We investigated the deformation failure mechanism of surrounding rock from the aspect of engineering support for a roadway in seams with soft roofs and soft floors and observed the large displacement of the roadway in...We investigated the deformation failure mechanism of surrounding rock from the aspect of engineering support for a roadway in seams with soft roofs and soft floors and observed the large displacement of the roadway in these soft seams.The result shows that the deformation area is quite large,and settlement of the roof is evident and displacement of the side walls is also obvious.We considered rock bolt-cable coupling for roadway support in seams with soft roofs and floors,in which the cable should be fixed at key positions.As well,we designed an optimal scheme to support a roadway in soft seams of the Shizuishan Second Mine in Ningxia,China.Field monitoring results show that bolt-cable coupling support has achieved the aims of roadway stability control and minimizes deformation.展开更多
Based on in-mine instrumentation and theoretical analysis of the unsymmetrical large-deformation that occurred in the roadway after excavation,Differential Floor Heave(DFH)was found to be the main reason for roadway f...Based on in-mine instrumentation and theoretical analysis of the unsymmetrical large-deformation that occurred in the roadway after excavation,Differential Floor Heave(DFH)was found to be the main reason for roadway failure.It needs to be pointed out that the specific roadway was driven in inclined rock strata.In addition,the factors that contribute to the occurrence of DFH are discussed in detail.It is believed that DFH is triggered by the unsymmetrical stress distribution in the floor and the different rock types encountered near the two floor corners.Hence,DFH control should be focused on the left floor corner where shearing failure occurs initially and the left floor surface where tensile failure is more severe.The proposed DFH control strategies include unsymmetrical grouting for the whole roadway,re-design of the roof and ribs support,reinforcement of the weak zones,and release of the concentrated stress in the earlier stage.Meanwhile,it is recommended that in the later stage,both bolts and cable bolts with higher strength and the backfilling technique using the coal measure rocks and concrete should be employed in the reversed-arch floor.The field instrumentation results,after using the proposed control strategies,indicate that large deformation in a DFH roadway has been successfully controlled.展开更多
The influence of an upper,mined coal seam on the stability of rock surrounding a roadway in a lower coal seam is examined.The technical problems of roadway control are discussed based on the geological conditions exis...The influence of an upper,mined coal seam on the stability of rock surrounding a roadway in a lower coal seam is examined.The technical problems of roadway control are discussed based on the geological conditions existing in the Liyazhuang Mine No.2 coal seam.The stress distribution and floor failure in the lower works after mining the upper coal is studied through numerical simulations.The failure mechanism of the roof and walls of a roadway located in the lower coal seam is described.The predicted deformation and failure of the roadway for different distances between the two coal seams are used to design two ways of supporting the lower structure.One is a combined support consisting of anchors with a joist steel tent and a combined anchor truss.A field test of the design was performed to good effect.The results have significance for the design of supports for roadways located in similar conditions.展开更多
文摘We investigated the deformation failure mechanism of surrounding rock from the aspect of engineering support for a roadway in seams with soft roofs and soft floors and observed the large displacement of the roadway in these soft seams.The result shows that the deformation area is quite large,and settlement of the roof is evident and displacement of the side walls is also obvious.We considered rock bolt-cable coupling for roadway support in seams with soft roofs and floors,in which the cable should be fixed at key positions.As well,we designed an optimal scheme to support a roadway in soft seams of the Shizuishan Second Mine in Ningxia,China.Field monitoring results show that bolt-cable coupling support has achieved the aims of roadway stability control and minimizes deformation.
基金financially supported by the National Natural Science Foundation of China (Nos.51204166 and 51174195)the Graduate Student Research Innovation Project of Ordinary University in Jiangsu Province (2013) (No.CXLX13_952)
文摘Based on in-mine instrumentation and theoretical analysis of the unsymmetrical large-deformation that occurred in the roadway after excavation,Differential Floor Heave(DFH)was found to be the main reason for roadway failure.It needs to be pointed out that the specific roadway was driven in inclined rock strata.In addition,the factors that contribute to the occurrence of DFH are discussed in detail.It is believed that DFH is triggered by the unsymmetrical stress distribution in the floor and the different rock types encountered near the two floor corners.Hence,DFH control should be focused on the left floor corner where shearing failure occurs initially and the left floor surface where tensile failure is more severe.The proposed DFH control strategies include unsymmetrical grouting for the whole roadway,re-design of the roof and ribs support,reinforcement of the weak zones,and release of the concentrated stress in the earlier stage.Meanwhile,it is recommended that in the later stage,both bolts and cable bolts with higher strength and the backfilling technique using the coal measure rocks and concrete should be employed in the reversed-arch floor.The field instrumentation results,after using the proposed control strategies,indicate that large deformation in a DFH roadway has been successfully controlled.
基金supported by the National Natural Science Foundation of China (No.50874103)the National Basic Research Program of China (No.2010CB226805)+1 种基金the Natural Science Foundation of Jiangsu Province (No.BK2008135)by the Open Foundation of State Key Laboratory of Geomechanics and Deep Underground Engineering (No.SKLGDUEK0905)
文摘The influence of an upper,mined coal seam on the stability of rock surrounding a roadway in a lower coal seam is examined.The technical problems of roadway control are discussed based on the geological conditions existing in the Liyazhuang Mine No.2 coal seam.The stress distribution and floor failure in the lower works after mining the upper coal is studied through numerical simulations.The failure mechanism of the roof and walls of a roadway located in the lower coal seam is described.The predicted deformation and failure of the roadway for different distances between the two coal seams are used to design two ways of supporting the lower structure.One is a combined support consisting of anchors with a joist steel tent and a combined anchor truss.A field test of the design was performed to good effect.The results have significance for the design of supports for roadways located in similar conditions.