Penalty model for delay of bidding section construction period in South-to-North Water Diversion Eastern Route Project from perspective of programs 被引量:2
1
作者 Jing-chun FENG Ya-fang REN +2 位作者 Zhong-nan DUAN Zhan-jun LIU Hai-yang LI 《Water Science and Engineering》 EI CAS 2012年第3期350-360,共11页
According to the multi-project and program management theory, this paper analyzes the program generation principle and establishes a program based on progress goals. On the basis of the present situation of calculatio... According to the multi-project and program management theory, this paper analyzes the program generation principle and establishes a program based on progress goals. On the basis of the present situation of calculation of penalty for delay of the bidding section construction period with the critical path method, we studied the effects of contractor-induced delay of the bidding section construction period in detail, including the effects on the construction period of the bidding section itself, the earliest start times of the next bidding section and other subsequent bidding sections, and the construction period of the program, and then constructed a penalty model for delay of the bidding section construction period from the perspective of programs. Using the penalty model, we conducted a practical analysis of penalty for delay of the construction period of the Baoying station program in the South-to-North Water Diversion Project. The model can help determine the amount of penalty for delay of the construction period in bidding sections scientifically and reasonably, 展开更多
关键词 program establishment program management bidding section construction period critical path method (CPM) penaly model south-to-north water diversion project
下载PDF
Spatio-temporal distribution of phytoplankton in the Danjiangkou Reservoir, a water source area for the South-to-North Water Diversion Project (Middle Route), China 被引量:12
2
作者 殷大聪 郑凌凌 宋立荣 《Chinese Journal of Oceanology and Limnology》 SCIE CAS CSCD 2011年第3期531-540,共10页
One of the water source areas of the South-to-North Water Diversion Project is the Danjiangkou Reservoir (DJKR). To understand seasonal variation in phytoplankton composition, abundance and distribution in the DJKR ... One of the water source areas of the South-to-North Water Diversion Project is the Danjiangkou Reservoir (DJKR). To understand seasonal variation in phytoplankton composition, abundance and distribution in the DJKR area before water diversion, as well as to estimate potential risks of water quality after water diversion, we conducted an investigation on phytoplankton in the DJKR from August 2008 to May 2009. The investigation included 10 sampling sites, each with four depths of 0.5, 5, 10, and 20 m. In this study, 117 taxa belonging to 76 genera were identified, consisting of diatoms (39 taxa), green algae (47 taxa), blue-green algae (19 taxa), and others (12 taxa). Annual average phytoplankton abundance was 2.01×10^6 ind./L, and the highest value was 14.72 ×10^6 ind/L (at site 3 in August 2008). Phytoplankton abundance in front of the Danjiangkou Dam (DJKD) was higher than that of the Danjiang Reservoir Basin. Phytoplankton distribution showed a vertical declining trend from 0.5 m to 20 m at most sites in August 2008 (especially at sites of 1, 2, 4 and 10), but no distinct pattern in other sampling months. In December 2008 and March 2009, Stephanodiseus sp. was the most abundant species, amounting to 55.23% and 72.34%, respectively. We propose that high abundance ofStephanodiscus sp. may have contributed greatly to the frequent occurrence of Stephanodiscus sp. blooms in middle-low reaches of the Hanjiang River during the early spring of 2009. In comparison with previous studies conducted from 1992 to 2006, annual average phytoplankton density, green algae and blue-green algae species, as well as major nutrient concentrations increased, while phytoplankton diversity indices declined. This indicates a gradual decline in water quality. More research should be conducted and countermeasures taken to prevent further deterioration of water quality in the DJKR. 展开更多
关键词 Danjiangkou Reservoir PHYTOPLANKTON south-to-north water diversion project EUTROPHICATION
下载PDF
Land Cover Changes and Drivers in the Water Source Area of the Middle Route of the South-to-North Water Diversion Project in China from 2000 to 2015 被引量:3
3
作者 GAO Wenwen ZENG Yuan +2 位作者 ZHAO Dan WU Bingfang REN Zhiyuan 《Chinese Geographical Science》 SCIE CSCD 2020年第1期115-126,共12页
The Middle Route of the South-to-North Water Diversion Project(MR-SNWDP)in China,with construction beginning in 2003,diverts water from Danjiangkou Reservoir to North China for residential,agriculture and industrial u... The Middle Route of the South-to-North Water Diversion Project(MR-SNWDP)in China,with construction beginning in 2003,diverts water from Danjiangkou Reservoir to North China for residential,agriculture and industrial use.The water source area of the MR-SNWDP is the region that is most sensitive to and most affected by the construction of this water diversion project.In this study,we used Landsat Thematic Mapper(TM)and HJ-1 A/B images from 2000 to 2015 by an object-based approach with a hierarchical classification method for mapping land cover in the water source area.The changes in land cover were illuminated by transfer matrixes,single dynamic degree,slope zones and fractional vegetation cover(FVC).The results indicated that the area of cropland decreased by 31%and was replaced mainly by shrub over the past 15 years,whereas forest and settlements showed continuous increases of 29.2% and 77.7%,respectively.The changes in cropland were obvious in all slope zones and decreased most remarkably(–43.8%)in the slope zone above 25°.Compared to the FVC of forest and shrub,significant improvement was exhibited in the FVC of grassland,with a growth rate of 16.6%.We concluded that local policies,including economic development,water conservation and immigration resulting from the construction of the MR-SNWDP,were the main drivers of land cover changes;notably,they stimulated the substantial and rapid expansion of settlements,doubled the wetlands and drove the transformation from cropland to settlements in immigration areas. 展开更多
关键词 remote sensing land cover change object-based classification Middle route of the south-to-north water diversion project(MR-SNWDP) China
下载PDF
Wet-Dry Runoff Correlation in Western Route of South-to-North Water Diversion Project,China 被引量:2
4
作者 HUANG Xiao-rong ZHAO Jing-wei YANG Peng-peng 《Journal of Mountain Science》 SCIE CSCD 2015年第3期592-603,共12页
The Western Route of the South-to-North Water Diversion Project is an important trans-basin diversion project to transfer water from the upstream Yangtze River and its tributaries (water-exporting area), to the upst... The Western Route of the South-to-North Water Diversion Project is an important trans-basin diversion project to transfer water from the upstream Yangtze River and its tributaries (water-exporting area), to the upstream of the Yellow River (water- importing area). The long-term hydrologieal data from 14 stream gauging stations in the Western Route area and techniques including the pre-whitening approach, non-parametric test, Bayes, law, variance analysis extrapolation, and Wavelet Analysis are applied to identify the streamflow eharacteristics and trends, streamflow time series cross-correlations, wetness-dryness encountering probability, and periodicities that occurred over the last 50 years. The results show that the water-exporting area, water- importing area, and the streteh downstream of the water-exporting have synehronization in high-low flow relationship, whereas they display non- synchronization in long-term evolution. This corresponds to the complicated and variable climate of the plateau region. There is no obvious increasing or decreasing trend in runoff at any gauging station. The best hydrological eompensation probability for rivers where water is diverted is about 25% to lO%, and those rivers influenced significantly by diversion are the Jinsha and Yalong rivers. Proper planning and design of compensation reservoirs for the water-exporting area and stretch downstream of the water- exporting area can increase the hydrological compensation possibility from water-exporting area to the water-importing area, and reduce the impact on the stretch of river downstream of the water- exporting area. 展开更多
关键词 south-to-north water diversion project Yangtze River Streamflow Encounter probability Correlation coefficient Cycle Hydrologicalcompensation
下载PDF
IMPACTS OF THE SOUTH-TO-NORTH WATER DIVERSION PROJECTS (MIDDLE ROUTE)ON THE WATER ENVIRONMENT OF THE MIDDLE AND LOWER REACHES OF THE HANJIANG RIVER
5
作者 FAN Bei-Lin, WAN Jian-Rong, ZHANG Jie and LIN Qiu-Sheng (Yangtze River Scientific Research Institute,River Research Deparment, Wuhan 430010,China) 《水生生物学报》 CAS CSCD 北大核心 2006年第6期643-646,共4页
In this paper, according to the rule of unbalanced sediment transport and the analysis of field data, different water diversion schemes were theoretically studied, including the erosion and sedimentation trend as well... In this paper, according to the rule of unbalanced sediment transport and the analysis of field data, different water diversion schemes were theoretically studied, including the erosion and sedimentation trend as well as their impacts on the environment of the middle and lower reaches of the Hanjiang River. The results showed that the 95×10 8m 3 water diversion scheme will cause less erosion and water level decrease than the 15×10 8m 3 water diversion scheme. Using a water diversion scheme of 95×10 8m 3, the decrease of water quantity can impact the river hydrodynamic regime substantially and the environments of the middle and lower reaches of the Hanjiang River will be greatly affected. It is therefore necessary to develop new water resources or build projects to meet the need of the environment and the needs for navigation. 展开更多
关键词 south-to-north water diversion project River regime water environment Mathematical model
下载PDF
Water-saving potential evaluation of water-receiving regions in Shandong province on the East Route of the South-to-North Water Transfer Project of China
6
作者 YIN Xiao-lin GAO Yuan-yuan +1 位作者 WU Hai-ping ZHAO Xue-ming 《Journal of Groundwater Science and Engineering》 2020年第3期287-297,共11页
Taking 13 water-receiving areas on the East Route of the South-to-North Water Diversion Project(ERSNWDP)in Shandong Province as the study area,and comparing it with Jiangsu Province on the ERSNWDP and the Middle Route... Taking 13 water-receiving areas on the East Route of the South-to-North Water Diversion Project(ERSNWDP)in Shandong Province as the study area,and comparing it with Jiangsu Province on the ERSNWDP and the Middle Route of the South-to-North(MRSNWDP),the current water-saving potential of the water-receiving areas within the municipalities of Shandong was analyzed.Different water-saving scenarios were constructed and analyzed with key water-saving indexes in various industries.These indexes include the effective utilization coefficient of farmland irrigation water,total water consumption of industrial sectors with an added value of over 10000 RMB,average leakage rate of the urban public water supply pipe network and the penetration rate of water-saving appliances.Based on the scenarios,comprehensive water-saving potential of the 13 water-receiving area cities was calculated.The results show that the water-saving potential of the study area is at a relative high level.However,some cities still have a certain amount of water-saving potential for agriculture and industry to be elevated.Under the recommended water-saving scenario,the water-saving potential is 1.134 billion m3,accounting for 5.33%of the current total water consumption,of which 460 million m3 is in agriculture,600 million m3 in industry,is and 74.20 million m3 in urban domestic sector.Comprehensive water-saving measures for the study area were proposed from the aspects of agricultural,industrial and domestic water uses.Agricultural and industrial water saving are more significant.The major cities for agricultural water saving include Jining City,Heze City,Weifang City and Jinan City;the focus cities of industrial water saving mainly include Weihai City,Jining City and Qingdao City and etc.;the key water-saving areas for urban use mainly include Zaozhuang City,Jining City and Heze City. 展开更多
关键词 east route of south-to-north water diversion project Shandong water receiving area water-saving level water-saving potential
下载PDF
Critical chain construction with multi-resource constraints based on portfolio technology in South-to-North Water Diversion Project 被引量:3
7
作者 Jing-chun FENG Lei LI +4 位作者 Nan YANG Yu-zhen HONG Min PANG Xiong YAO Li-cheng WANG 《Water Science and Engineering》 EI CAS 2011年第2期225-236,共12页
Recently, the critical chain study has become a hot issue in the project management research field. The construction of the critical chain with multi-resource constraints is a new research subject. According to the sy... Recently, the critical chain study has become a hot issue in the project management research field. The construction of the critical chain with multi-resource constraints is a new research subject. According to the system analysis theory and project portfolio theory, this paper discusses the creation of project portfolios based on the similarity principle and gives the definition of priority in multi-resource allocation based on quantitative analysis. A model with multi-resource constraints, which can be applied to the critical chain construction of the A-bid section in the South-to-North Water Diversion Project, was proposed. Contrast analysis with the comprehensive treatment construction method and aggressive treatment construction method was carried out. This paper also makes suggestions for further research directions and subjects, which will be useful in improving the theories in relevant research fields. 展开更多
关键词 multi-resource constraints south-to-north water diversion project project portfolio critical chain
下载PDF
Reliability model of organization management chain of South-to-North Water Diversion Project during construction period 被引量:3
8
作者 Feng Jingchun Zhou Yang +2 位作者 Hong Yuzhen Zhao Shixin Ren Xiaoqiang 《Water Science and Engineering》 EI CAS 2008年第4期107-113,共7页
In order to analyze the indispensability of the organization management chain of the South-to-North Water Diversion Project (SNWDP), two basic forms (series connection state and mixed state of both series connectio... In order to analyze the indispensability of the organization management chain of the South-to-North Water Diversion Project (SNWDP), two basic forms (series connection state and mixed state of both series connection and parallel connection) of the organization management chain can be abstracted. The indispensability of each form has been studied and is described in this paper. Through analysis of the reliability of the two basic forms, reliability models of the organization management chain in the series connection state and the mixed state of both series connection and parallel connection have been set up. 展开更多
关键词 south-to-north water diversion project reliability model management chain parallel connection series connection
下载PDF
Geological conditions and key rock mechanics issues in the Western Route of South-to-North Water Transfer Project 被引量:2
9
作者 XuechaoWang 《Journal of Rock Mechanics and Geotechnical Engineering》 SCIE 2011年第3期234-243,共10页
In terms of special geological conditions of the Western Route of South-to-North Water Transfer Project, the classification method for surrounding rocks is discussed by combining with the construction method of tunnel... In terms of special geological conditions of the Western Route of South-to-North Water Transfer Project, the classification method for surrounding rocks is discussed by combining with the construction method of tunnel boring machine (TBM). The classification standard of surrounding rocks is put forward on the basis of physical simulations and engineering practices. Damage, deformation and evolution of surrounding rocks induced by TBM excavation are discussed. Meanwhile, the long-term deformation mechanisms and stability of surrounding rocks are also studied. On this basis, a three-dimensional constitutive model for interbedded sandstone slate and a fiat shell-joint element-foundation system for calculating internal forces of segment lining are established. The deformation features of surrounding rocks of deep and steep interbedded sandstone slate and their influences on internal forces of segment lining are presented. Finally, the design methods of segment lining constructed in deep and steep flysch are proposed. 展开更多
关键词 the Western route of south-to-north water Transfer project rock mechanics issues classification of surrounding rocks stability of surrounding rocks excavation-induced damage lining design
下载PDF
Water diversion and agricultural production:Evidence from China 被引量:1
10
作者 YANG Rui XU Hang 《Journal of Integrative Agriculture》 SCIE CAS CSCD 2023年第4期1244-1257,共14页
Water diversion can alleviate water shortages caused by the uneven distribution of water resources.China’s Southto-North Water Diversion Project(SNWD)is the largest water diversion project worldwide.Based on the pref... Water diversion can alleviate water shortages caused by the uneven distribution of water resources.China’s Southto-North Water Diversion Project(SNWD)is the largest water diversion project worldwide.Based on the prefecturelevel data of China’s Huang-Huai-Hai Plain from 2000 to 2020,this study employs an empirical strategy of Differencesin-Differences(DID)to analyze the impact of SNWD on agricultural production.The results show that SNWD has significantly increased agricultural production,measured by the agricultural value added.The estimated results of the benchmark model remain robust when the contemporaneous policy is addressed,an alternative outcome is used,subsamples are estimated,and alternative estimation techniques are employed.This study argues that the potential impact mechanism may be that SNWD significantly increases the acreage for cash crops but reduces that for grain crops.Heterogeneity analysis shows that in prefectures with high temperature or land potential,SNWD’s impact on agricultural value added is relatively low.In contrast,in areas with prolonged sunshine or high slopes,SNWD’s impact on agricultural value added is relatively large.Given the low added value of grain crops,the government should consider strengthening food security by subsidizing water supply to sustain grain production. 展开更多
关键词 south-to-north water diversion project agricultural production Differences-in-Differences China
下载PDF
Coupling interaction between biodiversity and aquatic habitat area in Western Route Project vicinity 被引量:1
11
作者 Shi-min TIAN Zhao-yin WANG +1 位作者 Xiang-jun LIU Shi-kui LIANG 《Water Science and Engineering》 EI CAS 2010年第3期354-360,共7页
The Western Route of the South-to-North Water Transfer Project will divert water from the upper Yangtze River and its tributaries, the Dadu River and Yalong River, to the upper Yellow River. The project may ease the w... The Western Route of the South-to-North Water Transfer Project will divert water from the upper Yangtze River and its tributaries, the Dadu River and Yalong River, to the upper Yellow River. The project may ease the water shortage in the Yellow River Basin. However, it may also have some effects on the ecosystem in the upper Yangtze River Basin. Benthic invertebrates play an important role in the river ecosystem, particularly in the circulation of materials and nutrition. Benthic invertebrates are widely used to quickly assess river ecosystems because of their rapid response to changes in the water environment. The diversity of benthic invertebrates is closely associated with the aquatic habitat area. This study examined this interaction by sampling the benthic invertebrates in an expanding area. The conclusions are that the diversity of benthic invertebrates begins to decrease when the aquatic habitat area is reduced to 45% of the original area, and decreases dramatically when the aquatic habitat area is reduced to 10% of the original area. The aquatic habitat area should be kept at more than 45% of the original area in order to maintain the significant diversity of benthic invertebrates. 展开更多
关键词 Western route project south-to-north water Transfer project river ecosystem benthic invertebrates BIOdiversITY aquatic habitat area
下载PDF
Critical discharge at Datong for controlling operation of South-to-North Water Transfer Project in dry seasons 被引量:3
12
作者 Wang Yigang Huang Huiming Li Xi 《Water Science and Engineering》 EI CAS 2008年第2期47-58,共12页
Previous research shows that there is a strong correlation between saltwater intrusion in the Yangtze Estuary and discharge at Datong. In the near future, the discharge of the Yangtze River during dry seasons will dec... Previous research shows that there is a strong correlation between saltwater intrusion in the Yangtze Estuary and discharge at Datong. In the near future, the discharge of the Yangtze River during dry seasons will decrease due to the construction and operation of large water diversion projects, including the South-to-North Water Transfer Project, which will further exacerbate saltwater intrusion in the estuary. In this paper, a nested 1D river network model and a 2D saltwater numerical model are used to associate saltwater intrusion in the Yangtze Estuary with different values of discharge at Datong. It is concluded that 13 000 m3/s is the critical discharge at Datong for preventing saltwater intrusion and controlling the volume of water transferred by the South-to-North Water Transfer Project. Furthermore, based on the analysis of river discharge from Datong to Xuliujing and in consideration of the influence of all of the water diversion projects, operation schemes are proposed for the Eastern Route of the South-to-North Water Transfer Project for different hydrological years. 展开更多
关键词 saltwater intrusion critical discharge at Datong water diversion the south-to-north water Transfer project
下载PDF
On conservation and development of architecture and environment in the construction of large-scale national infrastructure——Exemplified by the Jiangsu Section of the Eastern Route South-to-North Water Diversion Project 被引量:1
13
作者 DUAN Jin ,LUO JianLi,WANG XingPing,TANG Jun&YU Gang School of Architecture,Southeast University,Nanjing 210096,China 《Science China(Technological Sciences)》 SCIE EI CAS 2009年第12期3613-3625,共13页
The water-diverting route project’s characteristics,natural landscapes,and histories and humanism of the Jiangsu Section of the Eastern Route South-to-North Water Diversion Project were systemically analyzed through ... The water-diverting route project’s characteristics,natural landscapes,and histories and humanism of the Jiangsu Section of the Eastern Route South-to-North Water Diversion Project were systemically analyzed through proposing and studying the canal culture routes,the water resources heritage corridors,the landscape and recreation corridors,and the town economic corridors.The station areas along the water-diverting route were scientifically zoned and graded through quantitative and qualitative synthetic methods.Both planning compendiums and construction controlling methods were proposed based on the project grades of points,lines,and areas.Conservation and development of architecture and environment in the large-scale national infrastructure construction were explored systemically.Theories and methods of developing harmonious water-supplying functions,ecological functions,landscape effects,and cultural effects of large-scale water resources were examined. 展开更多
关键词 Jiangsu Section of eastern route south-to-north water diversion project CANAL culture routes water resources heritage CORRIDORS landscape and RECREATION CORRIDORS town economic CORRIDORS synthetical ZONING and grading
原文传递
Computing payment for ecosystem services in watersheds: An analysis of the Middle Route Project of South-to-North Water Diversion in China 被引量:12
14
作者 Zhengju Dong Yan Yan +5 位作者 Jing Duan Xiao Fu Qingrong Zhou Xiang Huang Xiangen Zhu Jingzhu Zhao 《Journal of Environmental Sciences》 SCIE EI CAS CSCD 2011年第12期2005-2012,共8页
Payment for ecosystem services (PES) has attracted considerable attention as an economic incentive for promoting natural resource management recently. As emphasis has been placed on using the incentive-based mechani... Payment for ecosystem services (PES) has attracted considerable attention as an economic incentive for promoting natural resource management recently. As emphasis has been placed on using the incentive-based mechanism by the central government, rapid progress on PES research and practice has been achieved. However PES still faces many difficulties. A key issue is the lack of a fully-fledged theory and method to clearly define the design scope, accounting and feasibility of PES criteria. An improved watershed criteria model was developed in light of research on PES practices in China, investigations on the water source area for the Middle Route Project of South-to-North Water Diversion and ecosystem services outflows theory. The basic principle of assessment is the direct and opportunity cost for ecological conservation and environmental protection in the water source area deduct nationally-financed PES and internal effect. Then the scope and the criteria methods were determined, and internal effect was put forward to define benefits brought from water source area. Finally, Shiyan City, which is the main water source area for the Project of Water Diversion, was analyzed by this model and its payment was calculated. The results showed that: (1) during 2003–2050, the total direct cost and opportunity cost would reach up to 262.70 billion and 256.33 billion Chinese Yuan (CNY, 2000 constant prices), i.e., 50.61% and 49.38% of total cost, respectively; (2) Shiyan City would gain 0.23, 0.06 and 0.03 CNY/m3 in 2014–2020, 2021–2030, and 2031–2050, respectively. 展开更多
关键词 waterSHED payment for ecosystem services ecosystem services cost-benefit analysis Middle route project of South-to- North water diversion
原文传递
Nutrient transport following water transfer through the world's largest water diversion channel
15
作者 Yuanhui Cheng Hong Zhang Wei Yin 《Journal of Environmental Sciences》 SCIE EI CAS CSCD 2024年第1期703-714,共12页
Nutrient levels in the artificial channel constructed for the Middle Route Project are significant indicators of water quality safety and aquatic ecological integrity for this large,interbasin scheme.However,the distr... Nutrient levels in the artificial channel constructed for the Middle Route Project are significant indicators of water quality safety and aquatic ecological integrity for this large,interbasin scheme.However,the distribution and transport of nutrients along the channel were poorly understood.Based on a time-series dataset as well as mass balance and material flow analysis methods,the water and nutrient transport fluxes in the Middle Route of the South-to-North Water Diversion Project were identified in this study.The results indicate that the nutrient concentrations varied considerably with time,but there was no significant difference among the 30 stations of the main channel.Seasonal temperature difference was the major factor in the large fluctuations of water quality indicators over time.The nutrient loadings varied with the water volume outputs from the main channel to the waterreceiving cities.Atmospheric deposition was an important source of nutrients in the main channel,accounting for 9.13%,20.6%,and 0.635%of the nitrogen,phosphorus,and sulfur input from the Danjiangkou Reservoir,respectively.In 2021,a net accumulation of 988 tons of N,29 tons of P,and 2,540 tons of S,respectively,were present in the main channel.The increase of these external and internal nutrient loadings would cause water quality fluctuation and deterioration in some local sections of the main channel.Our study quantified the spatial and temporal patterns of nutrient transport in the Middle Route and revealed the ecological effects on the aquatic environment,assisting authorities on the project to develop effective water conservation strategies. 展开更多
关键词 Nutrient transport Spatiotemporal patterns The Middle route The south-to-north diversion project Hydro-ecological effects water-receiving cities
原文传递
南水北调西线工程水源区可调水量“十问” 被引量:2
16
作者 胡鹏 王浩 +13 位作者 赵勇 宁远 蒋云钟 刘欢 曾庆慧 杨泽凡 周毓彦 董宁澎 闫龙 阿膺兰 张丰博 唐家璇 王玉莲 王建华 《中国工程科学》 CSCD 北大核心 2024年第2期210-223,共14页
南水北调西线工程是我国“四横三纵”国家水网主骨架尚待建设的最后一环,而水源区可调水量是西线工程规划论证面临的焦点和难点问题。本文从水资源本底条件与演变趋势,生态环境与经济社会发展需水,调蓄水库与输水工程规模,调水对水源区... 南水北调西线工程是我国“四横三纵”国家水网主骨架尚待建设的最后一环,而水源区可调水量是西线工程规划论证面临的焦点和难点问题。本文从水资源本底条件与演变趋势,生态环境与经济社会发展需水,调蓄水库与输水工程规模,调水对水源区及其下游水资源开发利用、水生态环境、水力发电、航运等方面影响的角度,提出了与水源区可调水量相关的10个问题;以长江上游分布式水文模型为基础,建立了南水北调西线工程水源区可调水量模拟分析模型,力图系统、定量地回答所提问题。本文的主要研究结论有:在仅考虑满足水源区河道内外生态环境和经济社会需水的前提下,“上线+下线”组合方案多年平均可调水量为1.59×10^(10)m^(3),“完全下线”方案在建设岗托水库进行联调时,多年平均可调水量将达到1.74×10^(10)m^(3);在综合考虑调水对水源区水平衡、水力发电和航运影响及其可接受程度后,南水北调西线水源区可调水量为1.22×10^(10)~1.26×10^(10)m^(3)。长远来看,应谋划西南片区水网与国家水网主骨架、“大动脉”的连接与融合,在减小南水北调西线工程调水影响的同时,提高南水北调西线工程的整体供水能力以及对气候变化等外部条件的适应性。 展开更多
关键词 南水北调西线工程 水源区 可调水量 生态需水 跨流域调水
下载PDF
不同调水方式对巢湖水质影响模拟
17
作者 易雨君 魏震 +3 位作者 郭玉明 刘泓汐 刘培 徐俏 《水力发电学报》 CSCD 北大核心 2024年第9期1-12,共12页
引调水工程是目前用来改善湖泊水质的重要手段,然而引调水的调水路线、来水水量以及来水水质对湖泊水质改善效果都至关重要。本文以“引江济巢”工程为例,针对巢湖的浅水湖泊特征,考虑引调水入湖后不仅对水量和水质有直接改善作用,还可... 引调水工程是目前用来改善湖泊水质的重要手段,然而引调水的调水路线、来水水量以及来水水质对湖泊水质改善效果都至关重要。本文以“引江济巢”工程为例,针对巢湖的浅水湖泊特征,考虑引调水入湖后不仅对水量和水质有直接改善作用,还可能因为湖区水动力条件改变及内源释放影响水质,通过构建二维水动力水质模型,模拟不同调水路线、水量下湖区水动力条件,进一步考虑不同来水水质和底泥释放对水质改善的影响。结果显示,调水对流场的扰动在丰水年较弱、枯水年较强,流量对湖区水质影响随流量增大而增强,来水水质的优劣是决定湖区水体水质是否改善的关键。整体而言,西湖区受调水影响较小,东湖区能够对全湖水质变化起到指示作用。调水方案应基于湖泊实际水量与水质状态综合考虑调水流量与水质制定。 展开更多
关键词 “引江济巢”工程 巢湖 MIKE21 调水路线 水环境治理
下载PDF
气候变化对南水北调西线工程的影响及建议
18
作者 王国庆 虞畅 +3 位作者 金君良 宁忠瑞 王云 孙高霞 《人民黄河》 CAS 北大核心 2024年第9期60-66,共7页
南水北调工程是国家水网的重要组成部分,其西线工程建设是缓解我国西北、华北地区水资源短缺的重要举措。气候变化下西线工程引水区和受水区水资源情势直接关系到工程的规划建设与运行方式。基于历史实测资料和气候模式情景,采用数理统... 南水北调工程是国家水网的重要组成部分,其西线工程建设是缓解我国西北、华北地区水资源短缺的重要举措。气候变化下西线工程引水区和受水区水资源情势直接关系到工程的规划建设与运行方式。基于历史实测资料和气候模式情景,采用数理统计与水文模拟相结合的途径分析了气候变化对南水北调西线工程引水区和受水区水资源的影响。结果表明:1)1961—2020年西线调水区和受水区气候变化以暖湿化为主要特征,调水区年径流量整体稳定略增,受水区年径流量显著性减少。2)未来中期(2035年)和远期(2050年),调水区和受水区气温继续显著升高,降水多呈非显著增加;未来中期、远期调水区年径流量较基准期(1961—2000年)分别增加1.42%和2.08%,受水区年径流量分别减少1.02%和0.28%。3)未来气候变化下,调水区年径流量相对稳定,能够满足调水需求,受水区年径流量略减,对跨流域调水需求有所增加。为确保南水北调西线工程的长期稳定运行,建议加强气候变化及其影响的不确定性研究,制定科学合理的应对措施,以应对未来可能的水资源短缺的挑战。 展开更多
关键词 气候变化 RCCC-WBM模型 水资源 南水北调西线工程
下载PDF
南水北调中线总干渠冰盖糙率观测分析
19
作者 段文刚 邢梦媛 +2 位作者 黄明海 杨金波 沙继婷 《长江科学院院报》 CSCD 北大核心 2024年第10期78-85,118,共9页
冰盖糙率是确定渠道冰期输水水位和流量关系的基础参数,一直是明渠冰工程研究的重点之一。鉴于当前大型混凝土渠道冰盖糙率研究成果相当匮乏,以南水北调中线总干渠石家庄以北唯一无输水建筑物的唐河节制闸—放水河节制闸渠段为研究区域... 冰盖糙率是确定渠道冰期输水水位和流量关系的基础参数,一直是明渠冰工程研究的重点之一。鉴于当前大型混凝土渠道冰盖糙率研究成果相当匮乏,以南水北调中线总干渠石家庄以北唯一无输水建筑物的唐河节制闸—放水河节制闸渠段为研究区域,依据全线通水以来唯一生成全渠段封冻冰盖的2016年1—2月逐日水位和流量实测数据,采用伯努利能量方程和谢才-曼宁公式推求渠道糙率,定性定量分析封冻前后渠道糙率变化特征。结果表明:①研究渠段畅流期渠道糙率n b为0.0167,封冻期冰盖综合糙率n c为0.0146,冰盖下表面糙率n i为0.0118。②由于水力磨蚀作用,封冻期冰盖糙率随时间呈波动减小的趋势。③渠道一旦生成封冻冰盖,输水能力大幅降低,仅占渠道设计流量的66.7%。该研究给出了大型混凝土渠道封冻冰盖糙率和输水能力降低的确切数值,以期为冰期输水调度和类似工程设计提供科学依据。 展开更多
关键词 南水北调中线工程 冰盖糙率 渠道糙率 输水能力 水头损失
下载PDF
局部降温对输水渠道水华抑制的影响分析
20
作者 张雅卓 宋芷萱 +2 位作者 姚烨 闫琳琳 徐楚涵 《水资源与水工程学报》 CSCD 北大核心 2024年第2期130-138,148,共10页
南水北调中线工程自通水以来,发挥着巨大的社会和经济效益,已成为京津地区的主力水源。中线工程输水的水质理化指标相对稳定,但局部渠段存在藻类异常增殖现象,有水华爆发的风险。针对出现的藻类异常增殖问题,在通冷风这一改变局部气象... 南水北调中线工程自通水以来,发挥着巨大的社会和经济效益,已成为京津地区的主力水源。中线工程输水的水质理化指标相对稳定,但局部渠段存在藻类异常增殖现象,有水华爆发的风险。针对出现的藻类异常增殖问题,在通冷风这一改变局部气象条件的工程措施基础上,建立了澎河—沙河渡槽段平面二维水动力和水质模型,研究了通风位置、通风温度和通风时长等因素对输水渠道水温和藻类的影响。研究表明:水温和叶绿素a浓度均与通风位置、通风温度和通风时长有关,通风温度越低、通风时长越长,平均水温和叶绿素a浓度下降幅度越大,平均水温最高可下降约2℃,叶绿素a浓度最大可降低约54.5%,且仅上游和全渠段通风均可有效降低水温和抑制藻类生长,仅下游通风对水温和藻类的影响较小。因此,采取局部降温的方式可以起到一定的降低叶绿素a浓度的作用,综合考虑藻类抑制效果和工程成本,在水华易爆发渠段的上游通冷风是行之有效的工程措施。 展开更多
关键词 输水渠道水华 局部降温 通冷风 叶绿素A 水温 数值模拟 南水北调中线工程