During the construction of cast-in-place piles in warm permafrost,the heat carried by concrete and the cement hydration reaction can cause strong thermal disturbance to the surrounding permafrost.Since the bearing cap...During the construction of cast-in-place piles in warm permafrost,the heat carried by concrete and the cement hydration reaction can cause strong thermal disturbance to the surrounding permafrost.Since the bearing capacity of the pile is quite small before the full freeze-back,the quick refreezing of the native soils surrounding the cast-in-place pile has become the focus of the infrastructure construction in permafrost.To solve this problem,this paper innovatively puts forward the application of the artificial ground freezing(AGF)method at the end of the curing period of cast-in-place piles in permafrost.A field test on the AGF was conducted at the Beiluhe Observation and Research Station of Frozen Soil Engineering and Environment(34°51.2'N,92°56.4'E)in the Qinghai Tibet Plateau(QTP),and then a 3-D numerical model was established to investigate the thermal performance of piles using AGF under different engineering conditions.Additionally,the long-term thermal performance of piles after the completion of AGF under different conditions was estimated.Field experiment results demonstrate that AGF is an effective method to reduce the refreezing time of the soil surrounding the piles constructed in permafrost terrain,with the ability to reduce the pile-soil interface temperatures to below the natural ground temperature within 3 days.Numerical results further prove that AGF still has a good cooling effect even under unfavorable engineering conditions such as high pouring temperature,large pile diameter,and large pile length.Consequently,the application of this method is meaningful to save the subsequent latency time and solve the problem of thermal disturbance in pile construction in permafrost.The research results are highly relevant for the spread of AGF technology and the rapid building of pile foundations in permafrost.展开更多
In the construction of the Qinghai-Tibet Power Transmission Line (QTPTL), cast-in-place piles (CIPPs) are widely applied in areas with unfavorable geological conditions. The thermal regime around piles in permafro...In the construction of the Qinghai-Tibet Power Transmission Line (QTPTL), cast-in-place piles (CIPPs) are widely applied in areas with unfavorable geological conditions. The thermal regime around piles in permafrost regions greatly affects the stability of the towers as well as the operation of the QTPTL. The casting of piles will markedly affect the thermal regime of the surrounding permafrost because of the casting temperature and the hydration heat of cement. Based on the typical geological and engineering conditions along the QTPTL, thermal disturbance ofa CIPP to surrounding permafrost under different casting seasons, pile depths, and casting temperatures were simulated. The results show that the casting season (summer versus winter) can influence the refreezing process of CIPPs, within the first 6 m of pile depth. Sixty days after being cast, CIPPs greater than 6 m in depth can be frozen regardless of which season they were cast, and the foundation could be reffozen after a cold season. Comparing the refreezing characteristics of CIPPs cast in different seasons also showed that, without considering the ground surface conditions, warm seasons are more suitable for casting piles. With the increase of pile depth, the thermal effect of a CIPP on the surrounding soil mainly expands vertically, while the lateral heat disturbance changes little. Deeper, longer CIPPs have better stability. The casting temperature clearly affects the thermal disturbance, and the radius of the melting circle increases with rising casting temperature. The optimal casting temperature is between 2 ℃ and 9 ℃.展开更多
Many staircases in reinforced concrete (RC) frame structures suffered severe damage during the Wenchuan earthquake. Elastic analyses for 18 RC structure models with and without staircases are conducted and compared ...Many staircases in reinforced concrete (RC) frame structures suffered severe damage during the Wenchuan earthquake. Elastic analyses for 18 RC structure models with and without staircases are conducted and compared to study the influence of the staircase on the stiffness, displacements and internal forces of the structures. To capture the yielding development and damage mechanism of frame structures, elasto-plastic analysis is carried out for one of the 18 models. Based on the features observed in the analyses, a new type of staircase design i.e., isolating them from the master structure to eliminate the effect of K-type struts, is proposed and discussed. It is concluded that the proposed method of staircase isolation is effective and feasible for engineering design, and does not significantly increase the construction cost.展开更多
Similar to free-standing pile groups, piled raft foundations are conventionally designed in which the piles carry the total load of structure and the raft bearing capacity is not taken into account. Numerous studies i...Similar to free-standing pile groups, piled raft foundations are conventionally designed in which the piles carry the total load of structure and the raft bearing capacity is not taken into account. Numerous studies indicated that this method is too conservative. Only when the pile cap is elevated from the ground level,the raft bearing contribution can be neglected. In a piled raft foundation, pileesoileraft interaction is complicated. Although several numerical studies have been carried out to analyze the behaviors of piled raft foundations, very few experimental studies are reported in the literature. The available laboratory studies mainly focused on steel piles. The present study aims to compare the behaviors of piled raft foundations with free-standing pile groups in sand, using laboratory physical models. Cast-in-place concrete piles and concrete raft are used for the tests. The tests are conducted on single pile, single pile in pile group, unpiled raft, free-standing pile group and piled raft foundation. We examine the effects of the number of piles, the pile installation method and the interaction between different components of foundation. The results indicate that the ultimate bearing capacity of the piled raft foundation is considerably higher than that of the free-standing pile group with the same number of piles. With installation of the single pile in the group, the pile bearing capacity and stiffness increase. Installation of the piles beneath the raft decreases the bearing capacity of the raft. When the raft bearing capacity is not included in the design process, the allowable bearing capacity of the piled raft is underestimated by more than 200%. This deviation intensifies with increasing spacing of the piles.展开更多
The bearing capacity of pile foundations is affected by the temperature of the frozen soil around pile foundations.The construction process and the hydration heat of cast-in-place(CIP)pile foundations affect the therm...The bearing capacity of pile foundations is affected by the temperature of the frozen soil around pile foundations.The construction process and the hydration heat of cast-in-place(CIP)pile foundations affect the thermal stability of permafrost.In this paper,temperature data from inside multiple CIP piles,borehole observations of ground thermal status adjacent to the foundations and local weather stations were monitored in warm permafrost regions to study the thermal influence process of CIP pile foundations.The following conclusions are drawn from the field observation data.(1)The early temperature change process of different CIP piles is different,and the differences gradually diminish over time.(2)The initial concrete temperature is linearly related with the air temperature,net radiation and wind speed within 1 h before the completion of concrete pouring;the contributions of the air temperature,net radiation,and wind speed to the initial concrete temperature are 51.9%,20.3%and 27.9%,respectively.(3)The outer boundary of the thermal disturbance annulus is approximately 2 m away from the pile center.It took more than 224 days for the soil around the CIP piles to return to the natural permafrost temperature at the study site.展开更多
This thorough review explores the complexities of geotechnical engineering, emphasizing soil-structure interaction (SSI). The investigation centers on sheet pile design, examining two primary methodologies: Limit Equi...This thorough review explores the complexities of geotechnical engineering, emphasizing soil-structure interaction (SSI). The investigation centers on sheet pile design, examining two primary methodologies: Limit Equilibrium Methods (LEM) and Soil-Structure Interaction Methods (SSIM). While LEM methods, grounded in classical principles, provide valuable insights for preliminary design considerations, they may encounter limitations in addressing real-world complexities. In contrast, SSIM methods, including the SSI-SR approach, introduce precision and depth to the field. By employing numerical techniques such as Finite Element (FE) and Finite Difference (FD) analyses, these methods enable engineers to navigate the dynamics of soil-structure interaction. The exploration extends to SSI-FE, highlighting its essential role in civil engineering. By integrating Finite Element analysis with considerations for soil-structure interaction, the SSI-FE method offers a holistic understanding of how structures dynamically interact with their geotechnical environment. Throughout this exploration, the study dissects critical components governing SSIM methods, providing engineers with tools to navigate the intricate landscape of geotechnical design. The study acknowledges the significance of the Mohr-Coulomb constitutive model while recognizing its limitations, and guiding practitioners toward informed decision-making in geotechnical analyses. As the article concludes, it underscores the importance of continuous learning and innovation for the future of geotechnical engineering. With advancing technology and an evolving understanding of soil-structure interaction, the study remains committed to ensuring the safety, stability, and efficiency of geotechnical structures through cutting-edge design and analysis techniques.展开更多
The compositions, technical principles and construction equipments of a new piling method used for ground improvement plastic tube cast-in-place concrete pile were introduced. The results from static load tests on sin...The compositions, technical principles and construction equipments of a new piling method used for ground improvement plastic tube cast-in-place concrete pile were introduced. The results from static load tests on single piles with different forms of pile shoes and on their composite foundations were analyzed. The distribution patterns of axial force, shaft friction and toe resistance were studied based on the measurements taken from buried strain gauges. From the point of engineering application, the pile has merits in convenient quality control, high bearing capacity and reliable quality, showing higher reasonability, advancement and suitability than other ground improvement methods. The pile can be adopted properly to take place of ordinary ground improvement method, achieving greater economical and social benefits.展开更多
The high and large span cast-in-place reinforced concrete cantilever structure of the office building of some court, which is located I-steel at the cantilever and used steel pipe scaffold as the support, has guarante...The high and large span cast-in-place reinforced concrete cantilever structure of the office building of some court, which is located I-steel at the cantilever and used steel pipe scaffold as the support, has guaranteed the frame body and structure security by the frame body calculating, on-site test and reasonable construction order.展开更多
Despite significant advancements in in situ test techniques,construction practices,understanding of rock joint and rock mass behaviours,and numerical analysis methods,the design of bored concrete cast-insitu piles in ...Despite significant advancements in in situ test techniques,construction practices,understanding of rock joint and rock mass behaviours,and numerical analysis methods,the design of bored concrete cast-insitu piles in rock is still largely based on the assessment of bearing capacity.However,for many of the rock conditions encountered,the bearing capacity of piles is a nebulous concept and a figment of the designer’s imagination.Even if it can be reasonably quantified,it has little,if any,significance to the performance of a pile in rock.The load carrying capacity of even low strength rock(in most situations)is far in excess of the strength of the structure(for example,a building column)transmitting the load.Unsatisfactory performance of a pile in rock is usually a displacement issue and is a function of rock mass stiffness rather than rock mass strength.In addition,poor pile performance is much more likely to result from poor construction practices than excessive displacement of the rock mass.Exceptions occur for footings that are undermined,or where unfavourable structure in the rock allows movement towards a free surface to occur.Standards,codes of practices,reference books and other sources of design information should focus foundation design in rock on displacement rather than strength performance.Ground investigations should measure rock mass stiffness and defect properties,as well as intact rock strength.This paper summarises the fundamental concepts relating to performance of piles in rock and provides a basis for displacement focused design of piles in rock.It also presents comments relating to how piles are modelled in widely used commercial finite element software for soil-structure interaction analysis,within the context of the back-analysis of a pile load test,and proposes recommendations for pile analysis and design.展开更多
The reliability of post grouting pile axial resistance was studied by proposing a design method for its probabilistic limit state,which is represented by the partial coefficients of load,end,and side resistance.The hy...The reliability of post grouting pile axial resistance was studied by proposing a design method for its probabilistic limit state,which is represented by the partial coefficients of load,end,and side resistance.The hyperbolic,modified hyperbolic,and polynomial models were employed to predict the ultimate bearing capacity of test piles that were not loaded to damage in field tests.The results were used for the calculation and calibration of the reliability index.The reliability of the probabilistic limit state design method was verified by an engineering case.The results show that the prediction results obtained from the modified hyperbolic model are closest to those obtained through the static load test.The proposed corresponding values of total,side,and end resistance partial coefficients are 1.84,1.66,and 2.73 when the dead and live load partial coefficients are taken as 1.1 and 1.4,respectively.Meanwhile,the corresponding partial coefficients of total,side,and end resistance are 1.70,1.56,and 2.34 when the dead and live load partial coefficients are taken as 1.2 and 1.4,respectively.展开更多
This paper proposes an optimum design model for the offshore jacket platform considering multidesign criteria, multi-design constraints and the structure-pile-soil interaction, and gives an optimum design procedure in...This paper proposes an optimum design model for the offshore jacket platform considering multidesign criteria, multi-design constraints and the structure-pile-soil interaction, and gives an optimum design procedure in which the proposed optimum design model is used together with structural analysis software SAP91 and optimum algorithm software OPB1. The Chengbei (#)11 offshore platform, which lies in the Shengli oilfield, is designed by use of the above optimum design model. The results show that the optimum design model is stable, and it depends on neither the optimization algorithm nor initial values of design variables. All values of the objective function converge to the same minimum value, and the speed of convergence is high, showing that the proposed optimum design model is reasonable.展开更多
Sutong Bridge,as a world-record cable-stayed bridge with its main span exceeding 1 000 m constructed in Yangtze River estuary region in China,is located at a site with complicated hydrologic conditions and poor geotec...Sutong Bridge,as a world-record cable-stayed bridge with its main span exceeding 1 000 m constructed in Yangtze River estuary region in China,is located at a site with complicated hydrologic conditions and poor geotechnical conditions and therefore,scour protection will be a decisive factor for ensuring smooth and successful construction of this bridge.This paper,starting from structural description of deep-water group pile foundation,analyzes impact to the bridge safety introduced by scour and its protection and further presents different solutions of scour protection for foundation structures of this bridge.展开更多
A series of small-scale 1g X-section cast-in-place concrete(XCC)pile-penetration model tests were conducted to study the effects of soil density and pile geometry on the lateral responses of an existing pile and the v...A series of small-scale 1g X-section cast-in-place concrete(XCC)pile-penetration model tests were conducted to study the effects of soil density and pile geometry on the lateral responses of an existing pile and the variations in surrounding soil stress.The results showed that the bending patterns of existing XCC piles varied with penetration depth.The lateral response of the existing pile was sensitive to the change in relative density and pile geometry.For example,the bending moment of the existing pile increased along with these parameters.The development of the radial stressσ′r/σ′v0 of the soil around an existing pile showed different trends at various depths during the penetration of the adjacent pile.Moreover,the change in radial stress during the penetration of the XCC pile did not exhibit the“h/R effect”that was observed in the free-field soil,due to the shielding effect of the existing piles.The peak value of radial stressσ′r_max/σ′v0 decreased exponentially as the radial distance r/R increased.The attenuation ofσ′r_max/σ′v0 with r/R in the loose sand was faster than in the medium-dense or dense sands.Theσ′r_max/σ′v0 at the same soil location increased with the cross-section geometry parameter.展开更多
Large-scale shaking table tests were conducted to study the dynamic response of a slope reinforced by double-row anti-sliding piles and prestressed anchor cables. The test results show that the reinforcement suppresse...Large-scale shaking table tests were conducted to study the dynamic response of a slope reinforced by double-row anti-sliding piles and prestressed anchor cables. The test results show that the reinforcement suppressed the acceleration amplification effectively. The axial force time histories are decomposed into a baseline part and a vibration part in this study. The baseline part of axial force well revealed the seismic slope stability, the peak vibration values of axial force of the anchor cables changed significantly in different area of the slope under seismic excitations. The peak lateral earth pressure acting on the back of the anti-sliding pile located at the slope toe was much larger than that acting on the back of the anti-sliding pile located at the slope waist. The test results indicate an obvious load sharing ratio difference between these two anti-slide piles, the load sharing ratio between the two anti-sliding piles located at the slope toe and the slope waist varied mainly in a range of 2-5. The anti-slide pile at the slope waist suppressed the horizontal displacement of the slope surface.展开更多
A pile foundation is commonly adopted in geotechnical engineering to support structures, and its application has been extended to cold-regions engineering. In past decades, a host of scholars investigated pile behavio...A pile foundation is commonly adopted in geotechnical engineering to support structures, and its application has been extended to cold-regions engineering. In past decades, a host of scholars investigated pile behaviors and proposed design guidelines for seasonally frozen ground or permafrost. This paper reviews the research with respect to pile performance and engineering practice in cold regions, organized as follows:(1) creep tests and bearing capacity,(2) frost-jacking hazards,(3) laterally loaded piles,(4) dynamic responses,(5) refreezing due to concrete-hydration heat, and(6) improved countermeasures and design methods. We first summarize previous research and recent progress; then, predict the development trend of pile foundations in cold regions and recommend further research.展开更多
An optimization mathematical model of the pile forces for piled breasting dolphins in the open sea under various loading conditions is presented. The optimum layout with the well distributed pile forces and the least ...An optimization mathematical model of the pile forces for piled breasting dolphins in the open sea under various loading conditions is presented. The optimum layout with the well distributed pile forces and the least number of piles is achieved by the multiplier penalty function method. Several engineering cases have been calculated and compared with the result of the conventional design method. It is shown that the number of piles can be reduced at least by 10%~20% and the piles' bearing state is improved greatly.展开更多
A series of investigations were conducted to study the bearing capacity and load transfer mechanism of stiffened deep cement mixed (SDCM) pile. Laboratory tests including six specimens were conducted to investigate ...A series of investigations were conducted to study the bearing capacity and load transfer mechanism of stiffened deep cement mixed (SDCM) pile. Laboratory tests including six specimens were conducted to investigate the frictional resistance between the concrete core and the cementsoil. Two model piles and twenty-four full-scale piles were tested to examine the bearing behavior of single pile. Laboratory and model tests results indicate that the cohesive strength is large enough to ensure the interaction between core pile and the outer cement-soil. The full-scale test results show that the SDCM piles exhibit similar bearing behavior to bored and cast-in-place concrete piles. In general, with the rational composite structure the SDCM piles can transmit the applied load effectively, and due to the addition of the stiffer core, the SDCM piles possess high bearing capacity. Based on the findings of these experimental investigations and theoretical analysi , a practical design method is developed to predict the vertical bearing capacity of SDCM pile.展开更多
基金supported by the National Natural Science Foundation of China(Grant No.42071095)the Program of the State Key Laboratory of Frozen Soil Engineering(Grant No.SKLFSE-ZQ-59)+1 种基金the Science and Technology Project of Gansu Province(Grant No.22JR5RA086)the Science and Technology Research and Development Program of the Qinghai-Tibet Group Corporation(Grant No.QZ2022-G02).
文摘During the construction of cast-in-place piles in warm permafrost,the heat carried by concrete and the cement hydration reaction can cause strong thermal disturbance to the surrounding permafrost.Since the bearing capacity of the pile is quite small before the full freeze-back,the quick refreezing of the native soils surrounding the cast-in-place pile has become the focus of the infrastructure construction in permafrost.To solve this problem,this paper innovatively puts forward the application of the artificial ground freezing(AGF)method at the end of the curing period of cast-in-place piles in permafrost.A field test on the AGF was conducted at the Beiluhe Observation and Research Station of Frozen Soil Engineering and Environment(34°51.2'N,92°56.4'E)in the Qinghai Tibet Plateau(QTP),and then a 3-D numerical model was established to investigate the thermal performance of piles using AGF under different engineering conditions.Additionally,the long-term thermal performance of piles after the completion of AGF under different conditions was estimated.Field experiment results demonstrate that AGF is an effective method to reduce the refreezing time of the soil surrounding the piles constructed in permafrost terrain,with the ability to reduce the pile-soil interface temperatures to below the natural ground temperature within 3 days.Numerical results further prove that AGF still has a good cooling effect even under unfavorable engineering conditions such as high pouring temperature,large pile diameter,and large pile length.Consequently,the application of this method is meaningful to save the subsequent latency time and solve the problem of thermal disturbance in pile construction in permafrost.The research results are highly relevant for the spread of AGF technology and the rapid building of pile foundations in permafrost.
基金supported by the National Key Basic Research Program of China (973 Program) (No.2012CB026106)the National Natural Science Foundation of China (Grant No. 41171059)the Fund of the State Key Laboratory of Frozen Soil Engineering (No. SKLFSE-ZY-16)
文摘In the construction of the Qinghai-Tibet Power Transmission Line (QTPTL), cast-in-place piles (CIPPs) are widely applied in areas with unfavorable geological conditions. The thermal regime around piles in permafrost regions greatly affects the stability of the towers as well as the operation of the QTPTL. The casting of piles will markedly affect the thermal regime of the surrounding permafrost because of the casting temperature and the hydration heat of cement. Based on the typical geological and engineering conditions along the QTPTL, thermal disturbance ofa CIPP to surrounding permafrost under different casting seasons, pile depths, and casting temperatures were simulated. The results show that the casting season (summer versus winter) can influence the refreezing process of CIPPs, within the first 6 m of pile depth. Sixty days after being cast, CIPPs greater than 6 m in depth can be frozen regardless of which season they were cast, and the foundation could be reffozen after a cold season. Comparing the refreezing characteristics of CIPPs cast in different seasons also showed that, without considering the ground surface conditions, warm seasons are more suitable for casting piles. With the increase of pile depth, the thermal effect of a CIPP on the surrounding soil mainly expands vertically, while the lateral heat disturbance changes little. Deeper, longer CIPPs have better stability. The casting temperature clearly affects the thermal disturbance, and the radius of the melting circle increases with rising casting temperature. The optimal casting temperature is between 2 ℃ and 9 ℃.
基金The National Key Technologies R&D Program under Grant No. 2009BAJ28B01The Technologies R&D Program of China State Construction Engineering Co., Ltd under Grant No. CSCEC-2009-Z-15
文摘Many staircases in reinforced concrete (RC) frame structures suffered severe damage during the Wenchuan earthquake. Elastic analyses for 18 RC structure models with and without staircases are conducted and compared to study the influence of the staircase on the stiffness, displacements and internal forces of the structures. To capture the yielding development and damage mechanism of frame structures, elasto-plastic analysis is carried out for one of the 18 models. Based on the features observed in the analyses, a new type of staircase design i.e., isolating them from the master structure to eliminate the effect of K-type struts, is proposed and discussed. It is concluded that the proposed method of staircase isolation is effective and feasible for engineering design, and does not significantly increase the construction cost.
文摘Similar to free-standing pile groups, piled raft foundations are conventionally designed in which the piles carry the total load of structure and the raft bearing capacity is not taken into account. Numerous studies indicated that this method is too conservative. Only when the pile cap is elevated from the ground level,the raft bearing contribution can be neglected. In a piled raft foundation, pileesoileraft interaction is complicated. Although several numerical studies have been carried out to analyze the behaviors of piled raft foundations, very few experimental studies are reported in the literature. The available laboratory studies mainly focused on steel piles. The present study aims to compare the behaviors of piled raft foundations with free-standing pile groups in sand, using laboratory physical models. Cast-in-place concrete piles and concrete raft are used for the tests. The tests are conducted on single pile, single pile in pile group, unpiled raft, free-standing pile group and piled raft foundation. We examine the effects of the number of piles, the pile installation method and the interaction between different components of foundation. The results indicate that the ultimate bearing capacity of the piled raft foundation is considerably higher than that of the free-standing pile group with the same number of piles. With installation of the single pile in the group, the pile bearing capacity and stiffness increase. Installation of the piles beneath the raft decreases the bearing capacity of the raft. When the raft bearing capacity is not included in the design process, the allowable bearing capacity of the piled raft is underestimated by more than 200%. This deviation intensifies with increasing spacing of the piles.
基金supported by the Natural Science Foundation of China (Grants No.41101065)the State Key Laboratory of Frozen Soil Engineering Funds (SKLFSE-ZT-34,SKLFSE-ZQ-202103).
文摘The bearing capacity of pile foundations is affected by the temperature of the frozen soil around pile foundations.The construction process and the hydration heat of cast-in-place(CIP)pile foundations affect the thermal stability of permafrost.In this paper,temperature data from inside multiple CIP piles,borehole observations of ground thermal status adjacent to the foundations and local weather stations were monitored in warm permafrost regions to study the thermal influence process of CIP pile foundations.The following conclusions are drawn from the field observation data.(1)The early temperature change process of different CIP piles is different,and the differences gradually diminish over time.(2)The initial concrete temperature is linearly related with the air temperature,net radiation and wind speed within 1 h before the completion of concrete pouring;the contributions of the air temperature,net radiation,and wind speed to the initial concrete temperature are 51.9%,20.3%and 27.9%,respectively.(3)The outer boundary of the thermal disturbance annulus is approximately 2 m away from the pile center.It took more than 224 days for the soil around the CIP piles to return to the natural permafrost temperature at the study site.
文摘This thorough review explores the complexities of geotechnical engineering, emphasizing soil-structure interaction (SSI). The investigation centers on sheet pile design, examining two primary methodologies: Limit Equilibrium Methods (LEM) and Soil-Structure Interaction Methods (SSIM). While LEM methods, grounded in classical principles, provide valuable insights for preliminary design considerations, they may encounter limitations in addressing real-world complexities. In contrast, SSIM methods, including the SSI-SR approach, introduce precision and depth to the field. By employing numerical techniques such as Finite Element (FE) and Finite Difference (FD) analyses, these methods enable engineers to navigate the dynamics of soil-structure interaction. The exploration extends to SSI-FE, highlighting its essential role in civil engineering. By integrating Finite Element analysis with considerations for soil-structure interaction, the SSI-FE method offers a holistic understanding of how structures dynamically interact with their geotechnical environment. Throughout this exploration, the study dissects critical components governing SSIM methods, providing engineers with tools to navigate the intricate landscape of geotechnical design. The study acknowledges the significance of the Mohr-Coulomb constitutive model while recognizing its limitations, and guiding practitioners toward informed decision-making in geotechnical analyses. As the article concludes, it underscores the importance of continuous learning and innovation for the future of geotechnical engineering. With advancing technology and an evolving understanding of soil-structure interaction, the study remains committed to ensuring the safety, stability, and efficiency of geotechnical structures through cutting-edge design and analysis techniques.
基金Project (2007H03) supported by Communications Department of Zhejiang Province
文摘The compositions, technical principles and construction equipments of a new piling method used for ground improvement plastic tube cast-in-place concrete pile were introduced. The results from static load tests on single piles with different forms of pile shoes and on their composite foundations were analyzed. The distribution patterns of axial force, shaft friction and toe resistance were studied based on the measurements taken from buried strain gauges. From the point of engineering application, the pile has merits in convenient quality control, high bearing capacity and reliable quality, showing higher reasonability, advancement and suitability than other ground improvement methods. The pile can be adopted properly to take place of ordinary ground improvement method, achieving greater economical and social benefits.
文摘The high and large span cast-in-place reinforced concrete cantilever structure of the office building of some court, which is located I-steel at the cantilever and used steel pipe scaffold as the support, has guaranteed the frame body and structure security by the frame body calculating, on-site test and reasonable construction order.
文摘Despite significant advancements in in situ test techniques,construction practices,understanding of rock joint and rock mass behaviours,and numerical analysis methods,the design of bored concrete cast-insitu piles in rock is still largely based on the assessment of bearing capacity.However,for many of the rock conditions encountered,the bearing capacity of piles is a nebulous concept and a figment of the designer’s imagination.Even if it can be reasonably quantified,it has little,if any,significance to the performance of a pile in rock.The load carrying capacity of even low strength rock(in most situations)is far in excess of the strength of the structure(for example,a building column)transmitting the load.Unsatisfactory performance of a pile in rock is usually a displacement issue and is a function of rock mass stiffness rather than rock mass strength.In addition,poor pile performance is much more likely to result from poor construction practices than excessive displacement of the rock mass.Exceptions occur for footings that are undermined,or where unfavourable structure in the rock allows movement towards a free surface to occur.Standards,codes of practices,reference books and other sources of design information should focus foundation design in rock on displacement rather than strength performance.Ground investigations should measure rock mass stiffness and defect properties,as well as intact rock strength.This paper summarises the fundamental concepts relating to performance of piles in rock and provides a basis for displacement focused design of piles in rock.It also presents comments relating to how piles are modelled in widely used commercial finite element software for soil-structure interaction analysis,within the context of the back-analysis of a pile load test,and proposes recommendations for pile analysis and design.
基金The National Natural Science Foundation of China(No.51878160,52008100,52078128).
文摘The reliability of post grouting pile axial resistance was studied by proposing a design method for its probabilistic limit state,which is represented by the partial coefficients of load,end,and side resistance.The hyperbolic,modified hyperbolic,and polynomial models were employed to predict the ultimate bearing capacity of test piles that were not loaded to damage in field tests.The results were used for the calculation and calibration of the reliability index.The reliability of the probabilistic limit state design method was verified by an engineering case.The results show that the prediction results obtained from the modified hyperbolic model are closest to those obtained through the static load test.The proposed corresponding values of total,side,and end resistance partial coefficients are 1.84,1.66,and 2.73 when the dead and live load partial coefficients are taken as 1.1 and 1.4,respectively.Meanwhile,the corresponding partial coefficients of total,side,and end resistance are 1.70,1.56,and 2.34 when the dead and live load partial coefficients are taken as 1.2 and 1.4,respectively.
基金National Natural Science Foundation of China(Grant No.59895410)
文摘This paper proposes an optimum design model for the offshore jacket platform considering multidesign criteria, multi-design constraints and the structure-pile-soil interaction, and gives an optimum design procedure in which the proposed optimum design model is used together with structural analysis software SAP91 and optimum algorithm software OPB1. The Chengbei (#)11 offshore platform, which lies in the Shengli oilfield, is designed by use of the above optimum design model. The results show that the optimum design model is stable, and it depends on neither the optimization algorithm nor initial values of design variables. All values of the objective function converge to the same minimum value, and the speed of convergence is high, showing that the proposed optimum design model is reasonable.
基金National Science and Technology Support Program(No.2006BAG04B05)
文摘Sutong Bridge,as a world-record cable-stayed bridge with its main span exceeding 1 000 m constructed in Yangtze River estuary region in China,is located at a site with complicated hydrologic conditions and poor geotechnical conditions and therefore,scour protection will be a decisive factor for ensuring smooth and successful construction of this bridge.This paper,starting from structural description of deep-water group pile foundation,analyzes impact to the bridge safety introduced by scour and its protection and further presents different solutions of scour protection for foundation structures of this bridge.
基金supported by the National Natural Science Foundation of China(Nos.52308352,52238009,and 52108321)the Jiangxi Provincial Natural Science Foundation of China(No.20232BAB214082)+1 种基金the Open Research Fund Program of Guangdong Key Laboratory of Earthquake Engineering and Application Technology(No.2020B1212060071)the Science&Technology Project of the Education Department of Jiangxi Province(No.GJJ2200681),China.
文摘A series of small-scale 1g X-section cast-in-place concrete(XCC)pile-penetration model tests were conducted to study the effects of soil density and pile geometry on the lateral responses of an existing pile and the variations in surrounding soil stress.The results showed that the bending patterns of existing XCC piles varied with penetration depth.The lateral response of the existing pile was sensitive to the change in relative density and pile geometry.For example,the bending moment of the existing pile increased along with these parameters.The development of the radial stressσ′r/σ′v0 of the soil around an existing pile showed different trends at various depths during the penetration of the adjacent pile.Moreover,the change in radial stress during the penetration of the XCC pile did not exhibit the“h/R effect”that was observed in the free-field soil,due to the shielding effect of the existing piles.The peak value of radial stressσ′r_max/σ′v0 decreased exponentially as the radial distance r/R increased.The attenuation ofσ′r_max/σ′v0 with r/R in the loose sand was faster than in the medium-dense or dense sands.Theσ′r_max/σ′v0 at the same soil location increased with the cross-section geometry parameter.
基金financially supported by the National Key R&D Program of China(No.2018YFC1508601)the Fundamental Research Funds for the Central University(20822041B4038)
文摘Large-scale shaking table tests were conducted to study the dynamic response of a slope reinforced by double-row anti-sliding piles and prestressed anchor cables. The test results show that the reinforcement suppressed the acceleration amplification effectively. The axial force time histories are decomposed into a baseline part and a vibration part in this study. The baseline part of axial force well revealed the seismic slope stability, the peak vibration values of axial force of the anchor cables changed significantly in different area of the slope under seismic excitations. The peak lateral earth pressure acting on the back of the anti-sliding pile located at the slope toe was much larger than that acting on the back of the anti-sliding pile located at the slope waist. The test results indicate an obvious load sharing ratio difference between these two anti-slide piles, the load sharing ratio between the two anti-sliding piles located at the slope toe and the slope waist varied mainly in a range of 2-5. The anti-slide pile at the slope waist suppressed the horizontal displacement of the slope surface.
基金supported by the National Natural Science Foundation of China(Grant Nos.41731281and 41771073)
文摘A pile foundation is commonly adopted in geotechnical engineering to support structures, and its application has been extended to cold-regions engineering. In past decades, a host of scholars investigated pile behaviors and proposed design guidelines for seasonally frozen ground or permafrost. This paper reviews the research with respect to pile performance and engineering practice in cold regions, organized as follows:(1) creep tests and bearing capacity,(2) frost-jacking hazards,(3) laterally loaded piles,(4) dynamic responses,(5) refreezing due to concrete-hydration heat, and(6) improved countermeasures and design methods. We first summarize previous research and recent progress; then, predict the development trend of pile foundations in cold regions and recommend further research.
基金TheworkwassupportedbytheNationalFoundationofHighPerformanceComputation (No .9810 0 5 )
文摘An optimization mathematical model of the pile forces for piled breasting dolphins in the open sea under various loading conditions is presented. The optimum layout with the well distributed pile forces and the least number of piles is achieved by the multiplier penalty function method. Several engineering cases have been calculated and compared with the result of the conventional design method. It is shown that the number of piles can be reduced at least by 10%~20% and the piles' bearing state is improved greatly.
文摘A series of investigations were conducted to study the bearing capacity and load transfer mechanism of stiffened deep cement mixed (SDCM) pile. Laboratory tests including six specimens were conducted to investigate the frictional resistance between the concrete core and the cementsoil. Two model piles and twenty-four full-scale piles were tested to examine the bearing behavior of single pile. Laboratory and model tests results indicate that the cohesive strength is large enough to ensure the interaction between core pile and the outer cement-soil. The full-scale test results show that the SDCM piles exhibit similar bearing behavior to bored and cast-in-place concrete piles. In general, with the rational composite structure the SDCM piles can transmit the applied load effectively, and due to the addition of the stiffer core, the SDCM piles possess high bearing capacity. Based on the findings of these experimental investigations and theoretical analysi , a practical design method is developed to predict the vertical bearing capacity of SDCM pile.