According to the multi-project and program management theory, this paper analyzes the program generation principle and establishes a program based on progress goals. On the basis of the present situation of calculatio...According to the multi-project and program management theory, this paper analyzes the program generation principle and establishes a program based on progress goals. On the basis of the present situation of calculation of penalty for delay of the bidding section construction period with the critical path method, we studied the effects of contractor-induced delay of the bidding section construction period in detail, including the effects on the construction period of the bidding section itself, the earliest start times of the next bidding section and other subsequent bidding sections, and the construction period of the program, and then constructed a penalty model for delay of the bidding section construction period from the perspective of programs. Using the penalty model, we conducted a practical analysis of penalty for delay of the construction period of the Baoying station program in the South-to-North Water Diversion Project. The model can help determine the amount of penalty for delay of the construction period in bidding sections scientifically and reasonably,展开更多
1 Project overview The Beijing–Shanghai High Speed Railway(HSR)represents a major national strategic transportation project in China that is characterized by the largest-scale one-time investment in the country.At th...1 Project overview The Beijing–Shanghai High Speed Railway(HSR)represents a major national strategic transportation project in China that is characterized by the largest-scale one-time investment in the country.At the time,it was the longest HSR constructed in a single phase,with the highest technical standards in the world.Acting as an HSR artery between the Northern and Eastern regions of China,the Beijing–Shanghai HSR is the busiest HSR with the highest ridership in the country and the world at large.Additionally,it is the only commercial HSR consistently operates at a speed of 350 km/h globally.展开更多
Design Units: CCCC Highway Consultants Co., Ltd.; China Zhongtie Major Bridge Reconnaissance & Design Institute Co., Ltd. Construction Units: China Communications Construction Company Limited Consortium; China Rai...Design Units: CCCC Highway Consultants Co., Ltd.; China Zhongtie Major Bridge Reconnaissance & Design Institute Co., Ltd. Construction Units: China Communications Construction Company Limited Consortium; China Railway Shanhaiguan Bridge Group Co., Ltd.; Wuhan Heavy Engineering Co., Ltd.; CCCC First Harbor Engineering Company Ltd. Consortium; Guangdong Changda High- way Engineering Co., Ltd.; China ZhongTie Major Bridge Engineering Group Co., Ltd. Consortium; Chongqing Zhixiang Paving Technology Engineering Co., Ltd.; Hunan Construction Engineering Group; China Railway Electrification Bureau Group Co., Ltd. Consortium展开更多
基金supported by the National Science and Technology Plan of China (Major Project of the Eleventh Five-Year Plan, Grant No. 2006BAB04A13)the Philosophy and Social Science Fund of Education Department of Jiangsu Province (Grant No. 07SJD630006)+1 种基金the Third Key Discipline (Techno-Economics and Management) of the Project 211the Key Disciplines of Jiangsu Province (Engineering and Project Management)
文摘According to the multi-project and program management theory, this paper analyzes the program generation principle and establishes a program based on progress goals. On the basis of the present situation of calculation of penalty for delay of the bidding section construction period with the critical path method, we studied the effects of contractor-induced delay of the bidding section construction period in detail, including the effects on the construction period of the bidding section itself, the earliest start times of the next bidding section and other subsequent bidding sections, and the construction period of the program, and then constructed a penalty model for delay of the bidding section construction period from the perspective of programs. Using the penalty model, we conducted a practical analysis of penalty for delay of the construction period of the Baoying station program in the South-to-North Water Diversion Project. The model can help determine the amount of penalty for delay of the construction period in bidding sections scientifically and reasonably,
文摘1 Project overview The Beijing–Shanghai High Speed Railway(HSR)represents a major national strategic transportation project in China that is characterized by the largest-scale one-time investment in the country.At the time,it was the longest HSR constructed in a single phase,with the highest technical standards in the world.Acting as an HSR artery between the Northern and Eastern regions of China,the Beijing–Shanghai HSR is the busiest HSR with the highest ridership in the country and the world at large.Additionally,it is the only commercial HSR consistently operates at a speed of 350 km/h globally.
文摘Design Units: CCCC Highway Consultants Co., Ltd.; China Zhongtie Major Bridge Reconnaissance & Design Institute Co., Ltd. Construction Units: China Communications Construction Company Limited Consortium; China Railway Shanhaiguan Bridge Group Co., Ltd.; Wuhan Heavy Engineering Co., Ltd.; CCCC First Harbor Engineering Company Ltd. Consortium; Guangdong Changda High- way Engineering Co., Ltd.; China ZhongTie Major Bridge Engineering Group Co., Ltd. Consortium; Chongqing Zhixiang Paving Technology Engineering Co., Ltd.; Hunan Construction Engineering Group; China Railway Electrification Bureau Group Co., Ltd. Consortium