This paper investigates the influence of the deviation in freeze pipe installation on the development of the frozen wall in long cross passages by numerical simulation with ANSYS software.The study case is from the ar...This paper investigates the influence of the deviation in freeze pipe installation on the development of the frozen wall in long cross passages by numerical simulation with ANSYS software.The study case is from the artificial ground freezing project along the Fuzhou Metro Line 2 between Ziyang Station and Wuliting Station.Two freezepipe configurations,i.e.,one with perfectly aligned pipes without any deviation from design and another with randomly distributed deviation,are included for comparison.The effect of the random deviation in the freeze pipes on frozen wall interconnection time,the thickness of the frozen wall and the development of the temperature field is explored.For the characteristic section of the numerical model at a depth of 25 m,it is found that the frozen wall interconnection time under the random deviation case and no deviation case is 24 days and 18 days,respectively.The difference in the thickness of the thinnest frozen wall segment between the random deviation and no deviation cases is the largest in the early freezing stage(up to 0.75 m),which decreases with time to 0.31 m in the late freezing stage.The effects of random deviation are more significant in the early freezing stage and diminish as the freezing time increases.展开更多
To determine the appropriate soft foundation treatment for a river-crossing tunnel, freezing reinforcement design and technology were introduced based on the channel tunnel design and construction practice. Through fi...To determine the appropriate soft foundation treatment for a river-crossing tunnel, freezing reinforcement design and technology were introduced based on the channel tunnel design and construction practice. Through finite element analysis and engineering practices, two rows of horizontal perforated freezing pipes were designed and installed on both sides of a passage for tunnel rein- forcement, which produced the thickness and strength of frozen crust that satisfied the design requirements. These information are valuable for guiding the design and construction of river-crossing tunnels in coastal areas.展开更多
Based on the engineering background of the contact channel between Shangyang and Gushan of Fuzhou Metro Line 2 undercrossing the existing tunnel line,the freezing temperature field of the contact channel,the displacem...Based on the engineering background of the contact channel between Shangyang and Gushan of Fuzhou Metro Line 2 undercrossing the existing tunnel line,the freezing temperature field of the contact channel,the displacement field of the existing tunnel line and the contact channel with different net distances and horizontal angles are analyzed by ANSYS finite element software and field measurement method.The obtained results indicate that during the freezing period,the temperature drops at different measuring holes are almost the same.The temperature near the bottom freezing tube drops faster than that far from the tube.It is found that the bilateral freezing technique improves the formation of the freezing wall in the intersection area.In this case,the intersection time of the cross-section is 7 days faster than that of the adjacent ordinary section.The change curve of the displacement of the surface uplift in different freezing periods with the distance from the center of the channel is“M”shaped.The maximum uplift displacement at 12 m from channel center is 25 mm.The vertical displacement of the measuring point located above the central axis of the connecting channel is large.The farther the point from the central axis,the smaller the corresponding vertical displacement.When the horizontal angle between the existing tunnel and the connecting channel is less than 60,the existing vertical displacement of the tunnel changes rapidly with the horizontal angle,reaching 0.17 mm/.Meanwhile,when the net distance is less than 6.1 m,the change rate of the vertical displacement of the tunnel is up to 2.4 mm/m.展开更多
基金This research was supported by the project of Natural Science Foundation of Fujian Province(No.2022J01925)supported by the project of the Fuzhou Science and Technology Plan Project(2021-P-047)supported by the Open Project Program Foundation of Engineering Research Center of underground mine construction,Ministry of Education(Anhui University of Science and Technology)(No.JYBGCZX2021104).
文摘This paper investigates the influence of the deviation in freeze pipe installation on the development of the frozen wall in long cross passages by numerical simulation with ANSYS software.The study case is from the artificial ground freezing project along the Fuzhou Metro Line 2 between Ziyang Station and Wuliting Station.Two freezepipe configurations,i.e.,one with perfectly aligned pipes without any deviation from design and another with randomly distributed deviation,are included for comparison.The effect of the random deviation in the freeze pipes on frozen wall interconnection time,the thickness of the frozen wall and the development of the temperature field is explored.For the characteristic section of the numerical model at a depth of 25 m,it is found that the frozen wall interconnection time under the random deviation case and no deviation case is 24 days and 18 days,respectively.The difference in the thickness of the thinnest frozen wall segment between the random deviation and no deviation cases is the largest in the early freezing stage(up to 0.75 m),which decreases with time to 0.31 m in the late freezing stage.The effects of random deviation are more significant in the early freezing stage and diminish as the freezing time increases.
文摘To determine the appropriate soft foundation treatment for a river-crossing tunnel, freezing reinforcement design and technology were introduced based on the channel tunnel design and construction practice. Through finite element analysis and engineering practices, two rows of horizontal perforated freezing pipes were designed and installed on both sides of a passage for tunnel rein- forcement, which produced the thickness and strength of frozen crust that satisfied the design requirements. These information are valuable for guiding the design and construction of river-crossing tunnels in coastal areas.
基金This research was supported by the project of Natural Science Foundation of Fujian Province(No.2022J01925)supported by the project of the Fuzhou Science and Technology Plan Project(2021-P-047)supported by the Open Project Program Foundation of Engineering Research Center of underground mine construction,Ministry of Education(Anhui University of Science and Technology)(No.JYBGCZX2021104).
文摘Based on the engineering background of the contact channel between Shangyang and Gushan of Fuzhou Metro Line 2 undercrossing the existing tunnel line,the freezing temperature field of the contact channel,the displacement field of the existing tunnel line and the contact channel with different net distances and horizontal angles are analyzed by ANSYS finite element software and field measurement method.The obtained results indicate that during the freezing period,the temperature drops at different measuring holes are almost the same.The temperature near the bottom freezing tube drops faster than that far from the tube.It is found that the bilateral freezing technique improves the formation of the freezing wall in the intersection area.In this case,the intersection time of the cross-section is 7 days faster than that of the adjacent ordinary section.The change curve of the displacement of the surface uplift in different freezing periods with the distance from the center of the channel is“M”shaped.The maximum uplift displacement at 12 m from channel center is 25 mm.The vertical displacement of the measuring point located above the central axis of the connecting channel is large.The farther the point from the central axis,the smaller the corresponding vertical displacement.When the horizontal angle between the existing tunnel and the connecting channel is less than 60,the existing vertical displacement of the tunnel changes rapidly with the horizontal angle,reaching 0.17 mm/.Meanwhile,when the net distance is less than 6.1 m,the change rate of the vertical displacement of the tunnel is up to 2.4 mm/m.