Model test studies based on the similarity theory were conducted to investigate vibration effect and damage evolution characteristics of tunnel surrounding rock under push-type cyclic blasting excavation.The model was...Model test studies based on the similarity theory were conducted to investigate vibration effect and damage evolution characteristics of tunnel surrounding rock under push-type cyclic blasting excavation.The model was constructed with a ratio of 1∶15.By simulating the tunnel excavation of push-type cyclic blasting,the influence of the blasting parameter change on vibration effect was explored.The damage degree of tunnel surrounding rock was evaluated by the change of the acoustic wave velocity at the same measuring point after blasting.The relationship between the damage evolution of surrounding rock and blasting times was established.The research results show that:(1)In the same geological environment,the number of delay initiation is larger,the main vibration frequency of blasting seismic wave is higher,and the attenuation of high frequency signal in the rock and soil is faster.The influence of number of delay initiation on blasting vibration effect cannot be ignored;(2)Under push-type cyclic blasting excavation,there were great differences in the decreasing rates of acoustic wave velocity of the measuring points which have the same distance to the blasting region at the same depth,and the blasting damage ranges of surrounding rock were typically anisotropic at both depth and breadth;(3)When blasting parameters were basically kept as the same,the growth trend of the cumulative acoustic wave velocity decreasing rate at the measuring point was nonlinear under different cycle blasting excavations;(4)There were nonlinear evolution characteristics between the blasting cumulative damage(D)of surrounding rock and blasting times(n)under push-type cyclic blasting loading,and different measuring points had corresponding blasting cumulative damage propagation models,respectively.The closer the measuring point was away from the explosion source,the faster the cumulative damage extension.Blasting cumulative damage effect of surrounding rock had typically nonlinear evolution properties and anisotropic characteristics.展开更多
Numerical analysis of the total energy release of surrounding rocks excavated by drill-and-blast (D&B) method and tunnel boring machine (TBM) method is presented in the paper. The stability of deep tunnels during...Numerical analysis of the total energy release of surrounding rocks excavated by drill-and-blast (D&B) method and tunnel boring machine (TBM) method is presented in the paper. The stability of deep tunnels during excavation in terms of energy release is also discussed. The simulation results reveal that energy release during blasting excavation is a dynamic process. An intense dynamic effect is captured at large excavation footage. The magnitude of energy release during full-face excavation with D&B method is higher than that with TBM method under the same conditions. The energy release rate (ERR) and speed (ERS) also have similar trends. Therefore, the rockbursts in tunnels excavated by D&B method are frequently encountered and more intensive than those by TBM method. Since the space after tunnel face is occupied by the backup system of TBM, prevention and control of rockbursts are more difficult. Thus, rockbursts in tunnels excavated by TBM method with the same intensity are more harmful than those in tunnels by D&B method. Reducing tunneling rate of TBM seems to be a good means to decrease ERR and risk of rockburst. The rockbursts observed during excavation of headrace tunnels at Jinping II hydropower station in West China confirm the analytical results obtained in this paper.展开更多
Time interval of short delay ignition is an important factor to affect theefficiency of blasting cuts. The motion process of rock pieces in the cut cavity is analyzed, amechanical model to calculate the delay time of ...Time interval of short delay ignition is an important factor to affect theefficiency of blasting cuts. The motion process of rock pieces in the cut cavity is analyzed, amechanical model to calculate the delay time of parallel hole cuts is presented for tunnel blasting,and a theoretical method to determine the volume ratio (the clearage rate) of the rock pieceswithin the cut cavity at different moments is proposed for the blasting cut with an empty hole.Numerical analysis results show that the optimal delay interval is proportional to the boreholedepth. The suggested results are of practical value to the optimal design of the delay interval inmillisecond blasting related to the parallel hole cuts with an empty hole.展开更多
It is well known that the overbreak caused by the blasting damage during tunnel excavation increases costs associated with filling the collapsed area with shotcrete and results in filing of a claim by the contractor. ...It is well known that the overbreak caused by the blasting damage during tunnel excavation increases costs associated with filling the collapsed area with shotcrete and results in filing of a claim by the contractor. This paper outlines a new approach for prediction the overbreak depth during tunnel construction. Hence, firstly excavation damage zone(EDZ) are determined by average specific charge in each zone. Numerical modelling is used to simulate the EDZ around tunnel boundary and the overbreak depth are calculated by the rock strength factor. The predicted overbreak depth compared with observed field data from a case study. The results show that there exists an approximately up to 40% difference between the prediction and the observed volume of overbreak depth. Therefore, the method can be well used to predict the overbreak depth to estimate more precision of shotcrete and concrete volumes in tunnelling cost during design phase.展开更多
基金Supported by the National Natural Science Foundation of China(51064009,51464015)the Natural Science Foundation of Guangdong Province of China(2016A030313121)+1 种基金the Higher School Talent Introduction Project of Guangdong Province(A413.0210)the Science and Technology Project of Huizhou City of Guangdong Province of China(2014B020004018)
文摘Model test studies based on the similarity theory were conducted to investigate vibration effect and damage evolution characteristics of tunnel surrounding rock under push-type cyclic blasting excavation.The model was constructed with a ratio of 1∶15.By simulating the tunnel excavation of push-type cyclic blasting,the influence of the blasting parameter change on vibration effect was explored.The damage degree of tunnel surrounding rock was evaluated by the change of the acoustic wave velocity at the same measuring point after blasting.The relationship between the damage evolution of surrounding rock and blasting times was established.The research results show that:(1)In the same geological environment,the number of delay initiation is larger,the main vibration frequency of blasting seismic wave is higher,and the attenuation of high frequency signal in the rock and soil is faster.The influence of number of delay initiation on blasting vibration effect cannot be ignored;(2)Under push-type cyclic blasting excavation,there were great differences in the decreasing rates of acoustic wave velocity of the measuring points which have the same distance to the blasting region at the same depth,and the blasting damage ranges of surrounding rock were typically anisotropic at both depth and breadth;(3)When blasting parameters were basically kept as the same,the growth trend of the cumulative acoustic wave velocity decreasing rate at the measuring point was nonlinear under different cycle blasting excavations;(4)There were nonlinear evolution characteristics between the blasting cumulative damage(D)of surrounding rock and blasting times(n)under push-type cyclic blasting loading,and different measuring points had corresponding blasting cumulative damage propagation models,respectively.The closer the measuring point was away from the explosion source,the faster the cumulative damage extension.Blasting cumulative damage effect of surrounding rock had typically nonlinear evolution properties and anisotropic characteristics.
基金Supported by the National Key Basic Research and Development Program of China (2010CB732003)the National Natural Science Foundation of China (51009013,50909077)
文摘Numerical analysis of the total energy release of surrounding rocks excavated by drill-and-blast (D&B) method and tunnel boring machine (TBM) method is presented in the paper. The stability of deep tunnels during excavation in terms of energy release is also discussed. The simulation results reveal that energy release during blasting excavation is a dynamic process. An intense dynamic effect is captured at large excavation footage. The magnitude of energy release during full-face excavation with D&B method is higher than that with TBM method under the same conditions. The energy release rate (ERR) and speed (ERS) also have similar trends. Therefore, the rockbursts in tunnels excavated by D&B method are frequently encountered and more intensive than those by TBM method. Since the space after tunnel face is occupied by the backup system of TBM, prevention and control of rockbursts are more difficult. Thus, rockbursts in tunnels excavated by TBM method with the same intensity are more harmful than those in tunnels by D&B method. Reducing tunneling rate of TBM seems to be a good means to decrease ERR and risk of rockburst. The rockbursts observed during excavation of headrace tunnels at Jinping II hydropower station in West China confirm the analytical results obtained in this paper.
基金This work was financially supported by the National Natural Science Foundation of China (No. 59974019)
文摘Time interval of short delay ignition is an important factor to affect theefficiency of blasting cuts. The motion process of rock pieces in the cut cavity is analyzed, amechanical model to calculate the delay time of parallel hole cuts is presented for tunnel blasting,and a theoretical method to determine the volume ratio (the clearage rate) of the rock pieceswithin the cut cavity at different moments is proposed for the blasting cut with an empty hole.Numerical analysis results show that the optimal delay interval is proportional to the boreholedepth. The suggested results are of practical value to the optimal design of the delay interval inmillisecond blasting related to the parallel hole cuts with an empty hole.
文摘It is well known that the overbreak caused by the blasting damage during tunnel excavation increases costs associated with filling the collapsed area with shotcrete and results in filing of a claim by the contractor. This paper outlines a new approach for prediction the overbreak depth during tunnel construction. Hence, firstly excavation damage zone(EDZ) are determined by average specific charge in each zone. Numerical modelling is used to simulate the EDZ around tunnel boundary and the overbreak depth are calculated by the rock strength factor. The predicted overbreak depth compared with observed field data from a case study. The results show that there exists an approximately up to 40% difference between the prediction and the observed volume of overbreak depth. Therefore, the method can be well used to predict the overbreak depth to estimate more precision of shotcrete and concrete volumes in tunnelling cost during design phase.