Reducing the blasting vibration is important for blasting excavation in subway tunnel construction.Taking the 3rd bid section of Line 3 of Qingdao subway project as an example,the distance between tunnel vault and gro...Reducing the blasting vibration is important for blasting excavation in subway tunnel construction.Taking the 3rd bid section of Line 3 of Qingdao subway project as an example,the distance between tunnel vault and ground is 5 ~ 8 m.In order to insure the safety of the upper buildings,technologies of parallel cut with large diameter empty hole,one-time initiation and delay by parts,and multiple shallow holes were adopted in the project.The results showed that the maximum value of vertical vibration was limited in the criterion allowance,and the upper buildings were not damaged.Besides,problems were solved that the number of nonel detonator was difficult to meet the requirements of excavating a large cross-section tunnel by blasting,multiple cross-section could’t be initiated simultaneously,and construction efficiency was low,which ensure the construction safety and schedule.展开更多
文摘Reducing the blasting vibration is important for blasting excavation in subway tunnel construction.Taking the 3rd bid section of Line 3 of Qingdao subway project as an example,the distance between tunnel vault and ground is 5 ~ 8 m.In order to insure the safety of the upper buildings,technologies of parallel cut with large diameter empty hole,one-time initiation and delay by parts,and multiple shallow holes were adopted in the project.The results showed that the maximum value of vertical vibration was limited in the criterion allowance,and the upper buildings were not damaged.Besides,problems were solved that the number of nonel detonator was difficult to meet the requirements of excavating a large cross-section tunnel by blasting,multiple cross-section could’t be initiated simultaneously,and construction efficiency was low,which ensure the construction safety and schedule.