A steel underground pipeline with a diameter of 2.4 m and a total length of 3,617 m(plate thickness of 26 mm)has been constructed in a city in central Hubei,and the engineering,procurement,and construction(EPC)project...A steel underground pipeline with a diameter of 2.4 m and a total length of 3,617 m(plate thickness of 26 mm)has been constructed in a city in central Hubei,and the engineering,procurement,and construction(EPC)project has been lifted from the upstream channel to supplement water to the downstream lake inside the city.Through preliminary geological survey data,site topographic and geomorphic survey,urban construction,as well as the requirements of the construction party,the preliminary arrangement of working wells and receiving wells as well as the selection and customization of pipe jacking machines have been proposed.Frequency conversion motor and remote monitoring technology are adopted for geotechnical change and long-distance pipe jacking.Through detailed survey,the rock and soil change section as well as gradual change conditions have been determined,the accuracy of construction mechanics calculation and construction operation control have improved,the basis and analysis basis are provided,and some experiences in construction operation are summarized.展开更多
By using site observation data and establishing 3D model using ANSYS software, this paper has discussed the strain change of stratum stress during process of jacking-in and the impact of machine head on ground surface...By using site observation data and establishing 3D model using ANSYS software, this paper has discussed the strain change of stratum stress during process of jacking-in and the impact of machine head on ground surface under different frontal resistances. Analysis of the two cases shows that soil pressure reaches its maximum point when the soil is right above machine head, and soil stress will gradually decline when machine head passes over it. It also shows that impact brought by pipe-jacking construction on stress change of the surrounding soil is limited. The thesis suggest that road surface should be consolidated and soil condition be improved before construction to prevent loss and disaster caused by road surface deformation, jacking force can be increased so that jacking efficiency can be enhanced when ground stratum is well filled with soil, but the frontal resistance facing machine head should be equal to surrounding soil pressure in order to avoid rise of ground surface.展开更多
文摘A steel underground pipeline with a diameter of 2.4 m and a total length of 3,617 m(plate thickness of 26 mm)has been constructed in a city in central Hubei,and the engineering,procurement,and construction(EPC)project has been lifted from the upstream channel to supplement water to the downstream lake inside the city.Through preliminary geological survey data,site topographic and geomorphic survey,urban construction,as well as the requirements of the construction party,the preliminary arrangement of working wells and receiving wells as well as the selection and customization of pipe jacking machines have been proposed.Frequency conversion motor and remote monitoring technology are adopted for geotechnical change and long-distance pipe jacking.Through detailed survey,the rock and soil change section as well as gradual change conditions have been determined,the accuracy of construction mechanics calculation and construction operation control have improved,the basis and analysis basis are provided,and some experiences in construction operation are summarized.
基金the Science and Technology Foundation of Sichuan Department of Land and Resources(SCDLR0609)
文摘By using site observation data and establishing 3D model using ANSYS software, this paper has discussed the strain change of stratum stress during process of jacking-in and the impact of machine head on ground surface under different frontal resistances. Analysis of the two cases shows that soil pressure reaches its maximum point when the soil is right above machine head, and soil stress will gradually decline when machine head passes over it. It also shows that impact brought by pipe-jacking construction on stress change of the surrounding soil is limited. The thesis suggest that road surface should be consolidated and soil condition be improved before construction to prevent loss and disaster caused by road surface deformation, jacking force can be increased so that jacking efficiency can be enhanced when ground stratum is well filled with soil, but the frontal resistance facing machine head should be equal to surrounding soil pressure in order to avoid rise of ground surface.