To get the influence of the randomness of longitudinal resistance of ballast bed (LRBB) on track-bridge interaction, the statistical law of LRBB was studied with existing test data and the Shapiro-Wilk test. Based on ...To get the influence of the randomness of longitudinal resistance of ballast bed (LRBB) on track-bridge interaction, the statistical law of LRBB was studied with existing test data and the Shapiro-Wilk test. Based on the principle of track-bridge interaction, a rail-sleeper-bridge-pier integrated simulation model that could consider the randomness of LRBB was established. Taking a continuous beam bridge for the heavy-haul railway as an example, the effect of the randomness of LRBB on the mechanical behavior of continuous welded rail (CWR) on bridges under typical conditions was carefully examined with a random sampling method and the simulation model. The results show that the LRBB corresponding sleeper displacement of 2 mm obeys a normal distribution. When the randomness of LRBB is considered, the amplitudes of rail expansion force, rail bending force, rail braking force and rail broken gap all follow normal distribution. As the standard deviations of the four indexes are small, which indicates the randomness of LRBB has little effect on track-bridge interaction. The distributions of the four indexes make it possible to design CWR on bridges with the limit state method.展开更多
Considering arch rib, lateral brace, suspender, girder, pier and track position, the model for the interaction between long-span tied arch continuous bridge and multiple tracks was established by using steel-concrete ...Considering arch rib, lateral brace, suspender, girder, pier and track position, the model for the interaction between long-span tied arch continuous bridge and multiple tracks was established by using steel-concrete composite section beam element to simulate concrete-filled steel tube(CFST) arch rib, using the beam element with rigid arm to simulate the prestressed concrete girder and using nonlinear bar element to simulate longitudinal constraint between track and bridge. Taking a(77+3×156.8+77) m tied arch continuous bridge with four tracks on the Harbin-Qiqihar Passenger Dedicated Line as an example, the arrangement of continuously welded rail(CWR) was explored. The longitudinal force in CWR on the tied arch continuous bridge, the pier top horizontal force and torque due to the unbalance load case, were analyzed under the action of temperature, vertical live load, train braking and wind load.Studies show that, it can significantly reduce track displacement to set the track expansion devices at main span arch springing on both sides; the track stress due to arch temperature variation can reach 40.8 MPa; the track stress, pier top horizontal force and torque are related to the number of loaded tracks and train running direction, and the bending force applied to unloaded track is close to the loaded track, while the braking force applied to unloaded track is 1/4 to 1/2 of the loaded track; the longitudinal force of track due to the wind load is up to 12.4 MPa, which should be considered.展开更多
文摘To get the influence of the randomness of longitudinal resistance of ballast bed (LRBB) on track-bridge interaction, the statistical law of LRBB was studied with existing test data and the Shapiro-Wilk test. Based on the principle of track-bridge interaction, a rail-sleeper-bridge-pier integrated simulation model that could consider the randomness of LRBB was established. Taking a continuous beam bridge for the heavy-haul railway as an example, the effect of the randomness of LRBB on the mechanical behavior of continuous welded rail (CWR) on bridges under typical conditions was carefully examined with a random sampling method and the simulation model. The results show that the LRBB corresponding sleeper displacement of 2 mm obeys a normal distribution. When the randomness of LRBB is considered, the amplitudes of rail expansion force, rail bending force, rail braking force and rail broken gap all follow normal distribution. As the standard deviations of the four indexes are small, which indicates the randomness of LRBB has little effect on track-bridge interaction. The distributions of the four indexes make it possible to design CWR on bridges with the limit state method.
基金Project(51378503)supported by the National Natural Science Foundation of ChinaProject(2014M552158)supported by China Postdoctoral Science Foundation
文摘Considering arch rib, lateral brace, suspender, girder, pier and track position, the model for the interaction between long-span tied arch continuous bridge and multiple tracks was established by using steel-concrete composite section beam element to simulate concrete-filled steel tube(CFST) arch rib, using the beam element with rigid arm to simulate the prestressed concrete girder and using nonlinear bar element to simulate longitudinal constraint between track and bridge. Taking a(77+3×156.8+77) m tied arch continuous bridge with four tracks on the Harbin-Qiqihar Passenger Dedicated Line as an example, the arrangement of continuously welded rail(CWR) was explored. The longitudinal force in CWR on the tied arch continuous bridge, the pier top horizontal force and torque due to the unbalance load case, were analyzed under the action of temperature, vertical live load, train braking and wind load.Studies show that, it can significantly reduce track displacement to set the track expansion devices at main span arch springing on both sides; the track stress due to arch temperature variation can reach 40.8 MPa; the track stress, pier top horizontal force and torque are related to the number of loaded tracks and train running direction, and the bending force applied to unloaded track is close to the loaded track, while the braking force applied to unloaded track is 1/4 to 1/2 of the loaded track; the longitudinal force of track due to the wind load is up to 12.4 MPa, which should be considered.