The traditional way of installing large vessels has always been to employ the use of cranes. The Water Handling Debottlenecking Project team has, instead, made use of a different technology—employing a Self-Propelled...The traditional way of installing large vessels has always been to employ the use of cranes. The Water Handling Debottlenecking Project team has, instead, made use of a different technology—employing a Self-Propelled Modular Transporter (SPMT) to install nine vessels in situ. These SPMT units have many advantages over crane installations, such as safety and efficiency, not to mention lower costs due to their self-propelled capabilities.展开更多
Transportation of floating structures for long distance has always been associated with the use of heavy semi transport vessel. The requirements of this type of vessel are always special, and its availability is limit...Transportation of floating structures for long distance has always been associated with the use of heavy semi transport vessel. The requirements of this type of vessel are always special, and its availability is limited. To prepare for the future development of the South China Sea deepwater projects, COOEC has recently built a heavy lift transport vessel - Hai Yang Shi You 278 (HYSY278). This semi-submersible vessel has displacement capacity of 50k DWT, and a breath of 42 m. Understanding the vessel's applicability and preparing its use for future deepwater projects are becoming imminent need. This paper reviews the critical issues associated with the floating structure transportation and performs detailed analysis of two designed floating structures during transportation. The newly built COOEC transportation vessel HYSY278 will be used to dry transport the floating structures from COOEC fabrication yard in Qingdao to the oil field in the South China Sea. The entire process will start with load-out/float-offthe floating structures from the construction sites, offload the platform from the vessel if needed, dry transport floating structures through a long distance, and finally offload the platform. Both hydrodynamic and struc^tral analyses are performed to evaluate transport vessel and floating structures. Critical issues associated with the transportation and offloading of platform from the vessel will be studied in detail. Detailed study is performed to evaluate the response of the system during this phase and additional work needed to make the vessel feasible for use of this purpose. The results demonstrate that with proper modifications, HYSY278 can effectively be used for transporting structures with proper arrangement and well-prepared operation. The procedure and details are presented on the basis of study results. Special attentions associated with future use will also be discussed based on the results from analysis.展开更多
文摘The traditional way of installing large vessels has always been to employ the use of cranes. The Water Handling Debottlenecking Project team has, instead, made use of a different technology—employing a Self-Propelled Modular Transporter (SPMT) to install nine vessels in situ. These SPMT units have many advantages over crane installations, such as safety and efficiency, not to mention lower costs due to their self-propelled capabilities.
基金funded by the State Key Project "Installation Technical Study for Deepwater Floating Structure"
文摘Transportation of floating structures for long distance has always been associated with the use of heavy semi transport vessel. The requirements of this type of vessel are always special, and its availability is limited. To prepare for the future development of the South China Sea deepwater projects, COOEC has recently built a heavy lift transport vessel - Hai Yang Shi You 278 (HYSY278). This semi-submersible vessel has displacement capacity of 50k DWT, and a breath of 42 m. Understanding the vessel's applicability and preparing its use for future deepwater projects are becoming imminent need. This paper reviews the critical issues associated with the floating structure transportation and performs detailed analysis of two designed floating structures during transportation. The newly built COOEC transportation vessel HYSY278 will be used to dry transport the floating structures from COOEC fabrication yard in Qingdao to the oil field in the South China Sea. The entire process will start with load-out/float-offthe floating structures from the construction sites, offload the platform from the vessel if needed, dry transport floating structures through a long distance, and finally offload the platform. Both hydrodynamic and struc^tral analyses are performed to evaluate transport vessel and floating structures. Critical issues associated with the transportation and offloading of platform from the vessel will be studied in detail. Detailed study is performed to evaluate the response of the system during this phase and additional work needed to make the vessel feasible for use of this purpose. The results demonstrate that with proper modifications, HYSY278 can effectively be used for transporting structures with proper arrangement and well-prepared operation. The procedure and details are presented on the basis of study results. Special attentions associated with future use will also be discussed based on the results from analysis.