It is very difficult to estimate exact values of time and cost of an activity in project scheduling process because many uncertain factors, such as weather, productivity level, human factors etc. , dynamically affect ...It is very difficult to estimate exact values of time and cost of an activity in project scheduling process because many uncertain factors, such as weather, productivity level, human factors etc. , dynamically affect them during project implementation process. A GAs-based fully fuzzy optimal time-cost trade-off model is presented based on fuzzy sets and genetic algorithms (GAs). In tihs model all parameters and variables are characteristics by fuzzy numbers. And then GAs is adopted to search for the optimal solution to this model. The method solves the time-cost trade-off problems under an uncertain environment and is proved practicable through a giving example in ship building scheduling.展开更多
Time-cost trade off problem (TCTP), known in the literature as project crashing problem (PCP) and project speeding up problem (PSP) is a part of project management in planning phase. In this problem, determining the o...Time-cost trade off problem (TCTP), known in the literature as project crashing problem (PCP) and project speeding up problem (PSP) is a part of project management in planning phase. In this problem, determining the optimal levels of activity durations and activity costs which satisfy the project goal(s), leads to a balance between the project completion time and the project total cost. A large amount of literature has studied this problem under various behavior of cost function. But, in all of them, influence of discount has not been in-vestigated. Hence, in this paper, TCTP would be studied considering the influence of discount on the re-source price, using genetic algorithm (GA). The performance of proposed idea has been tested on a medium scale test problem and several computational experiments have been conducted to investigate the appropriate levels of proposed GA considering accuracy and computational time.展开更多
基金Supported by the National High-Tech. R&D Program for CIMS (NO. 2003AA414060).
文摘It is very difficult to estimate exact values of time and cost of an activity in project scheduling process because many uncertain factors, such as weather, productivity level, human factors etc. , dynamically affect them during project implementation process. A GAs-based fully fuzzy optimal time-cost trade-off model is presented based on fuzzy sets and genetic algorithms (GAs). In tihs model all parameters and variables are characteristics by fuzzy numbers. And then GAs is adopted to search for the optimal solution to this model. The method solves the time-cost trade-off problems under an uncertain environment and is proved practicable through a giving example in ship building scheduling.
文摘Time-cost trade off problem (TCTP), known in the literature as project crashing problem (PCP) and project speeding up problem (PSP) is a part of project management in planning phase. In this problem, determining the optimal levels of activity durations and activity costs which satisfy the project goal(s), leads to a balance between the project completion time and the project total cost. A large amount of literature has studied this problem under various behavior of cost function. But, in all of them, influence of discount has not been in-vestigated. Hence, in this paper, TCTP would be studied considering the influence of discount on the re-source price, using genetic algorithm (GA). The performance of proposed idea has been tested on a medium scale test problem and several computational experiments have been conducted to investigate the appropriate levels of proposed GA considering accuracy and computational time.