A Method for the Damage Detection of Pile Foundation in High-Pile Wharf Based on A Curvature Mode Deletion Model 被引量:2
1
作者 WANG Qi-ming ZHU Rui-hu +3 位作者 ZHENG Jin-hai WANG Ning LUO Meng-yan CHE Yu-fei 《China Ocean Engineering》 SCIE EI CSCD 2020年第6期871-880,共10页
As the top of the pile foundation in high-pile wharf is connected to the superstructure and most of the pile bodies are located below the water surface, traditional damage detection methods are greatly limited in thei... As the top of the pile foundation in high-pile wharf is connected to the superstructure and most of the pile bodies are located below the water surface, traditional damage detection methods are greatly limited in their application to pile foundation in service. In the present study, a new method for pile foundation damage detection is developed based on the curve shape of the curvature mode difference(CMD) before and after damage. In the method, the influence at each node on the overall CMD curve shape is analyzed through a data deletion model, statistical characteristic indexes are established to reflect the difference between damaged and undamaged units, and structural damage is accurately detected. The effectiveness and robustness of the method are verified by a finite element model(FEM) of high-pile wharf under different damage conditions and different intensities of Gaussian white noise. The applicability of the method is then experimentally validated by a physical model of high-pile wharf. Both the FEM and the experimental results show that the method is capable of detecting pile foundation damage in noisy curvature mode and has strong application potential. 展开更多
关键词 high-pile wharf pile foundation curvature mode data deletion model damage detection
下载PDF
自平衡法和高应变检测在码头灌注桩中的应用
2
作者 张丽珍 王东静 《水运工程》 2024年第8期134-138,234,共6页
海南某高桩码头工程地质条件特殊,表面覆盖硬岩层,下部为黏土层,码头基础采用灌注桩结构,以硬黏土层为持力层。施工后分别采用自平衡法静载试验和高应变法检测桩基承载力,将检测结果与规范理论计算结果进行比较。结果表明,通过自平衡检... 海南某高桩码头工程地质条件特殊,表面覆盖硬岩层,下部为黏土层,码头基础采用灌注桩结构,以硬黏土层为持力层。施工后分别采用自平衡法静载试验和高应变法检测桩基承载力,将检测结果与规范理论计算结果进行比较。结果表明,通过自平衡检测的荷载-位移关系曲线判断,桩端依旧处于弹性阶段,并根据在加载过程中桩身轴力沿桩身轴向的分布情况,可分别判断各桩侧摩阻力、端承载力的发挥值,从而判断桩阻力并没有全部发挥,桩基的实际极限承载力大于试验值。高应变检测法检测桩侧摩阻力结果大于理论计算结果,桩端承载力小于理论计算结果,总桩基承载力二者比较接近,因此可以作为静载试桩的辅助验证。在港口码头工程中采用自平衡静载测试法,并用高应变检测法进行验证,可以解决水域条件下大质量桩基承载力的检测问题。 展开更多
关键词 自平衡法静载试验 高应变检测 桩基承载力 码头灌注桩
下载PDF
重载码头堆场CFG桩网复合地基离心模型试验研究
3
作者 周春儿 董华钢 +3 位作者 王年香 徐光明 顾行文 任国峰 《海洋工程》 CSCD 北大核心 2024年第1期158-164,共7页
CFG桩网复合地基广泛应用于处理软土地基。采用土工离心模型试验研究某码头堆场超大荷载下CFG桩网复合地基的变形和桩土应力特性,试验模拟了地基、CFG桩、树根桩、加筋垫层、防尘网和轨道梁基础、矿石堆载等,分析了超大荷载作用下复合... CFG桩网复合地基广泛应用于处理软土地基。采用土工离心模型试验研究某码头堆场超大荷载下CFG桩网复合地基的变形和桩土应力特性,试验模拟了地基、CFG桩、树根桩、加筋垫层、防尘网和轨道梁基础、矿石堆载等,分析了超大荷载作用下复合地基表面变形、桩顶轴力、桩间土压力、桩土应力比的变化规律。试验结果表明,复合地基的沉降速率在稳定控制标准之内,沉降量满足堆场使用要求,防尘网基础和轨道梁基础水平位移和沉降均很小,桩土应力比为25.2~43.8,CFG桩网复合地基在350 kPa荷载作用下是稳定安全的,达到了预期加固效果。 展开更多
关键词 CFG桩 复合地基 软土地基 桩土应力 重载码头 离心模型试验
下载PDF
淤积与船舶撞击对高桩码头桩基受力的影响分析
4
作者 徐众和 陈同庆 +1 位作者 张庆河 张金凤 《水利水运工程学报》 CSCD 北大核心 2024年第5期132-141,共10页
中国部分高桩码头下方存在较大的泥沙淤积,且初始设计时并未考虑淤积的影响,较大淤积时淤积土体及船舶撞击会对码头桩基受力产生耦合影响。建立了船舶撞击-上部结构-桩基-土体相互作用的三维有限元数值模型,模拟分析回淤土体和船舶撞击... 中国部分高桩码头下方存在较大的泥沙淤积,且初始设计时并未考虑淤积的影响,较大淤积时淤积土体及船舶撞击会对码头桩基受力产生耦合影响。建立了船舶撞击-上部结构-桩基-土体相互作用的三维有限元数值模型,模拟分析回淤土体和船舶撞击作用对高桩码头桩基受力的影响。结果表明,土体淤积严重位置处的桩顶局部最大主应力、剪力、弯矩相较回淤前均增幅较大,淤积土体对桩基受力的影响十分显著。当法向船舶撞击速度为0.1和0.2 m/s时,船舶撞击力对桩基的影响小于回淤土体的影响。码头不同排架之间的桩基受力存在一定差异。码头后方桩基顶部最为危险,桩基顶部弯矩接近混凝土开裂弯矩,导致桩基容易出现开裂损伤。 展开更多
关键词 淤积 高桩码头 船舶撞击 桩基
下载PDF
淤积条件下码头桩基-岸坡体系受力变形分析
5
作者 任婧毓 王坤鹏 +2 位作者 崔春义 刘海龙 赵敏 《水利水运工程学报》 CSCD 北大核心 2024年第5期113-123,共11页
沿海港口码头常受淤积影响,导致岸坡土体发生位移,进而威胁码头结构安全。结合具体工程建立了码头桩基-淤积岸坡相互作用有限元模型,以内力组合值判定桩基塑性变形状态,与码头桩基开裂轴线实际位置基本相符,验证了建模合理性。在此基础... 沿海港口码头常受淤积影响,导致岸坡土体发生位移,进而威胁码头结构安全。结合具体工程建立了码头桩基-淤积岸坡相互作用有限元模型,以内力组合值判定桩基塑性变形状态,与码头桩基开裂轴线实际位置基本相符,验证了建模合理性。在此基础上,建立了桩-土相互作用简化模型,研究了淤积过程中桩基内力变化及桩-土体系位移演化趋势,分析了工程地质和码头结构方面因素对桩-土体系受力变形特征的影响规律。结果表明,岸坡淤积条件下,码头下方坡体水平位移及后方坡体竖向沉降较为明显;随着淤积土层厚度持续增加,岸坡稳定系数逐渐降低,而水平位移与竖向沉降逐渐增大,且变形量与淤积厚度呈线性关系。淤积过程中,各轴桩基水平位移沿纵向呈现相同变化趋势,而桩身弯矩分布则表现为3种不同模式;土体压缩模量对桩体位移和岸坡变形的影响最为显著,不同位置下影响桩顶弯矩变化的主导因素各异(或为压缩模量或为桩径),而淤积速度对桩-土体系受力变形状态的影响最小。本研究有助于完善岸坡淤积条件下桩-土相互作用理论体系,为工程实践中淤积码头的结构设计和日常维护提供理论支持。 展开更多
关键词 高桩码头 淤积岸坡 码头桩基 桩-土相互作用
下载PDF
回淤环境高桩码头桩基淤积荷载影响因素及简化计算
6
作者 赵敏 蒋腊梅 +1 位作者 陆敏 吴志良 《水利水运工程学报》 CSCD 北大核心 2024年第5期142-149,共8页
目前高含沙水域高桩码头受淤积影响导致码头位移或桩基受损情况较为普遍,工程设计中考虑淤积荷载影响主要以数值有限元分析为主,计算精度与土体参数及土体本构模型选取有关,工程应用较为不便。通过调研高桩码头淤积现状和受损情况,分析... 目前高含沙水域高桩码头受淤积影响导致码头位移或桩基受损情况较为普遍,工程设计中考虑淤积荷载影响主要以数值有限元分析为主,计算精度与土体参数及土体本构模型选取有关,工程应用较为不便。通过调研高桩码头淤积现状和受损情况,分析了桩土作用及影响因子,结果表明桩基淤积荷载主要与淤积土体参数、淤积高度、淤积岸坡坡度及桩基的倾斜角度有关;提出了桩基淤积荷载简化计算方法并应用于典型码头实例分析中,计算分析结果与检测实际情况基本吻合,揭示了码头桩基受损原因。该简化计算方法相比于数值有限元分析方法,所用参数均为常规工程参数,计算简单,能较好反映主要影响因素对淤积荷载的影响,可为回淤环境下高桩码头桩基设计提供参考。 展开更多
关键词 回淤 高桩码头 桩基 淤积荷载 桩土作用
下载PDF
某钢栈桥及水中桩基础施工技术研究
7
作者 李小湘 《价值工程》 2024年第25期54-57,共4页
研究旨在通过深入分析施工过程中的关键环节,寻求提高施工效率、保障工程质量和降低施工成本的方法。通过对钢栈桥及水中桩基础施工技术的研究,提出创新性的施工方案和技术手段,以实现工程施工的高效、安全和可持续发展。结果显示,采用... 研究旨在通过深入分析施工过程中的关键环节,寻求提高施工效率、保障工程质量和降低施工成本的方法。通过对钢栈桥及水中桩基础施工技术的研究,提出创新性的施工方案和技术手段,以实现工程施工的高效、安全和可持续发展。结果显示,采用钢栈桥结合钢平台施工水中桥梁桩基、墩柱、盖梁的方法安全可靠,多墩平行作业,各班组流水作业,提高了施工功效,大大缩短了施工工期,节约了施工成本。研究成果为钢栈桥及水中桩基础施工技术的改进提供了有益参考和借鉴。 展开更多
关键词 钢栈桥 水中 桩基础 施工技术
下载PDF
钢管板组合桩结构特点及施工工艺
8
作者 陈奇 《港口航道与近海工程》 2024年第S01期50-53,共4页
港口码头施工的过程中需要做好板桩码头桩基施工工作,桩基的质量决定着后续工程的施工质量。随着港口建设的不断发展,对码头质量要求逐步增高,传统的板桩结构已不能满足码头结构大型化、深水化的要求,因此钢管板组合桩结构形式逐渐得到... 港口码头施工的过程中需要做好板桩码头桩基施工工作,桩基的质量决定着后续工程的施工质量。随着港口建设的不断发展,对码头质量要求逐步增高,传统的板桩结构已不能满足码头结构大型化、深水化的要求,因此钢管板组合桩结构形式逐渐得到了广泛应用,此类组合在复杂的地质情况下仍能适应,并且具有力学性能好、施工较为简单、工期短和经济效益高等特点。以印度尼西亚锦江码头工程为例,介绍该结构特点及施工工艺。 展开更多
关键词 码头施工 桩基 钢管板组合桩 结构特点 施工工艺
下载PDF
Study on the Embedded Mode of Large Diameter Steel Tube and Concrete Combined Pile
9
作者 XIA Detain 《International English Education Research》 2016年第4期7-9,共3页
As the stiffness discontinuous of large diameter steel tube and concrete combined pile, the complicated stress state is caused by the combination of the pile foundation and the base rock, the steel casing and the bedr... As the stiffness discontinuous of large diameter steel tube and concrete combined pile, the complicated stress state is caused by the combination of the pile foundation and the base rock, the steel casing and the bedrock structure. It is needed to put forward a scientific basis to determine the pile foundation effective depth of embedded. For this purpose, the physical model and the numerical model of single pile with large diameter steel tube and reinforced concrete combined force are established. Through numerical simulation and contrast test of a large number of variable parameters, the various factors that affect the lateral bearing capacity of the embedded piles are discussed in detail, the mechanical properties of the foundation under the action of the steel tube and the pile foundation are obtained. 展开更多
关键词 Inland waterway large water level difference wharf pile foundation steel tube
下载PDF
高桩码头在船舶撞击下的动力响应及损伤分析 被引量:6
10
作者 刘利琴 陈建峰 +1 位作者 罗超 胡文韬 《哈尔滨工程大学学报》 EI CAS CSCD 北大核心 2023年第4期519-526,共8页
针对高桩码头在船舶意外撞击下的损伤问题,本文基于有限元软件ANSYS/LS-DYNA建立了船舶和高桩码头的结构模型,分析了船舶撞击下高桩码头基桩顶部的受力特性,对比分析了不同撞击速度、撞击角度下高桩码头受到的有效应力、撞击力以及基桩... 针对高桩码头在船舶意外撞击下的损伤问题,本文基于有限元软件ANSYS/LS-DYNA建立了船舶和高桩码头的结构模型,分析了船舶撞击下高桩码头基桩顶部的受力特性,对比分析了不同撞击速度、撞击角度下高桩码头受到的有效应力、撞击力以及基桩顶部位移,并依此对基桩损伤进行了判断。研究表明:在船舶撞击下,高桩码头后斜桩受到的压应力较大,前斜桩受到的拉应力较大;高桩码头的动力响应随着船舶撞击速度、撞击角度(锐角)及船舶吨位的增大而增大;当船舶的撞击角度为对称方向时,码头受到的撞击力和有效应力及桩顶最大位移的相对大小取决于船舶滑移过程中船艏与码头的相对运动趋势。 展开更多
关键词 高桩码头 船舶撞击 动力响应 拉压应力 基桩顶部位移 基桩损伤 撞击速度 撞击角度
下载PDF
引孔植桩工艺在深水裸岩码头灌注桩施工中的应用 被引量:4
11
作者 张校强 李琦 许建武 《水运工程》 北大核心 2023年第9期211-215,228,共6页
针对深水裸岩码头灌注桩的施工,无覆盖层导致水上施工平台的辅助钢管桩与灌注桩钢护筒着床困难,以某高桩码头工程为例,进行施工工艺实践研究,提出采用引孔植桩的解决方案。研究结果表明:1)针对水上施工平台搭建难题,可采用平台上冲孔引... 针对深水裸岩码头灌注桩的施工,无覆盖层导致水上施工平台的辅助钢管桩与灌注桩钢护筒着床困难,以某高桩码头工程为例,进行施工工艺实践研究,提出采用引孔植桩的解决方案。研究结果表明:1)针对水上施工平台搭建难题,可采用平台上冲孔引孔、水上船舶旋挖引孔等新工艺,提前对辅助钢管桩桩位进行引孔施工再植桩,并分析各自工艺的特点、适用性、功效及经济性。2)针对钢护筒埋设问题,可采用平台上旋挖引孔后植入的工艺。较好地解决了桩基入土深度问题,确保了灌注桩质量,可为类似工程提供参考。 展开更多
关键词 高桩码头 深水祼岩 灌注桩施工 引孔 植桩
下载PDF
某大型散货码头堆场地基处理方案 被引量:7
12
作者 徐妍彦 刘均卫 +1 位作者 陈娜 魏莱 《长江科学院院报》 CSCD 北大核心 2023年第5期131-138,共8页
为优化码头陆域堆场地基加固处理方案,以长江中下游右岸某大型散货码头堆场地基加固处理为研究对象,根据工程区域地质条件、地坑皮带机廊道基础荷载、堆场承载力,以及地基处理沉降和位移的要求,参照《水运工程地基设计规范》(JTS147-201... 为优化码头陆域堆场地基加固处理方案,以长江中下游右岸某大型散货码头堆场地基加固处理为研究对象,根据工程区域地质条件、地坑皮带机廊道基础荷载、堆场承载力,以及地基处理沉降和位移的要求,参照《水运工程地基设计规范》(JTS147-2017),结合不同桩型特点,两条地坑皮带机廊道之间的散货堆料区(A区)的地基处理采用PHC管桩法与CFG桩法进行比选,其他散货堆料区(B区)地基处理采用水泥土搅拌桩法与碎石桩法进行比选。运用GEO5-岩土工程有限元软件,计算上述4种地基处理不同组合方案下不同运行工况条件(满载、偏载)的地基变形量(沉降量和水平位移),综合考虑工程经济性和施工工期等,确定A区的地基采用CFG桩、其他散货堆料区域地基采用碎石桩。计算结果表明:采用这一组合方案进行地基处理后,A区地基沉降<100 mm、水平位移<10 mm,满足《建筑地基基础设计规范》(GB 50007-2011)要求;B区最大地基沉降为458.6 mm,地基最大水平位移为102.6 mm,满足《港口道路与堆场设计规范》(JTS 168-2017)要求。研究成果可为优化大型散货码头陆域堆场地基处理设计方案提供可靠依据。 展开更多
关键词 地基处理 散货堆场 CFG桩 水泥土搅拌桩 PHC管桩 碎石桩 地基沉降 水平位移
下载PDF
数字化交付在装配式桩基码头全生命周期建设中的应用 被引量:2
13
作者 陆晶晶 《水运工程》 北大核心 2023年第5期167-171,186,共6页
数字化交付是装配式桩基码头数字一体化建设技术实施的重要基础。本文以某装配式码头工程为依托,从装配式码头数字化交付的价值和内容需求出发,提出装配式码头数字化交付平台的架构设计方案,根据其全生命周期建设的特点,给出预制构件的... 数字化交付是装配式桩基码头数字一体化建设技术实施的重要基础。本文以某装配式码头工程为依托,从装配式码头数字化交付的价值和内容需求出发,提出装配式码头数字化交付平台的架构设计方案,根据其全生命周期建设的特点,给出预制构件的数字化编码规则、数据集成与发布以及数据安全等方面的技术实现方案建议,围绕BIM及各种工程文件交付、云端问题沟通与闭环解决、文件分享与归档整理等功能需求给出应用场景示例,实现了装配式码头全生命周期建设各方的数字化交付。 展开更多
关键词 数字化交付 装配式桩基码头 BIM
下载PDF
自平衡法在码头桩基极限承载能力检测中的应用 被引量:3
14
作者 陆志扬 王焱 李强贵 《科技创新与应用》 2023年第22期121-124,共4页
以码头平台Φ1200δ18钢管桩和Φ1200δ150PHC-钢管组合桩为研究对象。该文采用自平衡法进行桩基承载力试验,验证桩基的竖向极限承载力,为同类钢管桩及PHC-钢管桩的桩基施工、设计及检测提供参考和依据。
关键词 静载试验 PHC-钢管组合桩 自平衡法 高桩码头 桩基
下载PDF
装配式桩基码头构件制造与加工数字化技术 被引量:1
15
作者 王世坚 陆晶晶 《水运工程》 北大核心 2023年第5期182-186,共5页
介绍一种基于数字化加工的装配式桩基码头预制构件生产及管理方法。将BIM技术和数字化生产相结合,将整个构件BIM深化设计信息通过数字化的手段传递给构件的预制生产阶段,并基于物联网和互联网将RFID技术、BIM与构件管理系统整合,从而实... 介绍一种基于数字化加工的装配式桩基码头预制构件生产及管理方法。将BIM技术和数字化生产相结合,将整个构件BIM深化设计信息通过数字化的手段传递给构件的预制生产阶段,并基于物联网和互联网将RFID技术、BIM与构件管理系统整合,从而实现数字化、信息化、可视化的装配式桩基码头构件制造与加工管理,确保项目全生命周期预制构件信息传递的准确、及时和有效。 展开更多
关键词 装配式桩基码头 BIM 数字化
下载PDF
山区码头桩基冲刷研究
16
作者 叶茂胜 宋成涛 马未 《港工技术》 2023年第1期11-14,共4页
山区河流水位涨跌迅猛,码头桩基区域出现复杂绕流现象,受涡流运动的影响桩周区域基床随之发生冲刷,进而形成尺寸不一的局部冲刷坑,导致桩基入土深度减小、悬臂端长度增大。本文采用了5种计算公式对某山区码头桩基最大冲刷深度进行计算,... 山区河流水位涨跌迅猛,码头桩基区域出现复杂绕流现象,受涡流运动的影响桩周区域基床随之发生冲刷,进而形成尺寸不一的局部冲刷坑,导致桩基入土深度减小、悬臂端长度增大。本文采用了5种计算公式对某山区码头桩基最大冲刷深度进行计算,结合试验数据发现本工程山区河流环境下桩基局部冲刷坑最大深度的预测采用65-1式可行。 展开更多
关键词 码头 桩基 局部冲刷 深度
下载PDF
平果那茂码头一期主体工程桩基施工技术研究
17
作者 张智丽 韦纯 《建筑与装饰》 2023年第4期150-152,共3页
随着我国改革开放的高速发展,港口码头也进入了全面建设阶段,港口码头的建设对我国水运发展起着至关重要的作用.板梁式高桩码头是高桩码头的主要形式之一,在近年研究发现,在使用过程中出现了多种影响码头正常使用,甚至不能使用等问题.... 随着我国改革开放的高速发展,港口码头也进入了全面建设阶段,港口码头的建设对我国水运发展起着至关重要的作用.板梁式高桩码头是高桩码头的主要形式之一,在近年研究发现,在使用过程中出现了多种影响码头正常使用,甚至不能使用等问题.本文主要对平果县那茂码头桩基施工方式以及常见的技术问题进行探究分析. 展开更多
关键词 高桩码头桩基 施工技术 施工 码头主体工程
下载PDF
高桩码头桩基在倾斜泥面中的水平承载性能研究 被引量:26
18
作者 刘兹胜 卓杨 +1 位作者 时蓓玲 周国然 《岩土工程学报》 EI CAS CSCD 北大核心 2010年第12期1861-1867,共7页
现有的高桩码头设计方法在进行桩基水平承载力计算时通常是基于普通天然地基的水平泥面假设,而对泥面倾斜情况下,桩基的水平承载力计算至今没有一套成熟的计算方法可循。为揭示高桩码头排架在斜坡面上的工作机理,通过室内模型试验系统... 现有的高桩码头设计方法在进行桩基水平承载力计算时通常是基于普通天然地基的水平泥面假设,而对泥面倾斜情况下,桩基的水平承载力计算至今没有一套成熟的计算方法可循。为揭示高桩码头排架在斜坡面上的工作机理,通过室内模型试验系统研究了单桩在斜坡面上的水平承载特性。通过对室内模型试验结果分析,提出了基于泥面水平时桩基水平受力性能来确定不同泥面坡度下桩的水平承载性能的修正计算公式,包括桩身最大弯矩、桩身最大弯矩点位置、桩顶位移、泥面位移以及考虑泥面坡度和桩深度的土弹簧刚度修正公式,为处于倾斜泥面的高桩码头桩基设计计算提供了理论依据。 展开更多
关键词 高桩码头 桩基 倾斜泥面 水平承载性能
下载PDF
高桩码头安全评估中桩身完整性检测比例的探讨 被引量:9
19
作者 陈灿明 苏晓栋 +2 位作者 何建新 胡烨之 黄卫兰 《水道港口》 2017年第3期269-273,共5页
在役高桩码头检测评估中桩身完整性是必测项目,根据现行水运行业标准一般采用低应变反射波法,抽检数量不少于桩总数的10%或20%,且不得少于10根,当检测发现缺陷桩时,应扩大桩的抽检比例。根据多年在役高桩码头安全检测评估、尤其是交通... 在役高桩码头检测评估中桩身完整性是必测项目,根据现行水运行业标准一般采用低应变反射波法,抽检数量不少于桩总数的10%或20%,且不得少于10根,当检测发现缺陷桩时,应扩大桩的抽检比例。根据多年在役高桩码头安全检测评估、尤其是交通运输部开展码头靠泊能力核查和沿海港口码头结构加固改造工作中遇到的问题,通过现行水运工程和相关行业规范的对比分析,结合桩基完整性检测割桩损伤对码头水平承载力影响计算结果,探讨了桩基完整性检测抽样比例的合理性。提出在役高桩码头安全检测应以码头桩基施工质量合格为基础,以排除运行过程中产生的安全隐患为目的。安全检测时只需考虑在役高桩码头运行年限、靠泊方式、运行环境、异常靠泊率和结构型式等运行因素,选择较不利受力以及外观检查中桩基完整性存疑的桩基作为对象进行验证检测。 展开更多
关键词 在役高桩码头 桩基完整性 检测 评估 比例
下载PDF
某高桩码头桩基受力有限元分析及结构损伤研究 被引量:10
20
作者 赵安平 李昊洁 +1 位作者 俞红升 肖为民 《长江科学院院报》 CSCD 北大核心 2016年第9期128-132,137,共6页
为研究高桩码头桩基受力及结构损伤,对某高桩码头3类典型断面进行有限元数值模拟,并对基桩进行承载力计算分析;之后,将数值模拟结果与现场桩基结构损伤检测结果作比较,二者吻合较好,从而验证了理论分析的正确性,并最终给出受损部位的加... 为研究高桩码头桩基受力及结构损伤,对某高桩码头3类典型断面进行有限元数值模拟,并对基桩进行承载力计算分析;之后,将数值模拟结果与现场桩基结构损伤检测结果作比较,二者吻合较好,从而验证了理论分析的正确性,并最终给出受损部位的加固措施。根据基桩承载力有限元分析及实测结果,可以断定基桩顶部(距桩帽下方1-2m)为最易受损部位;对于码头3种断面类型,应尽量避免使用断面1、断面2的形式,原因是这2类断面的水平承载力太小,极易受水平力作用而在使用过程中发生损坏;提出2种加固基桩受损部位的措施,增大桩帽截面法和钢抱箍法,但在具体修复时,应根据实际情况在考虑时间因素、经济效益的前提下,认真总结比较这2种措施的优缺点,灵活选用修复措施,对桩基受损部位进行妥善处理。 展开更多
关键词 桩基工程 高桩码头 有限单元法 结构损伤 承载力分析 加固措施