Most power transfer studies involve contingencies and multi pattern scenarios that often can only be performed in reasonable time with the use of linear methods. In these works, the effect of reactive power flows in l...Most power transfer studies involve contingencies and multi pattern scenarios that often can only be performed in reasonable time with the use of linear methods. In these works, the effect of reactive power flows in line loading is neglected while formulating the problem for ATC (available transfer capability) calculations. This paper presents the determination of shunt reactive power compensation in the presence of FACTS (flexible AC transmission system) devices like: SSSC (static synchronous series compensator) and UPFC (unified power flow controller) for enhancement of power transfer capability of a power system incorporating the reactive power flows in ATC calculations. In doing so, redistribution of power flow takes place and therefore improves ATC of the system. Studies on a sample 5-bus power system model are carried out to illustrate the effect of shunt compensation along with line flow control.展开更多
混合型潮流控制器(hybrid power flow controller,HPFC)可以有效解决风电并网系统中存在的支路潮流过载问题,且相较于统一潮流控制器成本更低。针对现有的HPFC潮流优化研究尚未计及支路潮流最大值约束和风电不确定性的问题,提出一种基...混合型潮流控制器(hybrid power flow controller,HPFC)可以有效解决风电并网系统中存在的支路潮流过载问题,且相较于统一潮流控制器成本更低。针对现有的HPFC潮流优化研究尚未计及支路潮流最大值约束和风电不确定性的问题,提出一种基于场景削减的含HPFC风电并网系统最优潮流模型。首先,建立HPFC的功率注入模型,并推导了注入功率表达式;其次,采用K均值算法削减风电、负荷概率场景,通过CH(+)指标选择最优场景集合;最后,建立兼顾发电机运行成本、系统网络损耗、正常运行及N-1故障下的支路负载率的多目标优化模型,采用多目标粒子群优化(multi-objective particle swarm optimization,MOPSO)算法进行求解,利用模糊满意度函数在Pareto解集中筛选出折衷解。在MATLAB中仿真验证所提方法的有效性,结果表明该方法可以计及风电不确定性,保证电网在不同场景下的安全经济运行。展开更多
考虑风电场出力及负荷预测的不确定性,利用机会约束思想建立了含风电场的电网规划模型。以线路投资费用最少为规划目标,采用基于Monte Carlo模拟的直流概率潮流判断规划方案是否违反支路功率约束。同时把风电场并网公共连接点(point of ...考虑风电场出力及负荷预测的不确定性,利用机会约束思想建立了含风电场的电网规划模型。以线路投资费用最少为规划目标,采用基于Monte Carlo模拟的直流概率潮流判断规划方案是否违反支路功率约束。同时把风电场并网公共连接点(point of common coupling,PCC)处的电压闪变水平作为规划目标加入目标函数中。利用基本遗传算法(genetic algorithm,GA)对规划模型进行了求解。基于Garver6节点系统的仿真结果表明:可以在不显著增加电网投资的情况下,大幅度降低PCC处的电压闪变水平。展开更多
针对传统机组组合研究中因模型不够完善、约束过于简化而引起的计算准确度低和系统安全性差的缺陷,建立了考虑潮流方程和水电精确出力的水火机组组合(hydrothermal unit commitment,HTUC)模型。围绕该模型,文中首先采用广义Benders分解...针对传统机组组合研究中因模型不够完善、约束过于简化而引起的计算准确度低和系统安全性差的缺陷,建立了考虑潮流方程和水电精确出力的水火机组组合(hydrothermal unit commitment,HTUC)模型。围绕该模型,文中首先采用广义Benders分解算法将其划分为一个混合整数线性规划主问题和一个非线性规划子问题;然后将该子问题按时段进一步分解为T个规模较小的子问题,T为调度周期。其中,主问题对应于传统的水火联合调度(hydrothermal scheduling,HTS),子问题则是包含电压、无功等变量的约束潮流(constrained power flow,CPF)。主子问题之间通过可行割进行协调,并以交替迭代的方式获得原问题的解。最后对含有46台火电机组、8个梯级水电厂的IEEE 118节点系统进行计算,测试结果表明所提算法能在较少的时间内获得高质量的解,从而为大规模机组组合问题的求解提供参考。展开更多
提出了考虑频率特性和断面传输有功功率约束的潮流模型。该模型在考虑频率电压调节特性的潮流方程基础上,增加了断面传输有功功率方程,并对互联区域两端的平衡机组增加了有功调节变量及其控制方程。其中,平衡机组的调节功率等于其所在...提出了考虑频率特性和断面传输有功功率约束的潮流模型。该模型在考虑频率电压调节特性的潮流方程基础上,增加了断面传输有功功率方程,并对互联区域两端的平衡机组增加了有功调节变量及其控制方程。其中,平衡机组的调节功率等于其所在控制区的区域控制偏差(area control error,ACE)、有功网损偏差和超短期预测有功负荷偏差之和。通过对IEEE 118节点测试系统的仿真分析,验证了新模型的必要性和有效性,同时结果也表明所建模型能够有效提高频率和断面传输有功的控制水平。展开更多
文摘Most power transfer studies involve contingencies and multi pattern scenarios that often can only be performed in reasonable time with the use of linear methods. In these works, the effect of reactive power flows in line loading is neglected while formulating the problem for ATC (available transfer capability) calculations. This paper presents the determination of shunt reactive power compensation in the presence of FACTS (flexible AC transmission system) devices like: SSSC (static synchronous series compensator) and UPFC (unified power flow controller) for enhancement of power transfer capability of a power system incorporating the reactive power flows in ATC calculations. In doing so, redistribution of power flow takes place and therefore improves ATC of the system. Studies on a sample 5-bus power system model are carried out to illustrate the effect of shunt compensation along with line flow control.
文摘考虑风电场出力及负荷预测的不确定性,利用机会约束思想建立了含风电场的电网规划模型。以线路投资费用最少为规划目标,采用基于Monte Carlo模拟的直流概率潮流判断规划方案是否违反支路功率约束。同时把风电场并网公共连接点(point of common coupling,PCC)处的电压闪变水平作为规划目标加入目标函数中。利用基本遗传算法(genetic algorithm,GA)对规划模型进行了求解。基于Garver6节点系统的仿真结果表明:可以在不显著增加电网投资的情况下,大幅度降低PCC处的电压闪变水平。
文摘针对传统机组组合研究中因模型不够完善、约束过于简化而引起的计算准确度低和系统安全性差的缺陷,建立了考虑潮流方程和水电精确出力的水火机组组合(hydrothermal unit commitment,HTUC)模型。围绕该模型,文中首先采用广义Benders分解算法将其划分为一个混合整数线性规划主问题和一个非线性规划子问题;然后将该子问题按时段进一步分解为T个规模较小的子问题,T为调度周期。其中,主问题对应于传统的水火联合调度(hydrothermal scheduling,HTS),子问题则是包含电压、无功等变量的约束潮流(constrained power flow,CPF)。主子问题之间通过可行割进行协调,并以交替迭代的方式获得原问题的解。最后对含有46台火电机组、8个梯级水电厂的IEEE 118节点系统进行计算,测试结果表明所提算法能在较少的时间内获得高质量的解,从而为大规模机组组合问题的求解提供参考。
文摘提出了考虑频率特性和断面传输有功功率约束的潮流模型。该模型在考虑频率电压调节特性的潮流方程基础上,增加了断面传输有功功率方程,并对互联区域两端的平衡机组增加了有功调节变量及其控制方程。其中,平衡机组的调节功率等于其所在控制区的区域控制偏差(area control error,ACE)、有功网损偏差和超短期预测有功负荷偏差之和。通过对IEEE 118节点测试系统的仿真分析,验证了新模型的必要性和有效性,同时结果也表明所建模型能够有效提高频率和断面传输有功的控制水平。