One of the water source areas of the South-to-North Water Diversion Project is the Danjiangkou Reservoir (DJKR). To understand seasonal variation in phytoplankton composition, abundance and distribution in the DJKR ...One of the water source areas of the South-to-North Water Diversion Project is the Danjiangkou Reservoir (DJKR). To understand seasonal variation in phytoplankton composition, abundance and distribution in the DJKR area before water diversion, as well as to estimate potential risks of water quality after water diversion, we conducted an investigation on phytoplankton in the DJKR from August 2008 to May 2009. The investigation included 10 sampling sites, each with four depths of 0.5, 5, 10, and 20 m. In this study, 117 taxa belonging to 76 genera were identified, consisting of diatoms (39 taxa), green algae (47 taxa), blue-green algae (19 taxa), and others (12 taxa). Annual average phytoplankton abundance was 2.01×10^6 ind./L, and the highest value was 14.72 ×10^6 ind/L (at site 3 in August 2008). Phytoplankton abundance in front of the Danjiangkou Dam (DJKD) was higher than that of the Danjiang Reservoir Basin. Phytoplankton distribution showed a vertical declining trend from 0.5 m to 20 m at most sites in August 2008 (especially at sites of 1, 2, 4 and 10), but no distinct pattern in other sampling months. In December 2008 and March 2009, Stephanodiseus sp. was the most abundant species, amounting to 55.23% and 72.34%, respectively. We propose that high abundance ofStephanodiscus sp. may have contributed greatly to the frequent occurrence of Stephanodiscus sp. blooms in middle-low reaches of the Hanjiang River during the early spring of 2009. In comparison with previous studies conducted from 1992 to 2006, annual average phytoplankton density, green algae and blue-green algae species, as well as major nutrient concentrations increased, while phytoplankton diversity indices declined. This indicates a gradual decline in water quality. More research should be conducted and countermeasures taken to prevent further deterioration of water quality in the DJKR.展开更多
Recently, the critical chain study has become a hot issue in the project management research field. The construction of the critical chain with multi-resource constraints is a new research subject. According to the sy...Recently, the critical chain study has become a hot issue in the project management research field. The construction of the critical chain with multi-resource constraints is a new research subject. According to the system analysis theory and project portfolio theory, this paper discusses the creation of project portfolios based on the similarity principle and gives the definition of priority in multi-resource allocation based on quantitative analysis. A model with multi-resource constraints, which can be applied to the critical chain construction of the A-bid section in the South-to-North Water Diversion Project, was proposed. Contrast analysis with the comprehensive treatment construction method and aggressive treatment construction method was carried out. This paper also makes suggestions for further research directions and subjects, which will be useful in improving the theories in relevant research fields.展开更多
In order to analyze the indispensability of the organization management chain of the South-to-North Water Diversion Project (SNWDP), two basic forms (series connection state and mixed state of both series connectio...In order to analyze the indispensability of the organization management chain of the South-to-North Water Diversion Project (SNWDP), two basic forms (series connection state and mixed state of both series connection and parallel connection) of the organization management chain can be abstracted. The indispensability of each form has been studied and is described in this paper. Through analysis of the reliability of the two basic forms, reliability models of the organization management chain in the series connection state and the mixed state of both series connection and parallel connection have been set up.展开更多
Previous research shows that there is a strong correlation between saltwater intrusion in the Yangtze Estuary and discharge at Datong. In the near future, the discharge of the Yangtze River during dry seasons will dec...Previous research shows that there is a strong correlation between saltwater intrusion in the Yangtze Estuary and discharge at Datong. In the near future, the discharge of the Yangtze River during dry seasons will decrease due to the construction and operation of large water diversion projects, including the South-to-North Water Transfer Project, which will further exacerbate saltwater intrusion in the estuary. In this paper, a nested 1D river network model and a 2D saltwater numerical model are used to associate saltwater intrusion in the Yangtze Estuary with different values of discharge at Datong. It is concluded that 13 000 m3/s is the critical discharge at Datong for preventing saltwater intrusion and controlling the volume of water transferred by the South-to-North Water Transfer Project. Furthermore, based on the analysis of river discharge from Datong to Xuliujing and in consideration of the influence of all of the water diversion projects, operation schemes are proposed for the Eastern Route of the South-to-North Water Transfer Project for different hydrological years.展开更多
The Western Route of the South-to-North Water Diversion Project is an important trans-basin diversion project to transfer water from the upstream Yangtze River and its tributaries (water-exporting area), to the upst...The Western Route of the South-to-North Water Diversion Project is an important trans-basin diversion project to transfer water from the upstream Yangtze River and its tributaries (water-exporting area), to the upstream of the Yellow River (water- importing area). The long-term hydrologieal data from 14 stream gauging stations in the Western Route area and techniques including the pre-whitening approach, non-parametric test, Bayes, law, variance analysis extrapolation, and Wavelet Analysis are applied to identify the streamflow eharacteristics and trends, streamflow time series cross-correlations, wetness-dryness encountering probability, and periodicities that occurred over the last 50 years. The results show that the water-exporting area, water- importing area, and the streteh downstream of the water-exporting have synehronization in high-low flow relationship, whereas they display non- synchronization in long-term evolution. This corresponds to the complicated and variable climate of the plateau region. There is no obvious increasing or decreasing trend in runoff at any gauging station. The best hydrological eompensation probability for rivers where water is diverted is about 25% to lO%, and those rivers influenced significantly by diversion are the Jinsha and Yalong rivers. Proper planning and design of compensation reservoirs for the water-exporting area and stretch downstream of the water- exporting area can increase the hydrological compensation possibility from water-exporting area to the water-importing area, and reduce the impact on the stretch of river downstream of the water- exporting area.展开更多
The Middle Route of the South-to-North Water Diversion Project(MR-SNWDP)in China,with construction beginning in 2003,diverts water from Danjiangkou Reservoir to North China for residential,agriculture and industrial u...The Middle Route of the South-to-North Water Diversion Project(MR-SNWDP)in China,with construction beginning in 2003,diverts water from Danjiangkou Reservoir to North China for residential,agriculture and industrial use.The water source area of the MR-SNWDP is the region that is most sensitive to and most affected by the construction of this water diversion project.In this study,we used Landsat Thematic Mapper(TM)and HJ-1 A/B images from 2000 to 2015 by an object-based approach with a hierarchical classification method for mapping land cover in the water source area.The changes in land cover were illuminated by transfer matrixes,single dynamic degree,slope zones and fractional vegetation cover(FVC).The results indicated that the area of cropland decreased by 31%and was replaced mainly by shrub over the past 15 years,whereas forest and settlements showed continuous increases of 29.2% and 77.7%,respectively.The changes in cropland were obvious in all slope zones and decreased most remarkably(–43.8%)in the slope zone above 25°.Compared to the FVC of forest and shrub,significant improvement was exhibited in the FVC of grassland,with a growth rate of 16.6%.We concluded that local policies,including economic development,water conservation and immigration resulting from the construction of the MR-SNWDP,were the main drivers of land cover changes;notably,they stimulated the substantial and rapid expansion of settlements,doubled the wetlands and drove the transformation from cropland to settlements in immigration areas.展开更多
In terms of special geological conditions of the Western Route of South-to-North Water Transfer Project, the classification method for surrounding rocks is discussed by combining with the construction method of tunnel...In terms of special geological conditions of the Western Route of South-to-North Water Transfer Project, the classification method for surrounding rocks is discussed by combining with the construction method of tunnel boring machine (TBM). The classification standard of surrounding rocks is put forward on the basis of physical simulations and engineering practices. Damage, deformation and evolution of surrounding rocks induced by TBM excavation are discussed. Meanwhile, the long-term deformation mechanisms and stability of surrounding rocks are also studied. On this basis, a three-dimensional constitutive model for interbedded sandstone slate and a fiat shell-joint element-foundation system for calculating internal forces of segment lining are established. The deformation features of surrounding rocks of deep and steep interbedded sandstone slate and their influences on internal forces of segment lining are presented. Finally, the design methods of segment lining constructed in deep and steep flysch are proposed.展开更多
Objective To recognize and assess the impact of the South-to-north Water Transfer Project (SNWTP) on the ecological environment of Xiangfan, Hubei Province, situated in the water-out area, and develop sound scientific...Objective To recognize and assess the impact of the South-to-north Water Transfer Project (SNWTP) on the ecological environment of Xiangfan, Hubei Province, situated in the water-out area, and develop sound scientific countermeasures. Methods A three-layer BP network was built to simulate topology and process of the eco-economy system of Xiangfan. Historical data of ecological environmental factors and socio-economic factors as inputs, and corresponding historical data of ecosystem service value (ESV) and GDP as target outputs, were presented to train and test the network. When predicted input data after 2001 were presented to trained network as generalization sets, ESVs and GDPs of 2002, 2003, 2004... till 2050 were simulated as output in succession. Results Up to 2050, the area would have suffered an accumulative total ESV loss of RMB 104.9 billion, which accounted for 37.36% of the present ESV. The coinstantaneous GDP would change asynchronously with ESV, it would go through an up-to-down process and finally lose RMB89.3 billion, which accounted for 18.71% of 2001. Conclusions The simulation indicates that ESV loss means damage to the capability of socio-economic sustainable development, and suggests that artificial neural networks (ANNs) provide a feasible and effective method and have an important potential in ESV modeling.展开更多
According to the multi-project and program management theory, this paper analyzes the program generation principle and establishes a program based on progress goals. On the basis of the present situation of calculatio...According to the multi-project and program management theory, this paper analyzes the program generation principle and establishes a program based on progress goals. On the basis of the present situation of calculation of penalty for delay of the bidding section construction period with the critical path method, we studied the effects of contractor-induced delay of the bidding section construction period in detail, including the effects on the construction period of the bidding section itself, the earliest start times of the next bidding section and other subsequent bidding sections, and the construction period of the program, and then constructed a penalty model for delay of the bidding section construction period from the perspective of programs. Using the penalty model, we conducted a practical analysis of penalty for delay of the construction period of the Baoying station program in the South-to-North Water Diversion Project. The model can help determine the amount of penalty for delay of the construction period in bidding sections scientifically and reasonably,展开更多
In this paper, according to the rule of unbalanced sediment transport and the analysis of field data, different water diversion schemes were theoretically studied, including the erosion and sedimentation trend as well...In this paper, according to the rule of unbalanced sediment transport and the analysis of field data, different water diversion schemes were theoretically studied, including the erosion and sedimentation trend as well as their impacts on the environment of the middle and lower reaches of the Hanjiang River. The results showed that the 95×10 8m 3 water diversion scheme will cause less erosion and water level decrease than the 15×10 8m 3 water diversion scheme. Using a water diversion scheme of 95×10 8m 3, the decrease of water quantity can impact the river hydrodynamic regime substantially and the environments of the middle and lower reaches of the Hanjiang River will be greatly affected. It is therefore necessary to develop new water resources or build projects to meet the need of the environment and the needs for navigation.展开更多
The factors influencing the water supply price of a hydraulic project include natural conditions and economic policies. This paper thoroughly demonstrates the water price of South-to-North Water Transfer Project from ...The factors influencing the water supply price of a hydraulic project include natural conditions and economic policies. This paper thoroughly demonstrates the water price of South-to-North Water Transfer Project from the viewpoint of economic policies. It is considered that if the project is assigned as a profitable one and built depending on commercial loan from bank completely or mostly, the water price will be too high to be undertaken by users,and if the project places the public good at first while considering the economic benefit, its investment mainly relies on the state (national or local governments) appropriation and self-raised funds and a little from the bank loan on favorable terms, the price determined according to the principle of satisfying the cost and reasonable profit will be relatively lower and can be undertaken by the users in the North China where water shortage is serious. The problem of higher water price of agricultural irrigation to the north of the Yellow River can be tackled by taking measures such as "compensating agriculture by industry" according to foreign practical experiences and relevant suggestions.展开更多
Taking 13 water-receiving areas on the East Route of the South-to-North Water Diversion Project(ERSNWDP)in Shandong Province as the study area,and comparing it with Jiangsu Province on the ERSNWDP and the Middle Route...Taking 13 water-receiving areas on the East Route of the South-to-North Water Diversion Project(ERSNWDP)in Shandong Province as the study area,and comparing it with Jiangsu Province on the ERSNWDP and the Middle Route of the South-to-North(MRSNWDP),the current water-saving potential of the water-receiving areas within the municipalities of Shandong was analyzed.Different water-saving scenarios were constructed and analyzed with key water-saving indexes in various industries.These indexes include the effective utilization coefficient of farmland irrigation water,total water consumption of industrial sectors with an added value of over 10000 RMB,average leakage rate of the urban public water supply pipe network and the penetration rate of water-saving appliances.Based on the scenarios,comprehensive water-saving potential of the 13 water-receiving area cities was calculated.The results show that the water-saving potential of the study area is at a relative high level.However,some cities still have a certain amount of water-saving potential for agriculture and industry to be elevated.Under the recommended water-saving scenario,the water-saving potential is 1.134 billion m3,accounting for 5.33%of the current total water consumption,of which 460 million m3 is in agriculture,600 million m3 in industry,is and 74.20 million m3 in urban domestic sector.Comprehensive water-saving measures for the study area were proposed from the aspects of agricultural,industrial and domestic water uses.Agricultural and industrial water saving are more significant.The major cities for agricultural water saving include Jining City,Heze City,Weifang City and Jinan City;the focus cities of industrial water saving mainly include Weihai City,Jining City and Qingdao City and etc.;the key water-saving areas for urban use mainly include Zaozhuang City,Jining City and Heze City.展开更多
The over-exploitation of water resources in the Haihe River Basin (HRB) has now become a serious problem. This is clearly evidenced by the fact that many local rivers and lakes are drying up and the total amount of ...The over-exploitation of water resources in the Haihe River Basin (HRB) has now become a serious problem. This is clearly evidenced by the fact that many local rivers and lakes are drying up and the total amount of over-exploited groundwater has reached over 1000×10^8m^3. It is important to note that the exploitation of water resources in HRB was reasonable before 1979. After 1980, however, over-exploitation happened with an annual average amount of 40×10^8m^3. Both the dry season and rapid economic growth in HRB took place at the same time. Therefore, the over-exploitation of water in HRB was actually the negative result of the conjunction of a continuous dry season and rapid economic growth. So the over-exploitation would not be as serious as it is today if either of the above two stopped. After the first stage of south-to-north water transfer project, the water shortage problem in HRB could be eased for the following reasons: firstly, water transfer project will bring to the Basin 60x108m3 water resources; secondly, a wet season will come back eventually according to natural law of climate variability; finally, its agricultural and industrial use and total water consumption all have decreased from the peak value, so that the groundwater table will raise certainly and ecological water in rivers and lakes that were dried-up will be partly restored. In the future, the main problem of water resources security in HRB will include water pollution, operation risk of the south-to-north water transfer project, groundwater pollution and engineering geological hazards that may be brought by groundwater rise. The proposed countermeasures are as follows: keeping strengthening water demand management, raising water price as well as subsidies for the low- income family and improving other water related policies, preventing and dealing with water pollution seriously and getting fully prepared for the operation of south-to-north water transfer project.展开更多
Water diversion can alleviate water shortages caused by the uneven distribution of water resources.China’s Southto-North Water Diversion Project(SNWD)is the largest water diversion project worldwide.Based on the pref...Water diversion can alleviate water shortages caused by the uneven distribution of water resources.China’s Southto-North Water Diversion Project(SNWD)is the largest water diversion project worldwide.Based on the prefecturelevel data of China’s Huang-Huai-Hai Plain from 2000 to 2020,this study employs an empirical strategy of Differencesin-Differences(DID)to analyze the impact of SNWD on agricultural production.The results show that SNWD has significantly increased agricultural production,measured by the agricultural value added.The estimated results of the benchmark model remain robust when the contemporaneous policy is addressed,an alternative outcome is used,subsamples are estimated,and alternative estimation techniques are employed.This study argues that the potential impact mechanism may be that SNWD significantly increases the acreage for cash crops but reduces that for grain crops.Heterogeneity analysis shows that in prefectures with high temperature or land potential,SNWD’s impact on agricultural value added is relatively low.In contrast,in areas with prolonged sunshine or high slopes,SNWD’s impact on agricultural value added is relatively large.Given the low added value of grain crops,the government should consider strengthening food security by subsidizing water supply to sustain grain production.展开更多
This paper introduces the method of data envelopment analysis (DEA) for evaluation of the degree of harmony between water resources and economic development of the water conservancy area of China's South-to-North W...This paper introduces the method of data envelopment analysis (DEA) for evaluation of the degree of harmony between water resources and economic development of the water conservancy area of China's South-to-North Water Diversion Project (SNWDP). For this evaluation, a super-efficiency DEA (SEDEA) model was developed based on the super-efficiency method. To verify the applicability of the SEDEA model, both the SEDEA model and a normal-efficiency DEA (NEDEA) model were used to evaluate the degree of harmony between water resources and economic development of typical cities in the SNWDP water conservancy area. The results show that the SEDEA model ranks the degree of harmony of typical cities more efficiently than the NEDEA model, and thus can better evaluate the degree of harmony between water resources and economic development of different cities than the NEDEA model. Furthermore, the SEDEA model can be applied as an operational research tool in regional water resources management.展开更多
The Western Route of the South-to-North Water Transfer Project will divert water from the upper Yangtze River and its tributaries, the Dadu River and Yalong River, to the upper Yellow River. The project may ease the w...The Western Route of the South-to-North Water Transfer Project will divert water from the upper Yangtze River and its tributaries, the Dadu River and Yalong River, to the upper Yellow River. The project may ease the water shortage in the Yellow River Basin. However, it may also have some effects on the ecosystem in the upper Yangtze River Basin. Benthic invertebrates play an important role in the river ecosystem, particularly in the circulation of materials and nutrition. Benthic invertebrates are widely used to quickly assess river ecosystems because of their rapid response to changes in the water environment. The diversity of benthic invertebrates is closely associated with the aquatic habitat area. This study examined this interaction by sampling the benthic invertebrates in an expanding area. The conclusions are that the diversity of benthic invertebrates begins to decrease when the aquatic habitat area is reduced to 45% of the original area, and decreases dramatically when the aquatic habitat area is reduced to 10% of the original area. The aquatic habitat area should be kept at more than 45% of the original area in order to maintain the significant diversity of benthic invertebrates.展开更多
The unsteady flow in the Middle Route South-to-North Water Transfer Channel was simulated numerically using an implicit solution procedure for the Saint Venant equations. An equivalent roughness was used to simulate t...The unsteady flow in the Middle Route South-to-North Water Transfer Channel was simulated numerically using an implicit solution procedure for the Saint Venant equations. An equivalent roughness was used to simulate the effect of many transfer structures on the water levels in the main channel. Various gate operating and control methods were analyzed to study the response to disturbances produced by varying the flow rates through the Tianjin outlet. The results show that when the inflow at the head changes in the same way as the sum of the flow rates through all the outlets, the transition time and the fluctuation of the water levels using the timed gate operation method are less than when using the simultaneous gate operation method, but the variations of the gate openings and flow rates through each control gate are much larger. The flow disturbances produced by the Tianjin outlet can be rectified within several channel sections and the transition time can be greatly shortened by allowing the water levels immediately upstream of the control gates to vary within proscribed ranges, rather than being held constant.展开更多
基金Supported by the National Basic Research Program of China (973 Program) (No. 2008CB418006)the Knowledge Innovation Program of Chinese Academy of Sciences (No. KZCX-YW-14-1)
文摘One of the water source areas of the South-to-North Water Diversion Project is the Danjiangkou Reservoir (DJKR). To understand seasonal variation in phytoplankton composition, abundance and distribution in the DJKR area before water diversion, as well as to estimate potential risks of water quality after water diversion, we conducted an investigation on phytoplankton in the DJKR from August 2008 to May 2009. The investigation included 10 sampling sites, each with four depths of 0.5, 5, 10, and 20 m. In this study, 117 taxa belonging to 76 genera were identified, consisting of diatoms (39 taxa), green algae (47 taxa), blue-green algae (19 taxa), and others (12 taxa). Annual average phytoplankton abundance was 2.01×10^6 ind./L, and the highest value was 14.72 ×10^6 ind/L (at site 3 in August 2008). Phytoplankton abundance in front of the Danjiangkou Dam (DJKD) was higher than that of the Danjiang Reservoir Basin. Phytoplankton distribution showed a vertical declining trend from 0.5 m to 20 m at most sites in August 2008 (especially at sites of 1, 2, 4 and 10), but no distinct pattern in other sampling months. In December 2008 and March 2009, Stephanodiseus sp. was the most abundant species, amounting to 55.23% and 72.34%, respectively. We propose that high abundance ofStephanodiscus sp. may have contributed greatly to the frequent occurrence of Stephanodiscus sp. blooms in middle-low reaches of the Hanjiang River during the early spring of 2009. In comparison with previous studies conducted from 1992 to 2006, annual average phytoplankton density, green algae and blue-green algae species, as well as major nutrient concentrations increased, while phytoplankton diversity indices declined. This indicates a gradual decline in water quality. More research should be conducted and countermeasures taken to prevent further deterioration of water quality in the DJKR.
基金supported by the National Science and Technology Plan (Major Project of the Eleventh Five-Year Plan,Grant No. 2006BAB04A13)the Philosophy and Social Science Fund of the Education Department of Jiangsu Province (Grant No.07SJD630006)+2 种基金the Third Key Discipline (Techno-Economics and Management) of the 211 Projectthe Key Discipline of Jiangsu Province (Engineering and Project Management)the Office of the South-to-North Water Diversion Project Construction Committee under the State Council
文摘Recently, the critical chain study has become a hot issue in the project management research field. The construction of the critical chain with multi-resource constraints is a new research subject. According to the system analysis theory and project portfolio theory, this paper discusses the creation of project portfolios based on the similarity principle and gives the definition of priority in multi-resource allocation based on quantitative analysis. A model with multi-resource constraints, which can be applied to the critical chain construction of the A-bid section in the South-to-North Water Diversion Project, was proposed. Contrast analysis with the comprehensive treatment construction method and aggressive treatment construction method was carried out. This paper also makes suggestions for further research directions and subjects, which will be useful in improving the theories in relevant research fields.
基金supported by the National Science and Technology Plan(Major Project of the Eleventh Five-Year Plan,Grant No.2006BAB04A13)
文摘In order to analyze the indispensability of the organization management chain of the South-to-North Water Diversion Project (SNWDP), two basic forms (series connection state and mixed state of both series connection and parallel connection) of the organization management chain can be abstracted. The indispensability of each form has been studied and is described in this paper. Through analysis of the reliability of the two basic forms, reliability models of the organization management chain in the series connection state and the mixed state of both series connection and parallel connection have been set up.
基金supported by the National Natural Science Foundation of China (Grant No 50339010)
文摘Previous research shows that there is a strong correlation between saltwater intrusion in the Yangtze Estuary and discharge at Datong. In the near future, the discharge of the Yangtze River during dry seasons will decrease due to the construction and operation of large water diversion projects, including the South-to-North Water Transfer Project, which will further exacerbate saltwater intrusion in the estuary. In this paper, a nested 1D river network model and a 2D saltwater numerical model are used to associate saltwater intrusion in the Yangtze Estuary with different values of discharge at Datong. It is concluded that 13 000 m3/s is the critical discharge at Datong for preventing saltwater intrusion and controlling the volume of water transferred by the South-to-North Water Transfer Project. Furthermore, based on the analysis of river discharge from Datong to Xuliujing and in consideration of the influence of all of the water diversion projects, operation schemes are proposed for the Eastern Route of the South-to-North Water Transfer Project for different hydrological years.
基金supported by the China Meteorological Data Sharing Service System,the Bureau of Hydrology,and Water Resources of Sichuan Province,China
文摘The Western Route of the South-to-North Water Diversion Project is an important trans-basin diversion project to transfer water from the upstream Yangtze River and its tributaries (water-exporting area), to the upstream of the Yellow River (water- importing area). The long-term hydrologieal data from 14 stream gauging stations in the Western Route area and techniques including the pre-whitening approach, non-parametric test, Bayes, law, variance analysis extrapolation, and Wavelet Analysis are applied to identify the streamflow eharacteristics and trends, streamflow time series cross-correlations, wetness-dryness encountering probability, and periodicities that occurred over the last 50 years. The results show that the water-exporting area, water- importing area, and the streteh downstream of the water-exporting have synehronization in high-low flow relationship, whereas they display non- synchronization in long-term evolution. This corresponds to the complicated and variable climate of the plateau region. There is no obvious increasing or decreasing trend in runoff at any gauging station. The best hydrological eompensation probability for rivers where water is diverted is about 25% to lO%, and those rivers influenced significantly by diversion are the Jinsha and Yalong rivers. Proper planning and design of compensation reservoirs for the water-exporting area and stretch downstream of the water- exporting area can increase the hydrological compensation possibility from water-exporting area to the water-importing area, and reduce the impact on the stretch of river downstream of the water- exporting area.
基金Under the auspices of the National Key Research and Development Program of China(No.2016YFC0500201-01)National Natural Science Foundation of China(No.41671365,41771464)the Annual Project of the Office of the South-to-North Water Diversion Project(No.2018-21)
文摘The Middle Route of the South-to-North Water Diversion Project(MR-SNWDP)in China,with construction beginning in 2003,diverts water from Danjiangkou Reservoir to North China for residential,agriculture and industrial use.The water source area of the MR-SNWDP is the region that is most sensitive to and most affected by the construction of this water diversion project.In this study,we used Landsat Thematic Mapper(TM)and HJ-1 A/B images from 2000 to 2015 by an object-based approach with a hierarchical classification method for mapping land cover in the water source area.The changes in land cover were illuminated by transfer matrixes,single dynamic degree,slope zones and fractional vegetation cover(FVC).The results indicated that the area of cropland decreased by 31%and was replaced mainly by shrub over the past 15 years,whereas forest and settlements showed continuous increases of 29.2% and 77.7%,respectively.The changes in cropland were obvious in all slope zones and decreased most remarkably(–43.8%)in the slope zone above 25°.Compared to the FVC of forest and shrub,significant improvement was exhibited in the FVC of grassland,with a growth rate of 16.6%.We concluded that local policies,including economic development,water conservation and immigration resulting from the construction of the MR-SNWDP,were the main drivers of land cover changes;notably,they stimulated the substantial and rapid expansion of settlements,doubled the wetlands and drove the transformation from cropland to settlements in immigration areas.
基金Supported by the National Key Technology R&D Program in the 11th Five-year Plan of China (2006BAB04A06)
文摘In terms of special geological conditions of the Western Route of South-to-North Water Transfer Project, the classification method for surrounding rocks is discussed by combining with the construction method of tunnel boring machine (TBM). The classification standard of surrounding rocks is put forward on the basis of physical simulations and engineering practices. Damage, deformation and evolution of surrounding rocks induced by TBM excavation are discussed. Meanwhile, the long-term deformation mechanisms and stability of surrounding rocks are also studied. On this basis, a three-dimensional constitutive model for interbedded sandstone slate and a fiat shell-joint element-foundation system for calculating internal forces of segment lining are established. The deformation features of surrounding rocks of deep and steep interbedded sandstone slate and their influences on internal forces of segment lining are presented. Finally, the design methods of segment lining constructed in deep and steep flysch are proposed.
文摘Objective To recognize and assess the impact of the South-to-north Water Transfer Project (SNWTP) on the ecological environment of Xiangfan, Hubei Province, situated in the water-out area, and develop sound scientific countermeasures. Methods A three-layer BP network was built to simulate topology and process of the eco-economy system of Xiangfan. Historical data of ecological environmental factors and socio-economic factors as inputs, and corresponding historical data of ecosystem service value (ESV) and GDP as target outputs, were presented to train and test the network. When predicted input data after 2001 were presented to trained network as generalization sets, ESVs and GDPs of 2002, 2003, 2004... till 2050 were simulated as output in succession. Results Up to 2050, the area would have suffered an accumulative total ESV loss of RMB 104.9 billion, which accounted for 37.36% of the present ESV. The coinstantaneous GDP would change asynchronously with ESV, it would go through an up-to-down process and finally lose RMB89.3 billion, which accounted for 18.71% of 2001. Conclusions The simulation indicates that ESV loss means damage to the capability of socio-economic sustainable development, and suggests that artificial neural networks (ANNs) provide a feasible and effective method and have an important potential in ESV modeling.
基金supported by the National Science and Technology Plan of China (Major Project of the Eleventh Five-Year Plan, Grant No. 2006BAB04A13)the Philosophy and Social Science Fund of Education Department of Jiangsu Province (Grant No. 07SJD630006)+1 种基金the Third Key Discipline (Techno-Economics and Management) of the Project 211the Key Disciplines of Jiangsu Province (Engineering and Project Management)
文摘According to the multi-project and program management theory, this paper analyzes the program generation principle and establishes a program based on progress goals. On the basis of the present situation of calculation of penalty for delay of the bidding section construction period with the critical path method, we studied the effects of contractor-induced delay of the bidding section construction period in detail, including the effects on the construction period of the bidding section itself, the earliest start times of the next bidding section and other subsequent bidding sections, and the construction period of the program, and then constructed a penalty model for delay of the bidding section construction period from the perspective of programs. Using the penalty model, we conducted a practical analysis of penalty for delay of the construction period of the Baoying station program in the South-to-North Water Diversion Project. The model can help determine the amount of penalty for delay of the construction period in bidding sections scientifically and reasonably,
文摘In this paper, according to the rule of unbalanced sediment transport and the analysis of field data, different water diversion schemes were theoretically studied, including the erosion and sedimentation trend as well as their impacts on the environment of the middle and lower reaches of the Hanjiang River. The results showed that the 95×10 8m 3 water diversion scheme will cause less erosion and water level decrease than the 15×10 8m 3 water diversion scheme. Using a water diversion scheme of 95×10 8m 3, the decrease of water quantity can impact the river hydrodynamic regime substantially and the environments of the middle and lower reaches of the Hanjiang River will be greatly affected. It is therefore necessary to develop new water resources or build projects to meet the need of the environment and the needs for navigation.
文摘The factors influencing the water supply price of a hydraulic project include natural conditions and economic policies. This paper thoroughly demonstrates the water price of South-to-North Water Transfer Project from the viewpoint of economic policies. It is considered that if the project is assigned as a profitable one and built depending on commercial loan from bank completely or mostly, the water price will be too high to be undertaken by users,and if the project places the public good at first while considering the economic benefit, its investment mainly relies on the state (national or local governments) appropriation and self-raised funds and a little from the bank loan on favorable terms, the price determined according to the principle of satisfying the cost and reasonable profit will be relatively lower and can be undertaken by the users in the North China where water shortage is serious. The problem of higher water price of agricultural irrigation to the north of the Yellow River can be tackled by taking measures such as "compensating agriculture by industry" according to foreign practical experiences and relevant suggestions.
基金We would like to give our thanks to Water Resources Department of Shandong Province and Water Resources Research Institute of Shandong Province for their help.
文摘Taking 13 water-receiving areas on the East Route of the South-to-North Water Diversion Project(ERSNWDP)in Shandong Province as the study area,and comparing it with Jiangsu Province on the ERSNWDP and the Middle Route of the South-to-North(MRSNWDP),the current water-saving potential of the water-receiving areas within the municipalities of Shandong was analyzed.Different water-saving scenarios were constructed and analyzed with key water-saving indexes in various industries.These indexes include the effective utilization coefficient of farmland irrigation water,total water consumption of industrial sectors with an added value of over 10000 RMB,average leakage rate of the urban public water supply pipe network and the penetration rate of water-saving appliances.Based on the scenarios,comprehensive water-saving potential of the 13 water-receiving area cities was calculated.The results show that the water-saving potential of the study area is at a relative high level.However,some cities still have a certain amount of water-saving potential for agriculture and industry to be elevated.Under the recommended water-saving scenario,the water-saving potential is 1.134 billion m3,accounting for 5.33%of the current total water consumption,of which 460 million m3 is in agriculture,600 million m3 in industry,is and 74.20 million m3 in urban domestic sector.Comprehensive water-saving measures for the study area were proposed from the aspects of agricultural,industrial and domestic water uses.Agricultural and industrial water saving are more significant.The major cities for agricultural water saving include Jining City,Heze City,Weifang City and Jinan City;the focus cities of industrial water saving mainly include Weihai City,Jining City and Qingdao City and etc.;the key water-saving areas for urban use mainly include Zaozhuang City,Jining City and Heze City.
基金supported by the National Natural Sciences Fund of China (40971298)
文摘The over-exploitation of water resources in the Haihe River Basin (HRB) has now become a serious problem. This is clearly evidenced by the fact that many local rivers and lakes are drying up and the total amount of over-exploited groundwater has reached over 1000×10^8m^3. It is important to note that the exploitation of water resources in HRB was reasonable before 1979. After 1980, however, over-exploitation happened with an annual average amount of 40×10^8m^3. Both the dry season and rapid economic growth in HRB took place at the same time. Therefore, the over-exploitation of water in HRB was actually the negative result of the conjunction of a continuous dry season and rapid economic growth. So the over-exploitation would not be as serious as it is today if either of the above two stopped. After the first stage of south-to-north water transfer project, the water shortage problem in HRB could be eased for the following reasons: firstly, water transfer project will bring to the Basin 60x108m3 water resources; secondly, a wet season will come back eventually according to natural law of climate variability; finally, its agricultural and industrial use and total water consumption all have decreased from the peak value, so that the groundwater table will raise certainly and ecological water in rivers and lakes that were dried-up will be partly restored. In the future, the main problem of water resources security in HRB will include water pollution, operation risk of the south-to-north water transfer project, groundwater pollution and engineering geological hazards that may be brought by groundwater rise. The proposed countermeasures are as follows: keeping strengthening water demand management, raising water price as well as subsidies for the low- income family and improving other water related policies, preventing and dealing with water pollution seriously and getting fully prepared for the operation of south-to-north water transfer project.
基金supported by the Ministry of Agriculture and Rural Affairs of China(202207211210319)。
文摘Water diversion can alleviate water shortages caused by the uneven distribution of water resources.China’s Southto-North Water Diversion Project(SNWD)is the largest water diversion project worldwide.Based on the prefecturelevel data of China’s Huang-Huai-Hai Plain from 2000 to 2020,this study employs an empirical strategy of Differencesin-Differences(DID)to analyze the impact of SNWD on agricultural production.The results show that SNWD has significantly increased agricultural production,measured by the agricultural value added.The estimated results of the benchmark model remain robust when the contemporaneous policy is addressed,an alternative outcome is used,subsamples are estimated,and alternative estimation techniques are employed.This study argues that the potential impact mechanism may be that SNWD significantly increases the acreage for cash crops but reduces that for grain crops.Heterogeneity analysis shows that in prefectures with high temperature or land potential,SNWD’s impact on agricultural value added is relatively low.In contrast,in areas with prolonged sunshine or high slopes,SNWD’s impact on agricultural value added is relatively large.Given the low added value of grain crops,the government should consider strengthening food security by subsidizing water supply to sustain grain production.
基金supported by the Fundamental Research Funds for the Central Universities (Grant No. 2010B25814)the Philosophy and Social Science Foundation of Hohai University (Grant No. 2007402011)+1 种基金the Philosophy and Social Science Foundation of Jiangsu Province (Grant No. 07EYC059)a special project of the Ministry of Water Resources of the People's Republic of China (Grant No. 5006518023)
文摘This paper introduces the method of data envelopment analysis (DEA) for evaluation of the degree of harmony between water resources and economic development of the water conservancy area of China's South-to-North Water Diversion Project (SNWDP). For this evaluation, a super-efficiency DEA (SEDEA) model was developed based on the super-efficiency method. To verify the applicability of the SEDEA model, both the SEDEA model and a normal-efficiency DEA (NEDEA) model were used to evaluate the degree of harmony between water resources and economic development of typical cities in the SNWDP water conservancy area. The results show that the SEDEA model ranks the degree of harmony of typical cities more efficiently than the NEDEA model, and thus can better evaluate the degree of harmony between water resources and economic development of different cities than the NEDEA model. Furthermore, the SEDEA model can be applied as an operational research tool in regional water resources management.
基金supported by the National Hi-Tech Research and Development Program of China ("863" Project) (Grant No. 2006BAB04A08)the National Natural Science Foundation of China (Grant No. 50779027)
文摘The Western Route of the South-to-North Water Transfer Project will divert water from the upper Yangtze River and its tributaries, the Dadu River and Yalong River, to the upper Yellow River. The project may ease the water shortage in the Yellow River Basin. However, it may also have some effects on the ecosystem in the upper Yangtze River Basin. Benthic invertebrates play an important role in the river ecosystem, particularly in the circulation of materials and nutrition. Benthic invertebrates are widely used to quickly assess river ecosystems because of their rapid response to changes in the water environment. The diversity of benthic invertebrates is closely associated with the aquatic habitat area. This study examined this interaction by sampling the benthic invertebrates in an expanding area. The conclusions are that the diversity of benthic invertebrates begins to decrease when the aquatic habitat area is reduced to 45% of the original area, and decreases dramatically when the aquatic habitat area is reduced to 10% of the original area. The aquatic habitat area should be kept at more than 45% of the original area in order to maintain the significant diversity of benthic invertebrates.
基金this study was supported by the National Basic Research Program of China(2010CB428406)National Key Technology R&D Program of China(Grant No.2006BAB04A09)the National Science Foundation of P.R.China(Grant No.50939001 and 51079004)
基金Supported by China Postdoctoral Science Foundation (No. 20060390078)
文摘The unsteady flow in the Middle Route South-to-North Water Transfer Channel was simulated numerically using an implicit solution procedure for the Saint Venant equations. An equivalent roughness was used to simulate the effect of many transfer structures on the water levels in the main channel. Various gate operating and control methods were analyzed to study the response to disturbances produced by varying the flow rates through the Tianjin outlet. The results show that when the inflow at the head changes in the same way as the sum of the flow rates through all the outlets, the transition time and the fluctuation of the water levels using the timed gate operation method are less than when using the simultaneous gate operation method, but the variations of the gate openings and flow rates through each control gate are much larger. The flow disturbances produced by the Tianjin outlet can be rectified within several channel sections and the transition time can be greatly shortened by allowing the water levels immediately upstream of the control gates to vary within proscribed ranges, rather than being held constant.