the Guangxi Yongning Yong River Bridge and the Yunnan-Guangxi Railway Nanpan River Bridge--is discussed. CFST arch bridges in China have already gained a world-leading position; with the continuous innovation of key technologies, China will become the new leader in promoting the development of arch bridges.展开更多
Ultra-high performance concrete (UHPC) is featured by a compressive strength 5 times higher than that of ordinary concrete and by a high durability owing to the control of the chloride penetration speed by its dense s...Ultra-high performance concrete (UHPC) is featured by a compressive strength 5 times higher than that of ordinary concrete and by a high durability owing to the control of the chloride penetration speed by its dense structure. The high strength characteristics of UHPC offer numerous advantages like the reduction of the quantities of cables and foundations by the design of a lightweight superstructure in the case of the long-span bridge preserving its structural performance through axial forces and structures governed by compression. This study conducted the conceptual design of a hybrid cable-stayed bridge with central span of 1000 m and exploiting 200 MPa-class UHPC. The economic efficiency of the conceptual design results of the hybrid cable-stayed bridge with central span of 1000 m and of Sutong Bridge, the longest cable-stayed bridge in the world, was analyzed.展开更多
In order to obtain the present effective prestress and its longitudinal distribution of prestressed tendon during the process of inspection and evaluation, a unified analogue method was put forward. Based on the theor...In order to obtain the present effective prestress and its longitudinal distribution of prestressed tendon during the process of inspection and evaluation, a unified analogue method was put forward. Based on the theory for calculating instantaneous prestress loss of the tendons with complicated geometry, a universal numerical model was established. Therefore, the distribution of effective prestress could be simulated after recognizing the nominal coefficients of prestress loss with the obtained stress data of objective steel tendon. The numerical simulation results of a full-length tendon of a three-span continuous beam bridge show that the relative errors between the calculated value and the value in the code are within 5%, which meets the requirement for engineering application.展开更多
Starting from the ideas of Conventional Post Tensioning we present a heuristic argument of advantages of combined actions of post compression along with post tensioned technique for a PSC member through a Design Examp...Starting from the ideas of Conventional Post Tensioning we present a heuristic argument of advantages of combined actions of post compression along with post tensioned technique for a PSC member through a Design Example. Our aim was to assess the characterization of a pre stressed member if it was?to be under the Load effects of post compressing a bar with post tensioned method through hydraulic jacks as the reinforcements in the tensioned zone of conventional PSC bridge were to be compressed in order to induce internal tensile stress similar to internal compressive stresses developed due to conventional post tensioned design. The results ultimately concluded that post compressing a Slender bar by a pre stressing force in the compression zone by a value equal to 0.1?-?0.7 times the pre stressing force in the tension zone would eventually lead to cancelling out of tensile and compressive stresses, thereby forming the desired section which is comparatively smaller in size but can account for sustainability. The anchorage at the top end was?provided by special slender steel rods to eliminate the compressive stresses. All the dead loads?were?counteracted by the action of prestress and the bridge section was able to carry only live load which is deduced through examples in the article.展开更多
Arch bridges provide significant technical and economic benefits under suitable conditions.In particular,concrete-filled steel tubular(CFST)arch bridges and steel-reinforced concrete(SRC)arch bridges are two types of ...Arch bridges provide significant technical and economic benefits under suitable conditions.In particular,concrete-filled steel tubular(CFST)arch bridges and steel-reinforced concrete(SRC)arch bridges are two types of arch bridges that have gained great economic competitiveness and span growth potential due to advancements in construction technology,engineering materials,and construction equipment over the past 30 years.Under the leadership of the author,two record-breaking arch bridges—that is,the Pingnan Third Bridge(a CFST arch bridge),with a span of 560 m,and the Tian’e Longtan Bridge(an SRC arch bridge),with a span of 600 m—have been built in the past five years,embodying great technological breakthroughs in the construction of these two types of arch bridges.This paper takes these two arch bridges as examples to systematically summarize the latest technological innovations and practices in the construction of CFST arch bridges and SRC arch bridges in China.The technological innovations of CFST arch bridges include cable-stayed fastening-hanging cantilevered assembly methods,new in-tube concrete materials,in-tube concrete pouring techniques,a novel thrust abutment foundation for nonrocky terrain,and measures to reduce the quantity of temporary facilities.The technological innovations of SRC arch bridges involve arch skeleton stiffness selection,the development of encasing concrete materials,encasing concrete pouring,arch rib stress mitigation,and longitudinal reinforcement optimization.To conclude,future research focuses and development directions for these two types of arch bridges are proposed.展开更多
基金National Natural Science Foundation of China Under Grant No.50575101Transportation Science Research Item of Jiangsu Province Under Grant No.06Y20
文摘The dynamic finite element model (FEM) of a prestressed concrete continuous box-girder bridge, called the Tongyang Canal Bridge, is built and updated based on the results of ambient vibration testing (AVT) using a real-coded accelerating genetic algorithm (RAGA). The objective functions are defined based on natural frequency and modal assurance criterion (MAC) metrics to evaluate the updated FEM. Two objective functions are defined to fully account for the relative errors and standard deviations of the natural frequencies and MAC between the AVT results and the updated FEM predictions. The dynamically updated FEM of the bridge can better represent its structural dynamics and serve as a baseline in long-term health monitoring, condition assessment and damage identification over the service life of the bridge .
文摘The seismic analysis of a rigid-framed prestressed concrete bridge in Tianjin Light Railway is performed. A 3-D dynamic finite element model of the bridge is established considering the weakening effect caused by the soft soil foundation. After the dynamic characteristics are calculated in terms of natural frequencies and modes, the seismic analysis is carried out using the modal response spectrum method and the time-history method, respectively. Based on the calculated results, the reasonable design values are finally suggested as the basis of the seismic design of the bridge, and meanwhile the problems encountered were also analyzed. Finally, some conclusions are drawn as: 1) Despite the superiority of rigid-framed prestressed concrete bridge, the upper and lower ends of the piers of the bridge are proved to be the crucial parts of the bridge, which are easily destroyed under designed earthquake excitations and should be carefully analyzed and designed; 2) The soft soil foundation can possibly result in rather weakening of the lateral rigidity of the rigid-framed bridge, and should be paid considerable attention; 3) The modal response spectrum method, combined with time-history method, is suggested for the seismic analysis in engineering design of the rigid-framed prestressed concrete bridge.
基金Project(2006.318.223.02-01) supported by the Ministry of Transportation and Communications through the Scientific and Technological Funds of ChinaProject(2007AA11Z104) supported by the High Technology Research and Development of ChinaProject(20090072110045) supported by the Specialized Research Fund for the Doctoral Program of Higher Education of China
文摘To accurately evaluate the degradation process of prestressed concrete continuous bridges exposed to aggressive environments in life-cycle,a finite element-based approach with respect to the lifetime performance assessment of concrete bridges was proposed.The existing assessment methods were firstly introduced and compared.Some essential mechanics problems involved in the degradation process,such as the deterioration of materials properties,the reduction of sectional areas and the variation of overall structural performance caused by the first two problems,were investigated and solved.A computer program named CBDAS(Concrete Bridge Durability Analysis System) was written to perform the above-metioned approach.Finally,the degradation process of a prestressed concrete continuous bridge under chloride penetration was discussed.The results show that the concrete normal stress for serviceability limit state exceeds the threshold value after 60 a,but the various performance indicators at ultimate limit state are consistently in the allowable level during service life.Therefore,in the case of prestressed concrete bridges,the serviceability limit state is more possible to have durability problems in life-cycle;however,the performance indicators at ultimate limit state can satisfy the requirements.
基金the Science and Technology Program for West Communication Construction of MOC(Grant No.2005ZB05)
文摘Considering the construction features of prestressed concrete bridge, the comprehensive evaluation method about the bridge damage conditions are studied. Particular attentions are paid on establishing a muhilevel evaluation model for damaged prestressed concrete bridge, and the evaluation indices of the model as well as the rating standards are defined in the model. A normal relative function about the evaluation indices of each element is developed to calculate the relative degree, and for each element which is no sub-level elements. When evaluating the elements in sub-item level or index level of the model, the weights of elements that are pertained to one element are adopted, taking account of their deterioration degree. At the same time, the dam- age conditions of bridge are characterized by relative degree, element evaluation scale and structural technology mark of bridge, so it agrees with Code for Maintenance of Highway Bridges and Culvers.
文摘Time-dependant reliability is analyzed for the flexural cracking of prestressed concrete bridges under service limit state. The limit state function and random variables are derived from Chinese highway bridge design specifications. For deterioration of structural performances, chloride-induced reinforcement corrosion is emphasized. Through integrating first order reliability method (FORM) and time discretized approach, the time-variant reliability is evaluated. For illustrative propose, the reliability of a typical simply supported prestressed concrete beam is exemplified.
文摘The formwork and falsework in the construction of twin ribbed slab decks on a multi-span ecological bridge for a dual carriageway are presented. The bridge is situated in a valley plain which is crossed by small rivers and was designed principally with the environment in mind. The bridge length is over 356 m, and the width of the decks is 11.5 m. For the bridge works, a simple conventional falsework system was chosen with steel frames for the supports and steel rolled beams for the decks. The formwork was constructed in solid timber and plywood as multiple-use panels. The falsework was designed in order to build the two 10-span bridge decks in stages. The decks are continuous cast-in-situ prestressed concrete twin rib with spans of 30 m, 34 m and 45 m. An individual falsework system was designed, which was easy to move transversally following completion of each stage for one deck. After finishing each stage, for the second deck, the falsework was dismantled and used again in the next construction fronts. An individual arrangement for the falsework along with timber pilings was used to cross the biggest river. The formwork timber panels were used several times in the multistage bridge construction. The adopted falsework system is very simple, but it allowed the speedy construction of the two decks where there were severe time constraints.
文摘Based on experimental study result of two simply supported beams,which were prestressed by vertical tendons,the research on the weakening effect of vertical prestress ducts on web sections of prestressed concrete box girder was carried out. The test result shows that in the condition without grouting into the ducts,the cracking load is evidently lower than that with full grouting,and stirrup stress and principal tension stress at the surface of concrete will increase obviously. Meanwhile,the finite element analysis has been done to the test beams. The research is consistent with the analysis of finite element. The research tells that strengthening the detection and management for the vertical prestress grouting quality have an important meaning to prevent cracking of the prestressed concrete box girder bridge and provide one theoretical and testing basis for analyzing the cracking reason of such bridges.
文摘This study developed an optimal structural system for the hybrid cable-stayed bridge expected to have a durable lifetime of 200 years and of which major structural members are made of ultra high performance concrete (UHPC) with 200 MPa-class compressive strength. This innovative cable-stayed bridge system makes it possible to reduce each of the construction and maintenance costs by 20% compared to the conventional concrete cable-stayed bridge by improving significantly the weight and durability of the bridge. Therefore, detail design is carried out considering a real 800 m cable-stayed bridge and the optimal structure of the hybrid cable-stayed bridge is proposed and verified.
文摘This paper presents the method of reinforcing main girder of reinforced concrete cable-stayed bridge with prestressed steel strands.To verify the effectiveness of external prestressed strand reinforcement method.Static load tests and health monitoring-based assessment were carried out before and after reinforcement.Field load test shows that the deflection and stress values of the main girder are reduced by 10%~20%after reinforcement,and the flexural strength and stiffness of the strengthened beam are improved.The deflection and strain data of health monitoring of the specified section are collected.The deflection of the second span is 4 mm~10 mm,the strain range of the upper edge of the second span is-10με~-40με,and the strain range of the lower edge is 30με~75με.These values show the deflection and strain values fluctuate within a prescribed range,verifying the safety of the bridge.The reinforcement method of prestressed steel strand is feasible and effective.It can provide reference basis for the application of external prestressed strand reinforcement technology in similar projects.
基金The National Natural Science Foundation of China (No.50925828)
文摘Based on full-scale segment model tests of the abnormally shaped anchorage zone of the Maling River cable-stayed bridge pylon and FEM analysis, its mechanical and deformation properties were obtained, and the validity of FEM analysis was verified. An optimal layout of prestressed tendons in the anchorage zone was obtained by using the strut-and-tie method (STM). The comparison FEM analysis between the full-scale segment model and the optimal prestressed tendons model show that: the optimal model not only saves prestressed tendons, but also achieves the same cracking resistance; STM method is reliable and accurate in the analysis of the abnormally shaped anchorage zone of cable-stayed bridge pylon.
文摘In the past 20 years, great progress has been achieved in China in the construction of concrete-filled steel tube (CFST) arch bridges and concrete arch bridges with a CFST skeleton. The span of these bridges has been increasing rapidly, which is rare in the history of bridge development. The large-scale construction of expressways and high-speed railways demands the development of long-span arch bridges, and advances in design and construction techniques have made it possible to construct such bridges. In the present study, the current status, development, and major innovative technologies of CFST arch bridges and concrete arch bridges with a CFST skeleton in China are elaborated. This paper covers the key con- struction technologies of CFST arch bridges, such as the design, manufacture, and installation of steel tube arch trusses, the preparation and pouring of in-tube concrete, and the construction of the world's longest CFST arch bridge-the First Hejiang Yangtze River Bridge. The main construction technologies of rein- forced concrete arch bridges are also presented, which include cable-stayed fastening-hanging cantilever assembly, adjusting the load by means of stay cables, surrounding the concrete for arch rib pouring, and so forth. In addition, the construction of two CFST skeleton concrete arch bridges-the Guangxi Yongning Yong River Bridge and the Yunnan-Guangxi Railway Nanpan River Bridge--is discussed. CFST arch bridges in China have already gained a world-leading position; with the continuous innovation of key technologies, China will become the new leader in promoting the development of arch bridges.
文摘Ultra-high performance concrete (UHPC) is featured by a compressive strength 5 times higher than that of ordinary concrete and by a high durability owing to the control of the chloride penetration speed by its dense structure. The high strength characteristics of UHPC offer numerous advantages like the reduction of the quantities of cables and foundations by the design of a lightweight superstructure in the case of the long-span bridge preserving its structural performance through axial forces and structures governed by compression. This study conducted the conceptual design of a hybrid cable-stayed bridge with central span of 1000 m and exploiting 200 MPa-class UHPC. The economic efficiency of the conceptual design results of the hybrid cable-stayed bridge with central span of 1000 m and of Sutong Bridge, the longest cable-stayed bridge in the world, was analyzed.
基金Science & Technology Program for West Communication Construction of MOC(No.200531881215)
文摘In order to obtain the present effective prestress and its longitudinal distribution of prestressed tendon during the process of inspection and evaluation, a unified analogue method was put forward. Based on the theory for calculating instantaneous prestress loss of the tendons with complicated geometry, a universal numerical model was established. Therefore, the distribution of effective prestress could be simulated after recognizing the nominal coefficients of prestress loss with the obtained stress data of objective steel tendon. The numerical simulation results of a full-length tendon of a three-span continuous beam bridge show that the relative errors between the calculated value and the value in the code are within 5%, which meets the requirement for engineering application.
文摘Starting from the ideas of Conventional Post Tensioning we present a heuristic argument of advantages of combined actions of post compression along with post tensioned technique for a PSC member through a Design Example. Our aim was to assess the characterization of a pre stressed member if it was?to be under the Load effects of post compressing a bar with post tensioned method through hydraulic jacks as the reinforcements in the tensioned zone of conventional PSC bridge were to be compressed in order to induce internal tensile stress similar to internal compressive stresses developed due to conventional post tensioned design. The results ultimately concluded that post compressing a Slender bar by a pre stressing force in the compression zone by a value equal to 0.1?-?0.7 times the pre stressing force in the tension zone would eventually lead to cancelling out of tensile and compressive stresses, thereby forming the desired section which is comparatively smaller in size but can account for sustainability. The anchorage at the top end was?provided by special slender steel rods to eliminate the compressive stresses. All the dead loads?were?counteracted by the action of prestress and the bridge section was able to carry only live load which is deduced through examples in the article.
基金financially supported by the Guangxi Key Research and Development Plan Program(AB22036007).
文摘Arch bridges provide significant technical and economic benefits under suitable conditions.In particular,concrete-filled steel tubular(CFST)arch bridges and steel-reinforced concrete(SRC)arch bridges are two types of arch bridges that have gained great economic competitiveness and span growth potential due to advancements in construction technology,engineering materials,and construction equipment over the past 30 years.Under the leadership of the author,two record-breaking arch bridges—that is,the Pingnan Third Bridge(a CFST arch bridge),with a span of 560 m,and the Tian’e Longtan Bridge(an SRC arch bridge),with a span of 600 m—have been built in the past five years,embodying great technological breakthroughs in the construction of these two types of arch bridges.This paper takes these two arch bridges as examples to systematically summarize the latest technological innovations and practices in the construction of CFST arch bridges and SRC arch bridges in China.The technological innovations of CFST arch bridges include cable-stayed fastening-hanging cantilevered assembly methods,new in-tube concrete materials,in-tube concrete pouring techniques,a novel thrust abutment foundation for nonrocky terrain,and measures to reduce the quantity of temporary facilities.The technological innovations of SRC arch bridges involve arch skeleton stiffness selection,the development of encasing concrete materials,encasing concrete pouring,arch rib stress mitigation,and longitudinal reinforcement optimization.To conclude,future research focuses and development directions for these two types of arch bridges are proposed.