Surrounding rock control of gob-side entry driving with narrow coal pillar and roadway side sealing technology in Yangliu Coal Mine 被引量:7
1
作者 Zha Wenhua Shi Hao +1 位作者 Liu San Kang Changhao 《International Journal of Mining Science and Technology》 SCIE EI CSCD 2017年第5期819-823,共5页
Gob-side entry driving can increase coal recovery ratio, and it is implied in many coal mines. Based on geological condition of 10416 working face tailentry in Yangliu Coal Mine, the surrounding rock deformation chara... Gob-side entry driving can increase coal recovery ratio, and it is implied in many coal mines. Based on geological condition of 10416 working face tailentry in Yangliu Coal Mine, the surrounding rock deformation characteristics of gob-side entry driving with narrow coal pillar is analysed, reasonable size of coal pillar and reasonable roadway excavation time after mining are achieved. Surrounding rock control technology and effective roadway side sealing technology are proposed and are taken into field practice. The results showed that a safer and more efficient mining of working face can be achieved. In addition, results of this paper also have important theoretical significance and valuable reference for surrounding rock control technology of gob-side entry driving with narrow coal pillar under special geological condition. 展开更多
关键词 Narrow coal PILLAR gob-side ENTRY driving SURROUNDING rock control ROADWAY SIDE sealing technology
下载PDF
Cable-truss supporting system for gob-side entry driving in deep mine and its application 被引量:3
2
作者 Yin Qian Jing Hongwen +3 位作者 Dai Dapeng Zhu Tantan Zhao Honghui Meng Bo 《International Journal of Mining Science and Technology》 SCIE EI CSCD 2016年第5期885-893,共9页
In order to solve the large deformation controlling problem for surrounding rock of gob-side entry driving under common cable anchor support in deep mine, site survey, physical modeling experiment, numerical simulatio... In order to solve the large deformation controlling problem for surrounding rock of gob-side entry driving under common cable anchor support in deep mine, site survey, physical modeling experiment, numerical simulation and field measurement were synthetically used to analyze the deformation and failure characteristics of surrounding rock. Besides, applicability analysis, prestress field distribution characteristics of surrounding rock and the control effect on large deformation of surrounding rock were also further studied for the gob-side entry driving in deep mine using the cable-truss supporting system. The results show that, first, compared with no support and traditional bolt anchor support, roof cable-truss system can effectively restrain the initiation and propagation of tensile cracks in the roof surrounding rock and arc shear cracks in the two sides, moreover, the broken development of surrounding rock, roof separation and extrusion deformation between the two sides of the roadway are all controlled; second, a prestressed belt of trapezoidal shape is generated in the surrounding rock by the cable-truss supporting system, and the prestress field range is wide. Especially, the prestress concentration belt in the shallow surrounding rock can greatly improve the anchoring strength and deformation resisting capability of the rock stratum;third, an optimized support system of ‘‘roof and side anchor net beam, roof cable-truss supporting system and anchor cable of the narrow coal pillar" was put forward, and the support optimization design and field industrial test were conducted for the gob-side entry driving of the working face 5302 in Tangkou Mine, from which a good supporting effect was obtained. 展开更多
关键词 Deep mine gob-side entry driving Cable-truss supporting system Deformation and failure STABILITY
下载PDF
Failure laws of narrow pillar and asymmetric control technique of gob-side entry driving in island coal face 被引量:16
3
作者 Yang Jiping Cao Shenggen Li Xuehua 《International Journal of Mining Science and Technology》 SCIE EI 2013年第2期271-276,共6页
In allusion to the problems of complex stress distribution in the surrounding rock and deformation failure laws, as well as the difficulty in roadway supporting of the gob-side entry driving in the island coal face, 2... In allusion to the problems of complex stress distribution in the surrounding rock and deformation failure laws, as well as the difficulty in roadway supporting of the gob-side entry driving in the island coal face, 2107 face in Chengjiao Colliery is researched as an engineering case. Through physical mechanical test of rock, theoretical and numerical simulation analyses of rock, the analysis model of the roadway overlying strata structure was established, and its parameters quantified. To reveal the deformation law of the surrounding rock, the stability of the overlying strata structure was studied before, during and after the roadway driving. According to the field conditions, the stress distribution in coal pillar was quantified, and the surrounding rock deformation feature studied with different widths of the pillars in gob-side entry driving. Finally, the pillar width of 4 m was considered as the most reasonable. The research results show that there is great difference in support conditions among roadway roof, entity coal side and narrow pillar side. Besides, the asymmetric control technique for support of the surrounding rock was proposed. The asymmetric control technique was proved to be reasonable by field monitoring, support by bolt-net, steel ladder and steel wire truss used in narrow pillar side. 展开更多
关键词 Island coal face gob-side entry driving Narrow pillar Asymmetric control
下载PDF
Stability of coal pillar in gob-side entry driving under unstable overlying strata and its coupling support control technique 被引量:10
4
作者 Yuan Zhang Zhijun Wan +4 位作者 Fuchen Li Changbing Zhou Bo Zhang Feng Guo Chengtan Zhu 《International Journal of Mining Science and Technology》 SCIE EI 2013年第2期204-210,共7页
Considering the situation that it is difficult to control the stability of narrow coal pillar in gob-side entry driving under unstable overlying strata, the finite difference numerical simulation method was adopted to... Considering the situation that it is difficult to control the stability of narrow coal pillar in gob-side entry driving under unstable overlying strata, the finite difference numerical simulation method was adopted to analyze the inner stress distribution and its evolution regularity, as well as the deformation characteristics of narrow coal pillar in gob-side entry driving, in the whole process from entry driving of last working face to the present working face mining. A new method of narrow coal pillar control based on the triune coupling support technique (TCST), which includes that high-strength prestressed thread steel bolt is used to strain the coal on the goaf side, and that short bolt to control the integrity of global displacement zone in coal pillar on the entry side, and that long grouting cable to fix anchor point to constrain the bed separation between global displacement zone and fixed zone, is thereby generated and applied to the field production. The result indicates that after entry excavating along the gob under unstable overlying strata, the supporting structure left on the gob side of narrow coal pillar is basically invalid to maintain the coal-pillar stability, and the large deformation of the pillar on the gob side is evident. Except for the significant dynamic pressure appearing in the coal mining of last working face and overlying strata stabilizing process, the stress variation inside the coal pillar in other stages are rather steady, however, the stress expansion is obvious and the coal pillar continues to deform. Once the gob-side entry driving is completed, a global displacement zone on the entry side appears in the shallow part of the pillar, whereas, a relatively steady fixed zone staying almost still in gob-side entry driving and present working face mining is found in the deep part of the pillar. The application of TCST can not only avoid the failure of pillar supporting structure, but exert the supporting capacity of the bolting structure left in the pillar of last sublevel entry, thus to jointly maintain the stability of coal pillar. 展开更多
关键词 gob-side entry driving Unstable surrounding rock Coal pillar stability Surrounding rock control Coupling support
下载PDF
Stress and deformation analysis of gob-side pre-backfill driving procedure of longwall mining:a case study 被引量:1
5
作者 Rui Wu Penghui Zhang +2 位作者 Pinnaduwa H.S.W.Kulatilake Hao Luo Qingyuan He 《International Journal of Coal Science & Technology》 EI CAS CSCD 2021年第6期1351-1370,共20页
At present,non-pillar entry protection in longwall mining is mainly achieved through either the gob-side entry retaining(GER)procedure or the gob-side entry driving(GED)procedure.The GER procedure leads to difficultie... At present,non-pillar entry protection in longwall mining is mainly achieved through either the gob-side entry retaining(GER)procedure or the gob-side entry driving(GED)procedure.The GER procedure leads to difficulties in maintaining the roadway in mining both the previous and current panels.A narrow coal pillar about 5-7 m must be left in the GED procedure;therefore,it causes permanent loss of some coal.The gob-side pre-backfill driving(GPD)procedure effectively removes the wasting of coal resources that exists in the GED procedure and finds an alternative way to handle the roadway maintenance problem that exists in the GER procedure.The FLAC^(3D) software was used to numerically investigate the stress and deformation distributions and failure of the rock mass surrounding the previous and current panel roadways during each stage of the GPD procedure which requires"twice excavation and mining".The results show that the stress distribution is slightly asymmetric around the previous panel roadway after the"primary excavation".The stronger and stiffer backfill compared to the coal turned out to be the main bearing body of the previous panel roadway during the"primary mining".The highest vertical stresses of 32.6 and 23.1 MPa,compared to the in-situ stress of 10.5 MPa,appeared in the backfill wall and coal seam,respectively.After the"primary mining",the peak vertical stress under the coal seam at the floor level was slightly higher(18.1 MPa)than that under the backfill(17.8 MPa).After the"secondary excavation",the peak vertical stress under the coal seam at the floor level was slightly lower(18.7 MPa)than that under the backfill(19.8 MPa);the maximum floor heave and maximum roof sag of the current panel roadway were 252.9 and 322.1 mm,respectively.During the"secondary mining",the stress distribution in the rock mass surrounding the current panel roadway was mainly affected by the superposition of the front abutment pressure from the current panel and the side abutment pressure from the previous panel.The floor heave of the current panel roadway reached a maximum of 321.8 mm at 5 m ahead of the working face;the roof sag increased to 828.4 mm at the working face.The peak abutment pressure appeared alternately in the backfill and the coal seam during the whole procedure of"twice excavation and mining"of the GPD procedure.The backfill provided strong bearing capacity during all stages of the GPD procedure and exhibited reliable support for the roadway.The results provide scientific insight for engineering practice of the GPD procedure. 展开更多
关键词 gob-side pre-backfill driving procedure Floor heave Roadway stability Stress distribution Abutment pressure
下载PDF
Trial of small gateroad pillar in top coal caving longwall mining of large mining height 被引量:8
6
作者 Li Huamin Syd Peng +4 位作者 Li Huigui Xu Yongxiang Yuan Ruifu Yue Shuaishuai Li Kun 《International Journal of Mining Science and Technology》 SCIE EI CSCD 2016年第1期139-147,共9页
Coal seams in Tashan Mine of Datong Coal Group in China average 15 m thick and have been mined by the top coal caving longwall mining method of large mining height. Mining height was 3.8 m and the top coal caving heig... Coal seams in Tashan Mine of Datong Coal Group in China average 15 m thick and have been mined by the top coal caving longwall mining method of large mining height. Mining height was 3.8 m and the top coal caving height was 11.2 m. The gateroad pillar between panels was 38 m. During retreat mining,serious bumps occurred in the gateroads on both sides of the pillar affecting safety production. Therefore,pillarless mining was experimented. Using numerical modeling and comparative study of cases of similar mining condition,it was decided to employ a 6 m wide pillar,rather than the previous 38 m wide pillar.Support system for the gateroads was designed and implemented. During gateroad development,pillar failure conditions and entry deformation were monitored. Hydraulic fracturing method was employed to cut off the K3 sandstone along the entry rib so as to reduce the abutment pressure induced during retreat mining. Support reinforcement method combining grouting and advanced reinforcement methods was proposed to insure stable gateroad ahead of mining. Methane drainage and nitrogen injection were implemented to eliminate hazards associated with mine fire and spontaneous combustion. Since the development of gateroad has just completed,and retreat mining has not begun,the effectiveness of the proposed methods is unknown at this point. However,monitoring will continue until after mining.The results will be published in a separate paper. 展开更多
关键词 Large mining heightSmall gateroad pillarTop coal caving longwall miningHydraulic fracturinggob-side entry driving
下载PDF
倾斜中厚煤层错层位外错式巷道布置及相邻巷道联合支护技术 被引量:25
7
作者 王志强 郭磊 +2 位作者 苏泽华 王树帅 沈聪 《煤炭学报》 EI CAS CSCD 北大核心 2020年第2期542-555,共14页
基于倾斜中厚煤层沿空掘巷与支护技术展开研究。首先通过构建力学模型,依据基本顶最大弯矩确定基本顶的断裂位置及断裂形式,计算得在距离煤柱帮17.57 m处基本顶达到弯矩最大值23.02 MN·m,并进一步确定断裂线位于实体煤上方;结合&qu... 基于倾斜中厚煤层沿空掘巷与支护技术展开研究。首先通过构建力学模型,依据基本顶最大弯矩确定基本顶的断裂位置及断裂形式,计算得在距离煤柱帮17.57 m处基本顶达到弯矩最大值23.02 MN·m,并进一步确定断裂线位于实体煤上方;结合"内外应力场"理论,确定在当前覆岩力学环境下"内应力场"范围为15.89 m;综合考虑煤柱的空间关系,分析巷道围岩煤柱尺寸,确定窄煤柱水平错距为7.37 m,竖直错距为2.40 m;综合以上分析确定区段煤柱留设尺寸范围为7~12 m,通过FLAC3D数值模拟软件对不同煤柱尺寸的应力场、塑性区分布进行计算分析,对掘进和回采两个阶段下不同煤柱尺寸条件下稳定性进行研究和验证,最终确定窄煤柱的合理宽度为8 m。然后根据倾斜中厚煤层错层位外错式巷道布置形式所具有的立体化空间形式,提出错层位外错式区段间相邻巷道联合支护技术并对其技术特点进行理论分析;基于围岩松动圈支护理论,通过计算确定区段间相邻巷道联合支护参数并利用FLAC3D数值模拟软件对区段间相邻巷道联合支护方案和矿方原支护方案进行模拟,分别从支护应力场、塑性区分布和围岩相对变形率3方面对掘巷和回采阶段下两支护方案的效果进行验证,最终结果表明区段间相邻巷道联合支护方案相对于矿方原始支护方案,更有利于巷道围岩的变形控制。 展开更多
关键词 沿空掘巷 窄煤柱 错层位 外错式 相邻区段巷道 联合支护
下载PDF
长壁工作面巷顶沿空掘巷围岩应力分析 被引量:14
8
作者 王朋飞 冯国瑞 +2 位作者 赵景礼 Yoginder P.Chugh 王志强 《岩土力学》 EI CAS CSCD 北大核心 2018年第9期3395-3405,共11页
镇城底矿工作面的回采巷道一条沿顶板掘进,一条沿底板掘进,相邻两工作面在端头搭接,沿底板掘进的巷道形成巷顶沿空掘巷。通过理论分析、相似模拟、数值模拟及现场实测对巷顶沿空掘巷围岩结构及应力环境进行了研究。得到如下结论:该巷道... 镇城底矿工作面的回采巷道一条沿顶板掘进,一条沿底板掘进,相邻两工作面在端头搭接,沿底板掘进的巷道形成巷顶沿空掘巷。通过理论分析、相似模拟、数值模拟及现场实测对巷顶沿空掘巷围岩结构及应力环境进行了研究。得到如下结论:该巷道不受超前和固定支承压力影响,大结构下方的矸石垫层可起到能量和应力耗散的作用,避免了动载和冲击影响,应力低且稳定;岩层移动形成的垮落角对采空区应力大小和分布(尤其采空区边缘)有重要影响;垮落角越小,采空区应力越小,该巷道围岩应力越小,采空区恢复至原岩应力的距离越大;垮落角对岩体塑性区发育方向起控制和导向作用;该巷道围岩应力大幅低于原岩应力,卸压程度大;实测该巷道竖向和横向位移均比非沿空巷道小,即顶底板和两帮应力环境均得到改善。研究对维护具有冲击倾向的高应力巷道具有一定意义。 展开更多
关键词 错层位 沿空掘巷 双屈服 采空区 冲击倾向 高应力
下载PDF
Layout and support technology of entry for pillar face 被引量:1
9
作者 Wang Jianli Xu Ying +2 位作者 Li Wenfeng Wang Xiangyu Bai Jianbiao 《International Journal of Mining Science and Technology》 SCIE EI CSCD 2016年第5期877-884,共8页
In order to improve the recovery rate of coal, some mines have begun to recover the residual protective pillars in the form of short wall faces. However, it is difficult to control stability of the haulage entry and t... In order to improve the recovery rate of coal, some mines have begun to recover the residual protective pillars in the form of short wall faces. However, it is difficult to control stability of the haulage entry and the ventilating entry under the mining influences of the pillar face and the two side faces. Thus the 4311 face, which was designed to recover the 57 m wide residual protective pillar in Guojiashan Coal Mine,was taken as engineering background. Distribution law of stress and plastic zone in the residual protective pillar was analyzed using the numerical simulation. Then the gob-side entry driving technology was proposed to layout the entries for the pillar face. Based on the analysis of stress distribution and deformation characteristics of surrounding rocks in gob-side entry driving with different width of narrow pillars, the width of the narrow pillar of the entries in the 4311 face was decided to be 4 m. In order to control stability of the gob-side entry driving, the mechanical model of the main roof was established and deformation characteristic of surrounding rock was analyzed. Then the bolt support technology with high strength and high pre-tightening force was proposed for entry support. Especially, the hydraulic expansion bolts were used to support the narrow pillar rib. The engineering results show that the width of the narrow pillar is reasonable and the entry support technology is effective. The research achievement can provide some references to pillar recovery for other coal mines. 展开更多
关键词 Pillar recovery gob-side entry driving STABILITY Bolt support Hydraulic expansion bolt