Based on the analysis of the failure characteristics and backfilling effect of the compound roof at 1801 backfilling workface in Taiyuan coal mine, China, we propose a method of controlling the pre- subsidence of a co...Based on the analysis of the failure characteristics and backfilling effect of the compound roof at 1801 backfilling workface in Taiyuan coal mine, China, we propose a method of controlling the pre- subsidence of a compound roof by using pre-stressed bolts to improve the backfilling ratio of the work- face so as to maintain the global stability of the stope roof. In addition, PHASE simulation software was employed to analyze the influence law of pre-stressing force, length, and interval on roof subsidence at the workface. On the basis of the numerical simulation results, a model for calculating the pre-stressing force and length of the bolts, the interval between the bolts, as well as roof subsidence at the workface, was established by using SPSS regression analysis software. Moreover, the research results were applied successfully to the 1801 filling workface. According to the monitoring data of roof closure, it was found that the final subsidence value for the goal roof was 350 mm and the filling ratio at the workface was 86%, which could fully meet the demand for safety production at the workface. The safe and effective control of the stope roof was therefore realized, which achieves the goal of safe and efficient backfilling mining under a compound roof.展开更多
Xinli district of Sanshandao Gold Mine is the first subsea metal mine in China.To achieve 6 kt/d production capacity under the premise of safe mining,high-intensity mining might destroy the in-situ stress filed and th...Xinli district of Sanshandao Gold Mine is the first subsea metal mine in China.To achieve 6 kt/d production capacity under the premise of safe mining,high-intensity mining might destroy the in-situ stress filed and the stability of rockmass.According to sampling and testing of ore-rock and backfill and in-situ stress field measurement,safety factor method calculation model based on stress-strain strength reduction at arbitrary points and Mohr-Coulomb yield criterion was established and limit displacement subsidence values under the safety factor of different limit stoping steps were calculated.The results from three years in-situ mining and strata movement monitoring using multi-point displacements meter showed that the lower settlement frame stope hierarchical level filling mining method,mining sequence are reasonable and rockmass stability evaluation using safety factor method,in-situ real-time monitoring can provide the technical foundation for the safety of seabed mining.展开更多
Near-surface deposits that extend to considerable depths are often amenable to both open pit mining and/or underground mining. This paper investigates the strategy of mining options for an orebody using a Mixed Intege...Near-surface deposits that extend to considerable depths are often amenable to both open pit mining and/or underground mining. This paper investigates the strategy of mining options for an orebody using a Mixed Integer Linear Programming(MILP) optimization framework. The MILP formulation maximizes the Net Present Value(NPV) of the reserve when extracted with(i) open pit mining,(ii) underground mining, and(iii) concurrent open pit and underground mining. Comparatively, implementing open pit mining generates a higher NPV than underground mining. However considering the investment required for these mining options, underground mining generates a better return on investment than open pit mining. Also, in the concurrent open pit and underground mining scenario, the optimizer prefers extracting blocks using open pit mining. Although the underground mine could access ore sooner, the mining cost differential for open pit mining is more than compensated for by the discounting benefits associated with earlier underground mining.展开更多
We combined the similar simulation with numerical simulation to analyze the movement and deforma- tion features of overlying strata caused by paste backfill mining, study the movement and deformation laws of the overl...We combined the similar simulation with numerical simulation to analyze the movement and deforma- tion features of overlying strata caused by paste backfill mining, study the movement and deformation laws of the overlying strata in paste backfill mining, structural movement of the stope strata as well as the stope stress distribution laws. Furthermore, authors also explored the key factors to the movement and deformation of the overlying strata in paste backfill mining. The results indicate that a caving zone existed in the bending zone only in the overlying strata of the paste backfill mining. Compared with the roof caving mining, the degree of stress concentration and area of influence in the paste filling stope were apparently smaller. And the degree of destruction and area of the overlying strata decreased prominently. Also, there was no apparent strata behavior in the working face. Lastly, the filling ratio was the key to control the movement and deformation of the overlying strata. Combined with a specific engineering example, the author proved the reliability of the simulation results and provided a theoretical basis for the further extension of the paste backfill mining.展开更多
Cemented paste backfill (CPB) is gaining popularity in many underground mines worldwide. Sufficient water is added into CPB to make a flowable material for pipe transportation. Barricades are built near the drawpoin...Cemented paste backfill (CPB) is gaining popularity in many underground mines worldwide. Sufficient water is added into CPB to make a flowable material for pipe transportation. Barricades are built near the drawpoints to prevent in-rush of the fill slurry. To avoid barricade failures resulting from excessive backfill pressures, backfilling is typically performed with a plug pour followed by a final pour. The interval between the two pours should be shortened or removed to increase mining productivity and avoid pipe clogging. Recently, Li proposed to apply wick drains in backfilled stopes to promote drainage and consolidation. The preliminary simulations by considering an instantaneous filling indicated that the drainage of CPB can be significantly accelerated by using wick drains. Barricade was not considered. Here, some new numerical modeUings are presented with more representative filling sequences, stope geometry, and different draining configurations. The results illustrate that the stope can be backfilled continuously by using wick drains.展开更多
According to the special requirements of secondary mining of resources in gateway-and-pillar goal in extra-thick seams of Shanxi, this paper presents a technical proposal of back stoping from level floors. Numerical s...According to the special requirements of secondary mining of resources in gateway-and-pillar goal in extra-thick seams of Shanxi, this paper presents a technical proposal of back stoping from level floors. Numerical simulation and theoretical analysis are ccsed to investigate the compaction characteristics of cavities under stress as well as an appropriate mining height of the primary-mining layer based on dif- ferent mining widths and pillar widths. For Yangjian coal mine, the mining thickness of the first seam during back stoping from level floor is determined to be 3 m, which meets the relevant requirements. Gateway-and-pillar goaf of a single layer has a range of influence of 9 m vertically. If gateway-and-pillar goaf occurs both in 9-1 and 9-5 layers, the range is extended to within 11.2 m. When the mining width of a gateway is less than 2 m or larger than 5 m, the gateway-and-pillar goal in the upper layer of the primary-mining seam can be filled in and compacted after stoping. When the working face is 2 m away from the gateway and pillar before entering into it and after passing through it, the coal body under the gateway and pillar is subjected to relatively high stress. During mining of the upper layer, moreover, the working face should interlock the goaf in primary-mining layer for 20 m.展开更多
In underground mining by sublevel caving method, the deformation and damage of the surface induced by subsidence are the major challenging issues. The dynamic and soft backflling body increases the safety risks in the...In underground mining by sublevel caving method, the deformation and damage of the surface induced by subsidence are the major challenging issues. The dynamic and soft backflling body increases the safety risks in the subsiding area. In this paper, taking Zhangfushan iron mine as an example, the ore body and the general layout are focused on the safety of backflling of mined-out area. Then, we use the ANSYS software to construct a three-dimensional(3D) model for the mining area in the Zhangfushan iron mine. According to the simulation results of the initial mining stages, the ore body is stoped step by step as suggested in the design. The stability of the backflling is back analyzed based on the monitored displacements, considering the stress distribution to optimize the stoping sequence. The simulations show that a reasonable stoping sequence can minimize the concentration of high compressive stress and ensure the safety of stoping of the ore body.展开更多
基金the Qinglan Project,the National Key Basic Research Program of China (No.2013CB227905)the Science Fund for Creative Research Groups of the National Natural Science Foundation of China (No.51421003)
文摘Based on the analysis of the failure characteristics and backfilling effect of the compound roof at 1801 backfilling workface in Taiyuan coal mine, China, we propose a method of controlling the pre- subsidence of a compound roof by using pre-stressed bolts to improve the backfilling ratio of the work- face so as to maintain the global stability of the stope roof. In addition, PHASE simulation software was employed to analyze the influence law of pre-stressing force, length, and interval on roof subsidence at the workface. On the basis of the numerical simulation results, a model for calculating the pre-stressing force and length of the bolts, the interval between the bolts, as well as roof subsidence at the workface, was established by using SPSS regression analysis software. Moreover, the research results were applied successfully to the 1801 filling workface. According to the monitoring data of roof closure, it was found that the final subsidence value for the goal roof was 350 mm and the filling ratio at the workface was 86%, which could fully meet the demand for safety production at the workface. The safe and effective control of the stope roof was therefore realized, which achieves the goal of safe and efficient backfilling mining under a compound roof.
基金Project(10872218) supported by the National Natural Science Foundation of ChinaProject(2010CB732004) supported by the National Key Basic Research Program of China+1 种基金Project(20090461022) supported by the National Postdoctoral Foundation of ChinaProject (11MX21) supported by the Students' Innovation Project Aubsidize Award of Arcelor Mittal
文摘Xinli district of Sanshandao Gold Mine is the first subsea metal mine in China.To achieve 6 kt/d production capacity under the premise of safe mining,high-intensity mining might destroy the in-situ stress filed and the stability of rockmass.According to sampling and testing of ore-rock and backfill and in-situ stress field measurement,safety factor method calculation model based on stress-strain strength reduction at arbitrary points and Mohr-Coulomb yield criterion was established and limit displacement subsidence values under the safety factor of different limit stoping steps were calculated.The results from three years in-situ mining and strata movement monitoring using multi-point displacements meter showed that the lower settlement frame stope hierarchical level filling mining method,mining sequence are reasonable and rockmass stability evaluation using safety factor method,in-situ real-time monitoring can provide the technical foundation for the safety of seabed mining.
基金funding support provided by the Laurentian University Research Fund for the compilation of this report
文摘Near-surface deposits that extend to considerable depths are often amenable to both open pit mining and/or underground mining. This paper investigates the strategy of mining options for an orebody using a Mixed Integer Linear Programming(MILP) optimization framework. The MILP formulation maximizes the Net Present Value(NPV) of the reserve when extracted with(i) open pit mining,(ii) underground mining, and(iii) concurrent open pit and underground mining. Comparatively, implementing open pit mining generates a higher NPV than underground mining. However considering the investment required for these mining options, underground mining generates a better return on investment than open pit mining. Also, in the concurrent open pit and underground mining scenario, the optimizer prefers extracting blocks using open pit mining. Although the underground mine could access ore sooner, the mining cost differential for open pit mining is more than compensated for by the discounting benefits associated with earlier underground mining.
基金supported by the National Natural Science Foundation of China (No. 50774077)the Special Funds of Universities Outstanding Doctoral Dissertation (No. 200760)+1 种基金the Independent Research Funding of the State Key Laboratory of Coal Resources and Mine Safety (No. SKLCRSM10X02)the Fundamental Research Funds for the Central Universities (Nos. 2010QNA31 and2010QNA32)
文摘We combined the similar simulation with numerical simulation to analyze the movement and deforma- tion features of overlying strata caused by paste backfill mining, study the movement and deformation laws of the overlying strata in paste backfill mining, structural movement of the stope strata as well as the stope stress distribution laws. Furthermore, authors also explored the key factors to the movement and deformation of the overlying strata in paste backfill mining. The results indicate that a caving zone existed in the bending zone only in the overlying strata of the paste backfill mining. Compared with the roof caving mining, the degree of stress concentration and area of influence in the paste filling stope were apparently smaller. And the degree of destruction and area of the overlying strata decreased prominently. Also, there was no apparent strata behavior in the working face. Lastly, the filling ratio was the key to control the movement and deformation of the overlying strata. Combined with a specific engineering example, the author proved the reliability of the simulation results and provided a theoretical basis for the further extension of the paste backfill mining.
基金the Natural Sciences and Engineering Research Council of Canada (RGPIN)the Institut de recherche Robert-Sauvé en santé et en sécurité du travail (IRSST)the industrial partners of the Research Institute on Mines and the Environment (RIME UQAT-Polytechnique)
文摘Cemented paste backfill (CPB) is gaining popularity in many underground mines worldwide. Sufficient water is added into CPB to make a flowable material for pipe transportation. Barricades are built near the drawpoints to prevent in-rush of the fill slurry. To avoid barricade failures resulting from excessive backfill pressures, backfilling is typically performed with a plug pour followed by a final pour. The interval between the two pours should be shortened or removed to increase mining productivity and avoid pipe clogging. Recently, Li proposed to apply wick drains in backfilled stopes to promote drainage and consolidation. The preliminary simulations by considering an instantaneous filling indicated that the drainage of CPB can be significantly accelerated by using wick drains. Barricade was not considered. Here, some new numerical modeUings are presented with more representative filling sequences, stope geometry, and different draining configurations. The results illustrate that the stope can be backfilled continuously by using wick drains.
基金Financial support for this work was provided by the National High-Tech Research and Development Program of China (No. 2012AA062101)the Priority Academic Development Program of Jiangsu Higher Education Institutions (No. SZBF2011-6-B35)the Graduate Students Innovation Fund of Colleges and Universities in Jiangsu Province (No. CXZZ12_0950)
文摘According to the special requirements of secondary mining of resources in gateway-and-pillar goal in extra-thick seams of Shanxi, this paper presents a technical proposal of back stoping from level floors. Numerical simulation and theoretical analysis are ccsed to investigate the compaction characteristics of cavities under stress as well as an appropriate mining height of the primary-mining layer based on dif- ferent mining widths and pillar widths. For Yangjian coal mine, the mining thickness of the first seam during back stoping from level floor is determined to be 3 m, which meets the relevant requirements. Gateway-and-pillar goaf of a single layer has a range of influence of 9 m vertically. If gateway-and-pillar goaf occurs both in 9-1 and 9-5 layers, the range is extended to within 11.2 m. When the mining width of a gateway is less than 2 m or larger than 5 m, the gateway-and-pillar goal in the upper layer of the primary-mining seam can be filled in and compacted after stoping. When the working face is 2 m away from the gateway and pillar before entering into it and after passing through it, the coal body under the gateway and pillar is subjected to relatively high stress. During mining of the upper layer, moreover, the working face should interlock the goaf in primary-mining layer for 20 m.
文摘In underground mining by sublevel caving method, the deformation and damage of the surface induced by subsidence are the major challenging issues. The dynamic and soft backflling body increases the safety risks in the subsiding area. In this paper, taking Zhangfushan iron mine as an example, the ore body and the general layout are focused on the safety of backflling of mined-out area. Then, we use the ANSYS software to construct a three-dimensional(3D) model for the mining area in the Zhangfushan iron mine. According to the simulation results of the initial mining stages, the ore body is stoped step by step as suggested in the design. The stability of the backflling is back analyzed based on the monitored displacements, considering the stress distribution to optimize the stoping sequence. The simulations show that a reasonable stoping sequence can minimize the concentration of high compressive stress and ensure the safety of stoping of the ore body.